|
Return
to Agenda
ITEM EN8
COPY
EXECUTIVE
– 7 JANUARY 2003
Rail Projects
Report
by Director of Environmental Services
Introduction
- The objective
of this report is to 1) inform the Executive of progress with the key
rail projects undertaken in the past twelve months and; 2) review and
approve a list of rail aspirations compiled by the Rail Development
Officer and Parish representatives.
- In April 2000,
the former Public Transport Sub-Committee agreed a list of aspirations
for passenger rail in the county, and officers have used the list that
was approved to guide them when dealing with rail related issues. However,
in the past the County Council was not best able to promote its aspirations
as various officers in the public transport team dealt with rail in
addition to their main work. In April 2002, the post of Rail Development
Officer was created to enable the County Council to take a more proactive
role in its relationship with the rail industry.
- I am proposing
to submit an annual report to the Executive. This will review progress
of the rail projects during the previous twelve months; review, and
where necessary update, the rail aspirations list and; establish priorities
for the coming twelve month period, that can then feed into the allocation
of council finance. This is the first such report.
- So that the Executive
can give due consideration to the contents of this report, I have provided
some background information about the rail industry in Annex
1. The structure of the rail industry is in
a period of great change, and there is considerable uncertainty about
how this will effectaffect services in Oxfordshire over the next few
years.
Consultation
with Parish Councils
- During the preparation
of this report, contact was made with each Parish Council and Parish
Transport Representative and they were given the opportunity to submit
comments and provide a measure of the important local issues. I would
like to place on record my thanks to all of those who took the time
to respond.
- There werehave
been a total of 56 responses from parishes to date. Where parishes expressed
support for a particular project I have identified these within Annex
2. Some parishes also suggested new aspirations
that they would like members to consider and these are included in Part
D of Annex 2. Th ere was 1 response
that supported all the aspirations put forward in the consultation and
this came from Abingdon Parish Council. Copies of all responses have
been provided in the Members Resource Centre.
Key Rail
Projects and Future Aspirations
- The list of rail
aspirations that I am asking the Executive to consider has been compiled
from a number of sources. The foundation for the list is derived from
the existing rail aspirations that were agreed by Public Transport Sub-Committee
in April 2000. Some of these aspirations have been achieved, and some
have evolved since then and the Rail Development Officer has refined
the list to reflect any development. The final input into the proposed
list has come from the responses to the recent parish consultation.
I am confident that the County Council now has a comprehensive list
of rail aspirations that meet local needs.
- In Annex
2 I have included the detail on each rail project and aspiration.
I have split the Annex into four sections. In Part A, (download
as doc. file) I have given information relevant to the key rail
projects where officers have directed their attention in the past twelve
months.
- The remaining
aspirations are then listed in Parts B and C, in no particular order.
Part B (download as doc. file)
includes the aspirations that are specific to a particular location,
or train operator, whilst Part C (download
as doc. file) focuses on the more generic countywide aspirations.
The final section, Part D (download
as doc. file), lists any additional aspirations that have been suggested
by parishes as part of the recent consultation.
Recommended
Changes
- As well as indicating
which aspirations have specific support from parishes, I have, in some
cases, also recommended a change to an existing aspiration, primarily
to reflect progress that has been achieved since April 2000. The Executive
is asked to consider and adopt these recommended revisions.
- Members are also
invited to consider any additional changes they would like to make,
and nominate any other scheme and aspiration that they would like to
see included in the list.
Prioritisation
- An important part
of this report is to seek guidance on the relative importance of directing
resources to achieving each rail aspiration in 2003/04. This will enable
the Rail Development Officer to direct his limited resource to those
aspirations that members feel are important in the coming year.
- year. Other staff
resource will be available to help progress some of the aspirations,
such as the relocation of Oxford station.
- Rail related issues
will also be progressed in the context of our general transport and
land use planning work and in consideration of individual planning applications.
- I have indicated
the likelihood of progressing each aspiration in the coming year within
the rail environment outlined above.in Annex
1. This is based on the information available to officers at
the present time. This does not mean the aspiration cannot be achieved
in later years.
- I have recommended
an overall priority for each rail aspiration, and this indicates how
each one will be taken forward. This recommendation seeks to take into
account the achievability of the aspiration in the coming year and also
an understanding of members' views and its importance to local people.
- Having regard
to the resources available, aspirations that have a recommended overall
priority of LOW will only be mentioned as Oxfordshire County Council
aspirations, as and when appropriate. An overall priority of MEDIUM
will enable officers to actively pursue a particular aspiration as and
when the opportunity arises, whilst an overall HIGH priority will indicate
those aspirations that will be proactively pursued and will occupy the
bulk of the Rail Development Officers time.
