Return
to Agenda
ITEM CA9
CABINET
– 21 MARCH 2006
HIGHWAY
MAINTENANCE PROGRAMME 2006/07
Report by
Head of Transport
Introduction
- This report lists
the proposed expenditure on highway maintenance activities programmed
for 2006/07 from both the capital and revenue budgets.
- The available
revenue budget of £17, 563,734 consists of the agreed base revenue budget,
plus a standard inflation allowance of 2%, an additional contract inflation
allowance of 1% and an ongoing 2004/05 Policy and Budget Plan allowance
for the revenue implications of Capital Schemes. In addition there is
funding to cover increased energy costs identified within the 2006/07
non-discretionary budget pressures.
- Offsetting these
increases to the base budget are the agreed reductions to meet the Efficiency
Savings and Budget Pressures and also budget virements which need to
be agreed to cover a small shortfall in the staffing budget as a result
of an increase in the insurance premium.
- For clarity Annex
1 (download as .xls file)
sets out the calculation of the Highway Management Road Maintenance
Revenue Budget in tabular form and for comparison shows the sum allocated
in 2005/06.
- There is a basic
structural maintenance capital budget of £13,772,000 plus an additional
£2,450,000 specifically allocated for de-trunked roads. The total allocation
is from the agreed transport element of the Supported Capital Expenditure
(Revenue) (SCE(R)) for 2006/07 and will remain provisional until final
confirmation of the capital programme which is subject to another report
at this meeting.
- Over and above
the SCE(R) allocation a further sum (at present estimated to be £2,145,000)
will be carried forward from the 2005/06 allocation for ongoing major
maintenance on the A40. Approval has been obtained from GOSE to carry
funding into 2006/07 to enable the maintenance works to be co-ordinated
with improvement works planned for the Green Road Roundabout, Headington.
- At the end of
January there is a forecast 2005/06 revenue underspend within Highways
Management of £100k that is planned to be carried forward to fund the
ongoing Business Process Review of the Highway Management service. This
has previously been agreed by Cabinet in the course of revenue monitoring.
Insurance
Premiums
- Although the County
Council robustly defends highway compensation claims, and is generally
successful, industry costs have continued to rise and our premiums will
rise by £20k in 2006/07.
Energy
Costs
- The energy contract
is due for renewal from 1 October 2006. The current contract that started
on 1 October 2005 saw a substantial increase in the price of energy
over previous years and as costs continue to rise an increase of £570,000
over the 2005/06 budget is forecast for 2006/07.
Service
Priority for Local Roads and Pavements
- Following on from
2004/05 and 2005/06 the available budget has again been prioritised
to support the County Council’s objective to improve the condition of
local roads and pavements while at the same time holding the condition
of the principal road network at its present level.
- The balance of
budget allocations has been addressed to better reflect the different
conditions and demands in the North and South of the County. Studies
reveal for example that the condition of local roads in the South leads
to their costing more in reactive maintenance than roads in the North.
As more work is carried out to formalise asset management the more budgets
will be refined and the more tailored the service will become to meet
local demands.
Overview
of Local Non-Principal Roads Condition
- The desperate
state of non-principal roads towards the end of 2000/01 had been significantly
improved by the end of 2002/03 by directing more of the maintenance
budget to carriageway maintenance schemes. During 2004/05 approximately
£3.7 million of additional funding was spent on the network to address
the widespread damage caused by clay shrinkage during the exceptionally
dry summer of 2003. Following the actions, the Best Value Performance
Indicators (BVPIs) for classified and unclassified non-principal roads
have improved.
- The total amount
of repairs justified by assessment continues to be very high. However,
the backlog of maintenance work has yet to be addressed, and roads remain
vulnerable to weather damage, and to the demands placed upon them by
traffic. The County Council has responsibility for maintaining over
3,800 kilometres of non-principal roads and, with the exception of urgent/safety
type repairs, most of the minor rural roads and urban estate roads are
receiving little or no structural or preventative maintenance. Work
is currently in hand to more accurately determine the size of the overall
maintenance backlog, but current estimates value this at well over £100
million, with about 90% of this attributable to the non-principal road
network.
