Introduction
1. The
London
Road Corridor scheme (Pullens Lane –
Osler Road
) and
the Summertown shopping area street environmental scheme are included in the
Oxfordshire County Council’s Local Transport Programme for 2006-2011.
2. Both schemes have been the subject of
public consultation exercises and the design has developed to a stage where a
more detailed cost estimate has now been produced.
3. Financial Procedure Rules
require a detailed project appraisal to be undertaken for all capital projects
that exceed £1,000,000 and submitted to Cabinet for approval.
4. This report seeks approval to the
Detailed Project Appraisals for the schemes shown below.
A420 London
Road
Corridor (
Pullens Lane
–
Osler Road
) – Drawing
on display
5. This is the first section of the London
Road Corridor to be developed to make bus journeys quicker and more reliable
and improve road safety for all users.
6. The scheme was the subject of a public
consultation process and Transport Decisions Committee approved the final
design on
6 September 2007
.
Summertown
Shopping Area Street
Environmental Scheme –
Drawing on display
7. The scheme seeks to tackle congestion by
creating half-width bus lay-bys at two existing bus stops. This will reduce the
impedance to through traffic, improve pedestrian facilities with the
construction of a new pedestrian crossing and introduce a 20mph limit over the
whole route. The scheme also seeks to improve the street environment through
the use of quality surface materials to footway areas and the de-cluttering of
unnecessary street furniture.
8. The scheme was the subject of a public
consultation process and the Cabinet Member for Transport approved the final
design on
29 March 2007
.
Financial
Implications
9. The
London
Road Corridor (
Pullens Lane
–
Osler Road
) scheme is estimated at £3.219m including fees.
Funding has been allocated from the Capital Programme for the financial years
2006/07 to 2009/10 and comprises of Supported Capital Expenditure (SCE) and
developer funding. The programmed start of construction is June 2008. A full
assessment of the funding is shown in Annex 1 (download as .doc file) Project Appraisal No H188
attached to this report.
10. The Summertown Shopping Area
Environmental scheme is estimated at £1.482m including land and fees. Funding
for the scheme has been identified in the Capital Programme from 2006/07
through to 2009/10. This is made up from SCE sources and developer
contributions. A full assessment of the funding is shown in Annex 2 (download as .doc file)Project
Appraisal H187 attached to this report.
RECOMMENDATION
11. The Cabinet is RECOMMENDED to:
(a) approve Project Appraisal H188 for the
London Road
Corridor (
Pullens Lane
to
Osler Road
) scheme; and,
(b) approve Project Appraisal H187 for the Summertown Shopping
Area Environmental Scheme.
STEVE
HOWELL
Head
of Transport
Environment
& Economy
Background
papers:
Nil
Contact
Officers:
Mike Collins, Principal Engineer, Tel: 01865 815877
Andrew Vidovic, Assistant
Engineer, Tel: 01865 810437
November 2007
Return to TOP