- Members may wish
to consider revising some of the recommended overall priorities. However,
it should be remembered that the Rail Development Officer only has limited
resources to work proactively on a small number of projects at any one
time. I would suggest that no more than 5 HIGH priority schemes which
have a HIGH staff resource, or an equivalent number of lower staff input
projects, can be taken forward simultaneously.
- The effect of
moving a small number of aspirations between the LOW and MEDIUM priority
categories would have a lesser effect on officer workload. However,
if the majority of aspirations were moved to the MEDIUM category this
would make it difficult for officers to determine those of a higher
importance, and that, in effect, is likely to mean that in practice
they are treated as being of LOW priority.
- If members decide
to elevate some of the aspirations in overall priority, they would also
therefore need to consider decreasing the priorities of a similar number
of aspirations. A summary of the priorities can be found at the start
of Annex 2.
Financial
and Staff Implications
- As I have highlighted
in Annex 1, the rail industry
is going through a state of almost constant change. It is difficult
to predict with any degree of confidence the level of staff resource
and finance that each project may require in the future. However, so
that the members are able to give consideration to each project, I have
endeavoured to indicate the effect that each rail aspiration may have
on officer time and the financial implication for the Council.
- At this time it
is not possible to quantify the number of hours or days of officer time
that may be required on each project. However, for indicative purposes
only, I have given an indication of the likely implication on officer
time on a low, medium and high basis, based on the information available
at the present time.
- How these projects
will be funded will become clearer as each project is progressed. Some
of the aspirations may be funded entirely by the rail industry, whilst
others may be funded jointly by the rail industry and the County Council.
In some cases, they may be deliverable only if the county council provides
the majority of the funding either from its Capital Programme, possibly
supplemented by developers contributions. Until work on each project
is advanced, more precise costs will not be known and I am therefore
only able to give an indication of the likely financial implication
of each project for guidance only.
Potential
Funding Mechanisms
- As discussed above,
the SRA is now the key investor in the industry and will decide where
to direct its investment in line with its strategic policies and best
value objectives. Network Rail and the train operators will function
as delivery agents.
- In the current
environment, the SRA has indicated that they are unlikely to agree to
substantial investment in infrastructure and services. It is, however,
continuing with its Rail Passenger Partnership (RPP) scheme which can
fund smaller, local schemes.
- Under the RPP
Scheme, a bid is submitted to the SRA for up to 50% of the total cost
of a project, with the balance coming from the local community. Inevitably,
this is likely to be from the County Council or District Council, although
it is possible that for very small improvements, the local train operator
may be prepared to share some of the funding responsibility. There is
substantial work involved in preparing an RPP bid, as they need to meet
certain criteria laid down by the SRA, including a financial appraisal,
and they must have the support of Network Rail and a train operator.
- Another very useful
source of funding comes from commercial development. In some places,
developer contributions already exist; for example the County Council
has secured a major contribution from the developer of Bicester Village.
There is potential for more contributions to be secured and directed
towards enhanced public transport infrastructure, including rail.
- Another potential
source of funding is from the County Council’s Capital Programme. The
proposals for Grove/Wantage and Kidlington stations are included in
the Preparation Pool for the Capital Programme, although with no start
date attached to them. The most recent advice from the Government Office
for the South East suggests that capital allowancesallocation in support
of the Local Transport Plan should only be used for passenger interchange
works, and that trackside and other works on the railway itself should
be funded from within the rail industry. This means that Local Transport
Plan funding can only make a relatively small contribution towards the
overall cost of opening the stations.
- Although the SRA
is looking to continue funding smaller schemes through the RPP process,
one of the main ways of identifying where investment will take place
will arise through franchise replacement. The SRA is keen to improve
performance and reliability and to link these to franchise subsidy.
It seems likely that the SRA will direct funding towards schemes that
help achieve this overall objective. With the expected changes to the
franchises serving Oxfordshire there may be the opportunity that some
of the Council’s aspirations could be achieved in this way.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- note
the progress of the key rail projects during the past year;
and
- subject
to consideration of:
- whether
there are additional or amended details that members would
like to add to existing aspirations, or any additional aspirations;
and
- whether
there are specific locations where members specifically want
officers to investigate if some of the general aspirations
contained in Part C of Annex 12 can be introduced;
adopt
the recommended priorities and, where applicable, the recommended
changes to, the proposed rail aspirations as indicated in the
report.
DAVID
YOUNG
Director of
Environmental Services
Background papers: NILpapers: NIL
Contact
Officer: Adrian Saunders, Rail Development Officer Tel: Oxford
815080
Printed
on 9 December 2002
Return to TOP
|