|
Return
to Agenda
ITEM EX9
EXECUTIVE
– 6 JULY 2004
FUTURE OF
THE COMBINED MAINTENANCE CONTRACT AND ARRANGEMENTS FOR PROCURING HIGHWAY
CAPITAL WORKS
Report by
Head of Transport
Introduction
- This report seeks
approval for the principles on which the Combined Maintenance Contract
is to be either extended by renegotiation or re-tendered. It will set
out a contract strategy as a framework for compiling the Contract.
- To allow time
for the appropriate negotiations and procurement procedures to be followed,
approval for a one year extension to the Combined Maintenance Contract
has been given as provided for in the contract.
- The Combined Maintenance
Contract also includes highway capital schemes up to £300K in value.
Above this value schemes are usually individually tendered and alternative
methods of procurement, such as framework contracts, need to be investigated.
The Present
Position
- Highway maintenance
and small capital highway works were externalised in 2000 as part of
a Combined Maintenance Contract. The contract also included vehicle
maintenance and grounds maintenance for schools and other Council establishments.
Commencing in April 2000, it was let to Isis Accord Ltd for a five year
period ending in March 2005, with the presumption that annual extensions
would be given provided contractor performance was satisfactory.
- The value of the
contract was projected at £56M over the 5 years and involved the transfer
of 170 employees. However, good capital finance settlements through
the Local Transport Plan process and an increased Government emphasis
on Highway Maintenance will increase the value to around £90M over the
initial five year contract term.
- The grounds maintenance
element of the contract has a total value of around £1M per annum. Vehicle
maintenance looks after vehicles for Social & Health Care and the
Library Service and has a value of £300K per annum. There is considerable
synergy between the three elements of the Combined Maintenance Contract
bringing operational and financial benefits to grounds or vehicle maintenance
activities compared to the likely costs if these were separately contracted.
- Highway capital
schemes with an estimated value greater than £300K are usually individually
tendered with some exceptions of higher cost schemes being carried out
by Isis Accord where early involvement has brought financial benefits.
When specialist contractor expertise is required, schemes less than
£300K have been tendered.
The Principles
behind the Contract Strategy for the Future
- The Best Value
Review of Construction Services carried out in 2002 recommended that
contractual arrangements must enable and encourage actions in line with
the principles of ‘Rethinking Construction’. Government procurement
policy and advice also promotes contracts based on ‘Rethinking Construction’
principles. Within the County Council, Resources are basing the renewal
of the property term contracts on these principles.
- Rethinking Construction
identified five key ‘drivers of change’ needed for successful contracts:
- committed leadership
- a focus on the
customer
- integrated processes
and teams
- a quality driven
agenda and
- commitment to
people
- Focus on the customer
within the context of the Combined Maintenance Contract means delivering
appropriate quality work to cost and time, while still retaining flexibility
enough to offer a responsive service. Integrating processes would remove
some duplication or unnecessary work, possibly linking the client and
contractor in an arrangement that presents a single identity to the
public. This could remove some of the public confusion as to which organisation
is delivering Highway Maintenance, achieve a faster service response
and some efficiency gain through changes to work programming.
- One of the County
Council’s key objectives is protecting our environment. Greater use
of sustainable solutions, such as recycling, in highway maintenance
and new capital works will help meet this objective, as will closer
integration.
- The Customer Services
Review in Environment & Economy is likely to recommend that moves
are made to simplify public contact and improve response times to a
request for a service. Integrated contractor and client teams could
help such recommendations to be realised.
- The October 2003
Scrutiny Review on Highways and Drainage made a number of recommendations
that will need to be addressed in any future contract arrangements.
Changes in the contract should address several of the recommendations,
but in particular Recommendation 6:
"Find
a way to improve the monitoring of repair work, perhaps by stipulating
certain changes or standards as a necessary condition for extending
the contractor’s contract, or by drawing up an agreement between client
and contractor to specify how monitoring of works will be improved"
This
should be achieved through the introduction of a meaningful performance
measurement regime to monitor the delivery of work on the ground and
setting targets for improvement.
- Commitment to
people means looking to our partners to apply the same values to their
staff as the council does to its own staff. In this case, it means the
Council taking note of the fact that the bulk of the contractors workforce
is still made up of ex-County Council employees externalised as part
of this contract and being aware of the effect of its decisions on those
ex-employees.
- One of the outstanding
actions left in the Construction Services review is to consider how
individual contracts over the Combined Maintenance Contract threshold
are let.
Way Forward
- New arrangements
are sought which provide better incentives for improvements in efficiency
and economy, incorporate the above principles, and address issues that
have been "sore thumbs" in the current contract. This could be done
either by renegotiation of the existing contract with Isis Accord or
by retendering the contract. The preferred way forward is to renegotiate
with Isis Accord for the reasons below, but if this fails to deliver
the means to achieving our objectives then to retender the contract.
There is not enough time between now and the earliest end of the current
contract for a retender process should this prove necessary so a one
year extension of the contract to 31 March 2006 has been agreed, as
provided for in the contract.
- Taken in the round,
the overall performance of Isis Accord since the start of the contract
gives no grounds for ending the contract without attempting a renegotiation.
The original contract award included a quality assessment on which the
company scored well and overall the company has delivered what was promised.
The comparative information we have from the National Highway Works
Benchmarking Club (to which we belong), our own satisfaction monitoring,
and connections with other authorities that give an insight into contracts
elsewhere, indicate that Isis Accord’s performance is at least as good
as any likely competitor.
- It is generally
accepted by procurement professionals that renegotiation is less disruptive
than re-tendering. Re-tendering would be disruptive to both the county
and contractor at a time when delivering the capital programme is a
high priority for both the council and government.
