|
Return
to Agenda
ITEM EX6
EXECUTIVE
- 8 JULY 2003
FINANCIAL
MONITORING
Report by
the Head of Finance
Introduction
- This is the first
Monthly Monitoring Report for 2003/04. At this stage of the year there
are only a few identified variations to the agreed budget and these
are discussed below. As we progress further into the financial year
other variations will emerge and be reported accordingly.
- Members are reminded
that shortly there will be a series of budget seminars run by individual
directorates to enable members to ‘get inside the budget’. The ‘Medium
Term Financial Plan 2003/04 to 2007/08 - Summary’ is now available.
The more detailed book ’ Medium Term Financial Plan – Service Analysis,
Revenue and Capital’ is due to be available shortly.
Learning
& Culture
- No budget variations
have been identified at this stage. There is a potential issue in relation
to the impact of Job Evaluation on casual staff in libraries and this
will be reported to a future meeting of the Executive if necessary.
Social
& Health Care
- The impact of
tight control of budgets in 2002/03 within Social Services is still
being felt in the early part of 2003/04. This together with a contingency
held back to deal with any budgetary problems arising in year leaves
a current projected underspending of around £2m. This underspending
will reduce over the financial year in response to the demand for services.
It is anticipated that Social Services will be in balance at 31 March
2004. The Social Services provisional outturn position at 31 March 2003
is an overspend of £2.6m. There is a one off provision of £3m in the
2003/04 budget to offset this. Part of the contingency relates to the
additional £0.400m available to allocate in year, subject to member
approval.
- It is expected
that the overspend carried forward at 31 March 2003 of £0.102m on the
Youth Offending Team will be accommodated within the spending for 2003/04.
Environment,
Roads & Transport
- There is an anticipated
underspend of £0.4m due to the Structure Plan Examination in Public
now being likely to take place in Spring 2004. This underspend will
be carried forward to fund the work in 2004/05.
- At this stage
it is anticipated that all other budgets will be fully spent including
the variations brought forward from 2002/03. In 2002/03 the Capital
Programme was expected to provide £1m for the budget reserve through
a revenue/capital switch. This did not prove possible due to an overspending
on the Transport capital programme leaving balances £1m less than anticipated.
This switch will now take place in 2003/04 and the £1m will be reinstated
to balances.
Community
Safety
- There is a projected
overspend on the Registration Service of £0.262m. This reflects a brought
forward overspend of £0.157m from 2002/03 and at this stage a projected
overspend of £0.105m in 2003/04. Work is being undertaken currently
to meet part of the overspend from 2002/03 by other means. Significant
changes are being made in 2003/04 which will bring down substantially
the overspend position during the year, and this will become clearer
in future reports to the Executive. The overall forecast position for
Community Safety is an overspend of £0.240m.
Corporate
Governance
- There are two
changes identified so far. The first change is a technical change to
the way in which we have to account for the external audit fee. This
results in an estimated charge of £0.292m in the 2003/04 accounts, as
we must now accrue for the fee. It is recommended that the Executive
approve a supplementary estimate in 2003/04 to meet this cost.
- The Oxfordshire
Community Network Project had been projected to overspend by £1.4m in
2002/03, to be met from balances. The actual figure is £1.376m. Of this
£0.867m was incurred in 2002/03 and due to an additional grant allocation
of £0.147m from the New Opportunities Fund, only £0.362m remains outstanding.
This has slipped into 2003/04 and is a call on balances this financial
year.
Fire Service
Pay Award
- The Fire Service
Pay Award from November 2002 has now been agreed. The budget for 2003/04
included a provision based on the offer from the employers side. We
will report any variance to the budget figure once a full costing exercise
has been completed. It is not anticipated that there will be any additional
costs above the budget provision.
Job Evaluation
- The task of costing
Job Evaluation has been enormous and complicated. Further detailed analysis
has shown that the costs are expected to be some £0.110m more than the
budget provision. This sum will be a call on balances.
Temporary
Mortuary
- A temporary mortuary
was set up at Brize Norton at the request of the Ministry of Defence
to receive the bodies of British soldiers killed in the Iraq conflict
. The Council has incurred costs of £0.346m to date. These costs are
being reimbursed by the Ministry.