- If the County
Council is to deal with this backlog, a sustained level of spending
is required for deterioration to be controlled and improvements maintained.
Scheme funding in 2006/07 is therefore being targeted, within budget
constraints, to the sites of highest priority, alongside a significantly
increased allocation for surface dressing treatments to improve safety
by restoring surface texture and preserve structural integrity.
- With pro-active
asset management planning, a strategy is being developed to map out,
over a number of years, the parts of the highway network where funds
should be directed to achieve greatest benefit and maximum return. Consequently,
non-principal roads are likely to receive a greater proportion of the
assessed schemes structural maintenance budget than before. This should
also impact positively on the CPA score for highways.
Principal
Roads (‘A’ roads)
- The County Council
maintains over 650 kilometres of Principal Roads, including a number
of recently de-trunked roads that have an important strategic function
and carry high volumes of commercial and other traffic.
- The priority and
investment given to principal road strengthening in recent years has
improved their condition to the point that the target set in the Local
Transport Plan was met by the end of 2002/03, a rate of improvement
that placed Oxfordshire in the top quartile of authorities nationally
for this indicator.
- The condition
prediction model based on surveys of road strength shows that funding
in future years will need to be carefully balanced to keep principal
roads at the optimum of 6 – 8% of roads requiring strengthening at any
time, whilst simultaneously allowing sufficient funds to be re-directed
to bring about continued improvements to the non-principal road network.
These ambitions must also take account of other Local Transport Plan
(LTP) targets including the reduction in the numbers of injury accidents
involving skidding on wet roads. The sensitivity of the Principal Roads
BVPI to expenditure is borne out by the marginal drop from 6% of roads
requiring strengthening to 7% between 2003/04 and 2004/05 and to 8%
in 2005/06. However, a number of expensive and high profile maintenance
schemes have recently been completed, including A4144 Abingdon Road.
Other schemes such as those on the A40 around Oxford are in the implementation
stage, and should result in significant benefits to road users as well
as being reflected positively in next years BVPI’s.
- Finance for these
capital funded schemes is obtained through the LTP process. The County
Council has a good record in recent years for obtaining the amounts
bid for major structural maintenance work. As well as providing technical
justification for schemes, in future it will be necessary to demonstrate
that sufficient emphasis is being placed on highway maintenance by the
Authority if this level of capital funding is to continue or increase.
A further point to note is the effect of proposed changes to the funding
rules for ‘routine’ (revenue) based maintenance work on de-trunked roads.
An announcement is expected some time during 2006/07, but the changes
may well result in less money being granted to Oxfordshire for this
work. If this does occur it will place additional pressure on the revenue
budget.
- High profile principal
road schemes programmed for 2006/07 include repairs to the A40 between
Cutteslowe and Sandhills, the A420 Shrivenham Bypass, and the A420 High
Street in Oxford. The Principal Roads budget for 2006/07 is approximately
£3million, with an additional £2million funding for A40 works carried
forward from 2005/06.
- Project appraisals
for structural maintenance schemes in excess of £1m are included in
the Annex to this report.
Footway
(Pavement) Conditions
- An increased level
of funding for footways has been maintained in recent years with positive
results. The year-on-year assessment ratings that signal the need for
repair and, consequently, the level to which deterioration has occurred
on footways across the county as a whole have shown a marked improvement,
a has the BVPI overall. However, it must be stressed that there are
large numbers of footways whose condition justifies repair that still
do not make the programme.
Oxford
City Centre Improvement
- As in the last
two years £400k of the 2006/07 budget has been allocated to footway
improvements in the centre of Oxford. In 2005/06 the footways in the
vicinity of the Oxford Castle site were improved to tie in with the
new development. In 2006/07 it is proposed to combine the structural
maintenance of the High Street from Carfax to Turl Street with "Streetscene"
improvements of the footways with the added aim of reducing clutter.
Drainage
System Maintenance
- During 2005/06
the budget allocation of £350k, increased in 2004/05 from £300k, funded
a total of 36 schemes. This included 5 major schemes, one of which -
Clifton Hampden Stage 1 - was prioritised due to the failure of a brick
culvert under the highway as well as serious flooding upstream. Further
progress has been made into the backlog of schemes during the year and
the budget will remain at £350k in 2006/07 in recognition that there
are still areas of public concern over the need to protect highways
and property from flooding.