- The provisions
of TUPE would mean that the Isis Accord workforce and management would
be transferred to another contractor if they won a contract re-tender.
At a time of construction skills shortage a change of contractor would
in effect only achieve a change in company style and unsettle the workforce.
- There are areas
of the contract that are not perceived to be working well, often related
to the costs of individual items. These concerns need to be addressed
by a more open and fair system of reimbursement, such as actual costs,
which demonstrate the reasonableness of the costs and remove misconceptions.
- Another concern
is the ability of the contractor to programme and deliver work on time.
Programming work is dependent not only on the performance of the contractor
but also on the consultant and the County Council as client. Better
project management and the introduction of a master programme for all
individually named schemes that is agreed by all parties has started
to improve certainty of delivery on time of these works. Delays on smaller,
often isolated pieces of work are also a source of irritation, particularly
where they have been promised to and/or paid for by others and delay
reflects badly on us. More integrated teams with more influence for
the client to direct work gangs should help avoid this sort of problem.
- Performance monitoring
has been introduced into the Engineering Services Contract with Babtie
as a contractual obligation and this should be extended into the Combined
Maintenance Contract. Future extensions to the contract should be contractually
linked to performance.
- Isis Accord is
part of the Accord group of companies running similar contracts in other
counties. As a company they have a good record of using innovative methods
of working as promoted in Rethinking Construction. They recently won
the Staffordshire County Council Highway Maintenance contract, a contract
containing similar aspirations to our contract strategy. Isis Accord
have made a presentation to the client staff showing that they are prepared
to make changes in line with our contract strategy.
- There is no apparent
reason why renegotiation should fail, but as an incentive and a fallback,
the way forward also allows time for re-tendering the contract. A re-tender
would adopt the same contract strategy as set out for renegotiation.
Contract
Strategy for Renegotiation or Re-tendering
- The detailed Contract
Strategy for the renegotiation or, if that fails, the re-tendering of
the Highway Maintenance Contract is set out in Annex A (download
as .doc file). A summary of the main requirements of the contract
strategy is given below:
- Provide a distinct
public identity for all aspects of delivery of the Highway Service
(design, construction, maintenance) by integrating as far as is practicable
the operations of the client, consultant and contractor. The practicalities
of co-location should be investigated.
- Incorporate
improved mechanisms for control of cost, time and quality, preferably
based on the mechanisms of the Engineering and Construction Contract
(NEC contract) Term Maintenance Contract.
- Specify the
requirements for performance measurement and management, and for the
provision of systems to support it. Introduce challenging targets
to drive and encourage continuous improvement.
- Adopt ‘open
book’ principles to ensure fair and reasonable reimbursement of the
Contractor and demonstrate to the client the same. The same principles
should be extended into the contractor’s supply chain.
- Move from the
informal partnering in the existing contract to a formal partnering
arrangement based on options within the NEC contract.
- Considering
the synergies between the three elements of the Combined Maintenance
Contract, the new contract should investigate continuing to include
Vehicle and Grounds Maintenance. This will need confirmation from
the clients managing these aspects of the existing contract.
- Facilitate the
introduction of environmental improvements such as increased use of
recycled materials and the use of alternative fuels in vehicles.
- Allow flexibility
within the contract to allow for future developments.
- The contract strategy
for delivering highway maintenance and small capital highway improvement
schemes needs also to consider how the larger capital schemes are to
be procured. The use of either one or several parallel framework contracts
would reduce the costs of tendering individual schemes and facilitate
early contractor involvement. Setting the financial limits to give an
overlap between the framework contracts and the highways maintenance
contract will enable benchmarking and some useful competiveness. A framework
contract allows a firm or firms to be appointed to construct a number
of projects over a period of time giving efficiency savings through
early contractor involvement and greater supply chain certainty.
Programme
- The proposed programme
for the renegotiation/re-tendering is included in Annex B (download
as .pdf file). This programme shows that agreement on the renegotiation
of the contract with Isis Accord needs to be reached before the end
of October 2004 to allow sufficient time for re-tendering to take place.
- If renegotiation
with Isis Accord is successful, changes will be made to the contract
so that all the principles outlined in the strategy are in place by
April 2006. Up to three further year extensions will be granted dependent
on performance. The contract will then need to be re-tendered to start
in April 2010.
- If renegotiation
does not prove possible, the contract will need to be re-tendered to
start in April 2006. The detailed programme is given in Annex B (download
as .pdf file).
Financial
and Staff Implications
- At externalisation
170 employees transferred to the successful contractor. If the contract
is re-tendered TUPE will likely apply and a significant number will
need to transfer to the successful organisation.
- There will be
some staff implications in preparing or renegotiation of the contract.
The existing staff do not have all the expertise required for this work
and consultants will need to be engaged at a predicted cost of £25K
to provide specialist advice on the contract form and terms.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- approve
the Contract Strategy set out in paragraphs 25 and 26 of the
report and in more detail in Annex A (download
as .doc file);
- endorse
the extension of the existing contract by negotiation as described
in the report, as a preferred option for the future Combined
Maintenance Contract;
- to
note the extension of the Isis Accord Contract for one year
up to March 2006 to enable time for renegotiation of the contract
and if this should fail re-tendering of the contract; and
- approve
the development of a framework contract or contracts to cover
works greater than £200K.
DAVID
MCKIBBIN
Head of Transport
Background Papers:
Buro Happold Report to support the Best Value Review; Scrutiny Review
of Highways and Drainage. October 2003
Contact
Officer: Peter Brown Tel: 01865 815641
June
2004
Return to TOP
|