Return
to Agenda
Division(s):
Witney West, Witney North
|
ITEM EX14
EXECUTIVE
– 15 MARCH 2005
WEST END
LINK ROAD - WITNEY
Report by
Interim Head of Transport and Head of Property
Introduction
- This report seeks
approval for a revised detailed project appraisal for the Witney: West
End Link Road Stage 1 with a total cost of £1.610 million.
Scheme
Progress
- Since the project
appraisal for the West End Link Road Stage 1 was presented to the Executive
in November 2001, a detailed design has been carried out and tenders
sought for carrying out the works. The original estimate of £875,000
(August 2001) was uplifted to £1,040,000 (August 2003) and approved
by the Executive on 22 July 2003. Unfortunately the contract award could
not proceed because it came to light that a small plot of land on the
road line was in the ownership of the official receiver of the Early’s
of Witney factory site. Protracted negotiations finally resulted in
a dedication for highway purpose of this land on 27 January 2005.
- Detailed planning
permission was granted on 28 April 2003. Conditions attached to this
approval have been complied with in so far as is necessary to allow
the start of development.
- An associated
closure of Dark Lane and Moor Avenue, to remove ‘rat running’, was approved
by the Transport Implementation Committee on 29 May 2003. The statutory
deadline for making the order is 26 March 2005 (2 years after publication
of the proposed order) so the proposed order has been republished and
any objections will be considered by the Transport Implementation Committee
at their meeting on 24 March 2005.
- Tenders for the
construction of the link road were received on 24 February 2005 and
these are being evaluated in accordance with Best Value criteria. Officers
estimate that the total cost of the scheme (including fees) has now
risen to £1,610,000. As this latest figure constitutes a change of more
than 10% of the previous estimate a new approval is now required, see
Annex 1 (download as .doc file)
for detailed Project Appraisal H163/2.
- It is anticipated
that work will commence on site in late June or early July 2005, subject
to the necessary Section 106 and Section 278 agreement being signed
by the three landowners to fully finance the scheme. The revised cost
is entirely within the original outlined financial agreement with the
three landowners. A construction contract will not be awarded until
this agreement is completed by all parties.
Environmental
Implications
- Stage 1 of the
link road will provide the opportunity to reduce traffic congestion
in Witney High Street. It will also facilitate the redevelopment of
brownfield land south of Mill Street.
- The scheme is
to be built in a conservation area and the construction of the single
carriageway road will be undertaken in a way which minimises environmental
impact. The Environment Agency, together with the District Council,
have been consulted during the design stage and their requirements complied
with.
Financial
and Staff Implications
- Financial Implications
are detailed in the Resource Appraisal at Annex 2 (download
as .doc file). Most of the increased cost is because an allowance
has now been made for potential Land Compensation Act Part 1 Claims.
Inflation and a risk contingency for claims on the construction contract
and public utility costs account for the remaining increase.
- Project management
is being carried out by officers of Environment & Economy and can
be encompassed within current staffing levels.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to approve the Detailed Project Appraisal H163/2 as set
out in Annexes 1 and 2.
RICHARD
DIX
Interim Head of Transport
NEIL MONAGHAN
Head of Property
Background
papers: Nil
Contact
Officer:
Colin Baird Environment & Economy Tel: Oxford 815536
Mark Tailby Corporate
Property Group Tel: Oxford 816012
February
2005
Return to TOP
|