- As part of the
reallocation of budgets between North and South gully cleaning budgets
will be adjusted but no more funding will be available overall and it
will continue not to be possible to carry out twice yearly cleaning
of all gullies.
Bridge
Strengthening and Structural Maintenance
- The structural
maintenance allocation includes funding for strengthening and structural
maintenance of bridges. This includes a significant sum for working
with Network Rail to strengthen substandard road over rail bridges.
Progress has been slow due to the difficulties of working over railway
lines; however, the County Council will complete the re-decking of Oxhey
Road bridge near Cropredy and start work on Goring Station Bridge during
2006/07. Scheme development has commenced on Lower Heyford Railway Bridge,
Potash Bridge at Milton and Wolvercote (Goose Green) Railway Bridge.
Temporary restrictions are currently in place on these bridges.
- Structural maintenance
and strengthening of county bridges continues with major work on Shillingford
Bridge, Marsh Lane Flyover and Bodicote Flyover proposed for 2006/07.
The last remaining substandard bridge on the principal road network
is Newbridge carrying the A415 over the River Thames at Standlake. This
bridge is scheduled to be replaced in 2010/11 because strengthening
is not possible and work has started on identifying options that will
preserve the historic bridge and provide an alternative crossing.
- Expenditure on
structural (LTP) bridge maintenance and strengthening will be less than
allocated at £1.86M but will increase in future years as schemes are
constructed. The overall maintenance budget has therefore been based
on the premise that bridge maintenance funding over and above that figure
will be added to the roads budget in the short term and repaid when
the outstanding bridgeworks are committed.
Bridge
Condition and Routine Maintenance
- Draft performance
measures are now available from DfT for bridges. Using the Bridge Condition
Indicator determined from regular bridge inspections the condition of
bridges in Oxfordshire is classed as good, but is showing a small year
on year deterioration. The revenue allocation for routine bridge maintenance
remains at the same level in real terms as 2005/06.
Allocation
of the Available Budget to the Programme
- The use of the
available budget has been prioritised to support the ‘Cleaner/Greener’
agenda and the County Council’s objective to improve the condition of
local roads and pavements while at the same time holding the condition
of the principal road network at its present level. The use of the available
budget can be best summarised as follows:
- The allocation
for structural maintenance schemes on Principal roads is increased
by £1.7m
- The non-principal
schemes budget last year was supplemented with £1.28m of additional
funding for emergency repairs to drought damaged roads. The 06/07
base line figure for non-principal roads is therefore slightly higher
than last year.
- The budget for
assessed footway schemes is increased by £240k for 2006/07. Within
this the £400k identified for Central Oxford Enhancements will be
used as a contribution to the high profile maintenance and streetscape
improvements to High Street, Oxford. The additional investment in
footways will also improve the best value performance indicator for
footways (BV 187).
- £190k is allocated
this year specifically to Mobility Crossings, for dropped kerbs and
ramps to be constructed for improved access to footways at certain
locations.
- The trend to
increase the Surface Dressing budget year on year continues in 2006/07
with an additional investment of £0.5m. £1m of the allocation is to
be targeted to improving skidding resistance at specific sites, and
for signing of other sites in the forward programme where there is
poor skidding resistance.
- As part of the
Cleaner/Greener priority additional funds will be directed to the
maintenance of verges along High Speed Roads, to enable two full cuts
to be performed per session. £20k has also been set aside for trialling
a ‘cut & collect’ machine that gathers the arisings as they are
mown. If successful, it is likely that the machine coverage will be
increased next year.
- Continuing with
the Cleaner/Greener theme, £300k has been targeted specifically for
cleaning signs and for clearance of vegetation around them.
- Furthermore,
the budget for Weed Control has been almost tripled for 2006/07 to
enable repeat treatments to be applied.
- The allocation
for Village Maintenance gangs has been increased substantially for
the second consecutive year to £1,537,800.
- £200k will be
spent on 2006/07 on improvements to signalised pedestrian crossings
that should also result in improvements to BVPI 165 which is a key
indicator for improvement to the CPA rating.