Contingency
- As part of the
budget setting process for 2003/04, overprovision for inflation on property
rates resulted in an unallocated contingency of £0.118m. This will be
returned to balances.
Balances
- The effect of
the above changes and the budget contribution to balances is as follows:
|
|
£m
|
|
Provisional
County Fund Balance at 1 April 2003
|
3.529
|
|
Unallocated
Contingency
|
0.118
|
|
Contribution
from Revenue Budget
|
3.700
|
|
External
Audit Fee
|
-0.292
|
|
Oxfordshire
Community Network Project
|
-0.362
|
|
Job Evaluation
– Additional Costs
|
-0.110
|
|
Repayment
from Environmental Capital Programme
|
1.000
|
|
Estimated
County Fund Balance at 31 March 2004
|
7.583
|
Programme
Area Carry Forward Reserves
- At this stage
of the year there is no further information available, other than as
reported. The minor variations reported relate to the reported underspend
to be carried forward of £0.400m for Environment, Roads & Transport
and the projected overspend on Community Safety of £0.240m. An analysis
of individual Programme Area reserves at 31 March 2003 is shown below:
| |
£000
|
£000
|
|
Learning
& Culture
|
1,135
|
|
|
Environment,
Roads & Transport
|
1,574
|
|
|
Corporate
Governance
|
1,815
|
|
|
|
|
4,524
|
|
Social
& Health Care
|
-
2,542
|
|
|
Community
Safety
|
-81
|
|
|
|
|
-2,623
|
|
Net position
|
|
1,901
|
City Schools
Re-organisation Cashflow
- The City Schools
Re-organisation cashflow is expected to reach its peak at the end of
2003/04. The anticipated costs are £1.108m offset by part year savings
of £0.400m from formula allocation savings. This leaves a cumulative
overdrawn position of £3.984m at 31 March 2004. There is a further potential
variation when the Middle Schools close at the end of the summer term
2003, as the LEA will need to meet the costs of any deficit budgets.
This position will not be known until September and will be reported
to the Executive then.
Consolidated
Position
- The overall position
on balances based on the projections shown in this report shows an estimated
£3.751m remains in reserves to meet all other potential and outstanding
pressures arising in the year. This assumes, perhaps prematurely, that
the Carryforward Reserve for all areas will be net nil (save for reported
minor variations). The more likely position is that Social & Health
Care will deliver a balanced budget this year (see paragraph 4) and
there will continue to be some carryforward in other areas. The position
is summarised below:
|
|
£m
|
|
Revenue
Balances
City
Schools Overspend
Projected
Programme Areas Carryforward
based on paragraph 15 above
|
7.575
-3.984
0.160
|
|
|
3.751
|
County
Council Staffing
- Annex 1
(download as .doc file) analyses
the Cdouncil’s workforce at 31 March 2003. The next update will be at
30 June 2003, when information will be presented according to the new
directorates.
Conclusion
- This is the first
monitoring report for 2003/04 and clearly the financial position for
all programme areas will emerge more fully as the year progresses. Whilst
County Fund Balances remain below the 1% recommended threshold, there
is provision within the agreed Medium Term Financial Plan to increase
them by £1m annually up to 2007/08. I will be reviewing this policy
as part of the budget process. With regard to the overall financial
position, I do not have specific cause for concern at this early stage.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- note
the report;
- approve
a supplementary estimate of £292,000 for the external audit
fee as set out in paragraph 8;
- approve
a supplementary estimate of £362,000 for the Oxfordshire Community
Network as set out in paragraph 9, in place of the similar amount
originally to have been funded from balances in 2002/03;
- approve
a supplementary estimate of £110,000 to meet the additional
cost of Job Evaluation arising in 2003/04 as set out in paragraph
11;
- approve
the arrangements for dealing with unallocated contingency provision
in respect of Social & Health Care and property rates as
set out in paragraphs 4 and 14.
CHRIS
GRAY
Head of Finance
Background
Paper Nil.
Contact
Officer Mike Petty Tel 01865 815622
June
2003
*
Please note the following: the structure on the old MIS system was outdated
and therefore does not match the current structure. This means that it
is not possible to give an accurate indication for the annual change in
numbers for each group of staff within Directorates. Total changes in
numbers are given. There are some employees who have more than one job
with the Council, these have been counted separately for each job for
the first time.
Return to TOP
|