- The allocation
for Area Traffic Schemes has been reduced to support the investment
in highway maintenance. Traffic schemes will become funded principally
from LTP and need to be justified against the objectives of the LTP.
- £15k has been
allocated to expedite the reinstatement of road markings in Central
Oxford for more efficient parking control.
- £150k has been
directed to Business Process Re-engineering (BPR) to identify further
opportunities for organisational and procedural reform which will
lead to improved operations and efficiencies.
- The highlighted
increases in budget allocations have been realised through an increasingly
pro-active approach to asset management that has enabled funds to be
better directed to service the present needs of the network, rather
than on a predominantly historical basis. The amounts allocated within
the 2006/07 highway maintenance budget have been re-aligned to reflect
this, although overall the revenue budget remains at a similar level
to 2005/06.
Oxford
City Section 42 Submission and Allocation
- After lengthy
discussions at officer level indicated that there may be better ways
of delivering a range of services in Oxford City, the City Council withdrew
from the negotiations and continue to claim their right under Section
42 of the Highways Act to maintain the unclassified roads in Oxford.
Section 42 requires the City Council to submit by 15 December an estimate
of maintenance works costs for the following financial year. The County
Council may approve the estimate as submitted or with modifications.
- The City Council
has submitted an estimate as required and this is shown in column A
of Annex 3 (download as .doc file).
The estimate includes the cost of repairs to all defects noted on all
of the unclassified roads and is the equivalent within Oxford of the
total backlog for the County as a whole. The recommended modified estimate
is shown in Column B. The modified estimate carries on the methodology
that is based on a proportionate share of relevant 2004/05 County Council
allocations, with adjustments for 2005/06 inflation. The modified estimates
for assessed carriageway and footway schemes are the totals of schemes
in Oxford City that have been through the same rating process as all
other similar schemes in the county and are included in the programme
lists in the Members’ Resource Centre.
Snow Clearing
- The County Council
has a duty under the Highways Act 1980 to remove snow from the highway.
Section 150 (1) states that "if an obstruction arises in a highway from
accumulation of snow or from the falling down of banks on the side of
the highway, or from any other cause, the highway authority shall remove
the obstruction".
- It is generally
accepted that any accumulation of snow which prevents safe or convenient
access to any community has to be cleared as quickly as possible in
compliance of this duty.
- There are no funds
within the Environment & Economy budgets to clear snow, which could
cost in excess of £500,000 per day and a "Policy for the financial implications
of snow clearance" was agreed at this meeting a year ago. It is intended
to continue with this protocol to give the Head of Transport a degree
of confidence that the initial expenditure on snow clearing will be
centrally funded.
Summary
Tables
- Attached to the
report are the following:
- Annex 1
contains a breakdown of the Highway Management revenue budget (download
as .xls file).
- A summary of
the planned expenditure on all activities is shown in Annex 2
(download as .doc file).
- Annex 3 Oxford
City Council Section 42 estimate and recommended modified estimate
as explained above.(download as .doc
file)
- Annex 4 is
a summary of the standards of non-assessed maintenance activities
and budgets.(download as .doc file)
- Annex 5
contains Capital Project Detailed Resource Appraisals for the A420
High Street, Oxford improvements; A40 Cutteslowe to Headington and
Sandhills and A420 Shrivenham Bypass Structural Maintenance schemes.(download
as .doc file)
- Lists of the individual
schemes included in the programme on the basis of the ratings derived
from surveys of each site have been put in the Members’ Resource Centre.
Separate lists are given for drought damaged roads, principal roads,
non-principal roads and footway schemes.
RECOMMENDATION
- The Cabinet
is RECOMMENDED to:
- endorse
the details of the 2006/07 Highway Maintenance programme as
set out in Annex 2 subject to confirmation of the capital funding
for structural maintenance;
- approve
the Oxford City Council’s Section 42 estimate as modified and
shown in Column B of Annex 3;
- approve
the Detailed Project Appraisals at Annex 5.
STEVE
HOWELL
Head of Transport
Background
papers: Nil
Contact
Officer: Brian Fell Tel 01865 815083
March
2006
Return to TOP
|