|
Return
to Agenda
ITEM EX5
EXECUTIVE
– 15 APRIL 2003
TRANSPORT
CAPITAL PROGRAMME 2003/04 TO 2005/06
Report by
Assistant Director (Transport Development) and Head of Finance
Introduction
- This report seeks
the Executive’s approval for the 2003/04 Transport Capital Programme
and the Provisional Programmes for 2004/05 and 2005/06. The programmes
have been developed taking into account the Executive’s decision on
18 March 2003 on the allocations of the Single Capital Pot (SCP) to
the 6 main transport budget headings and further discussions with the
Executive Members for Transport and Strategic Planning & Waste Management.
Background
- The Transport
Capital Programme has grown rapidly since 2000/01 as additional Government
allocations and developer contributions have become available. The outturn
figures for the last 5 years are shown in Table 1 below.
|
Year
|
Outturn
£m
|
|
1998/99
|
10.1
|
|
1999/00
|
10.9
|
|
2000/01
|
10.4
|
|
2001/02
|
25.2
|
|
2002/03
|
33.3*
|
*Provisional
- The rapid expansion
of the programme has proved to be a real challenge for Oxfordshire County
Council staff, Babtie (the Term Consultant for Engineering Design) and
Isis Accord (the Combined Maintenance Contractor). Due to the historic
lower level of the transport programme, there were very few schemes
in approved forward programmes and not only has it been necessary to
promote and design a much increased annual programme but in order to
prepare for future years’ programmes, much preliminary design and assessment
work has had to be undertaken.
- This has resulted
in some slippage in planned programmes. Problems recruiting additional
staff in a tight labour market, combined with increasing levels of consultation
and technical problems with individual schemes, have led to underspending
in recent years. Due to careful financial management, no Government
credit approvals have been lost and funding has been carried forward
to support the following years’ programmes. In 2002/03 commitments of
£3.340m were carried forward to the current year, which was similar
to 2001/02.
- The increasing
availability of transport funding has led to a sharp rise in public
expectations and many requests are being received for a wide variety
of schemes from across the County. Even with the transport programme
proposed for 2003/04, it will not be possible to meet these public expectations.
If Oxfordshire County Council is to continue to attract good settlements
from the Government there is also a need to make progress on delivering
on key transport targets. This requires substantial investment in road
maintenance, public transport, cycling and road safety schemes; and
will limit our ability to meet community aspirations for schemes such
as pedestrian crossings and traffic calming. The Community Safety (Transport)
programme has been established to enable the County Council to respond
appropriately to these requests and this programme will help to meet
the commitments set out in the County Council’s stated values.
Programming Issues
- On 18 March the
Executive approved the provisional allocations to each of the 6 main
budget headings. As in previous years, priority was given to structural
maintenance and to meeting commitments being carried forward. This inevitably
limits the number of schemes that can be included in other programme
areas and there will undoubtedly be disappointment if schemes that have
a high level of community support have to be deferred to the 2004/05
or 2005/06 programmes.
- The Executive
Members for Transport and Strategic Planning & Waste Management
are very concerned to ensure that we use our resources in the most effective
way. The 2002/03 programme was reviewed in October 2002 and approval
given to bring forward maintenance schemes from 2003/04 to ensure that
the SCP funding was all spent. It would be possible to follow the same
approach in October 2003 but this would not help to deliver other schemes
that are urgently wanted.
- An alternative
strategy has been developed which recognises that, based on previous
years’ experience, there will again be slippage in the delivery of the
2003/04 programme due to consultations delaying schemes, objections
to traffic orders or technical design problems. In the report to the
18 March Executive the shortfall of funding required to complete the
2002/03 programme was identified as £1.592m, resulting in schemes to
this value having to be deferred to 2004/05.
- The underspend
reported in October 2002 was forecast to be £1.8m (approximately 10%
of the SCP funding). To avoid the risk of underspending in 2003/04 and
to maximise the size of the delivered programme, it is proposed to include
in the 2003/04 programme £2.0m of schemes (10% of the 2003/04 SCP) that
would have formed part of the 2004/05 programme, in the expectation
that the programme will underspend by at least this much. At this stage
it is impossible to predict which schemes will slip but the programme
will be kept under review and expenditure carefully monitored.
- This approach
will result in the new schemes included in 2003/04 programme being very
similar to those envisaged when it was reviewed in October 2002; although
the proposed allocations to each budget heading have been reviewed in
the light of the latest information on the state of each scheme. The
total programme includes an additional £3m of SCP being directed at
Structural Maintenance. (This would have been an additional £4.0m, but
£1m was brought forward into 2002/03 and has already been spent.)
- It must be recognised
that there will be an additional £2.0m commitment carried forward into
2004/05; but this will be off-set to some extent by the first £1.5m
repayment of the SCP that was "borrowed" in 2001/02. Although there
is an element of risk in this approach, the worst outcome that could
arise is that there will not be sufficient slippage in the programme
to enable all programmed 2003/04 schemes to be completed by 31 March
2004 due to a lack of SCP funding. Some schemes may simply have to be
deferred to April or May 2004 and funded as a commitment on the 2004/05
budget. The intention would be to review the programme in October 2003,
as in previous years, and take appropriate action to ensure that the
expenditure of the SCP exactly matched the £19.927m available. The availability
of developer contributions and on-street parking surpluses provides
some flexibility to achieve this result.
- New financial
and programming systems have recently been introduced that will enable
greater financial control and monitoring. It is not anticipated that
this approach will create any financial difficulties.
Proposed
Programmes
- The proposed detailed
programmes are set out in the accompanying booklet.
(tables - (download as .xls file))
(cover and notes - (download as .doc file).
The revised allocations to the 6 main budget headings are set out at
Annex 1. The
provisional allocations approved at the meeting held on 18 March are
included at Annex 2
for comparison.
- There is a need
to provide some flexibility in the programme to be able to respond to
opportunities or problems that may arise during the year. The Community
Safety (Transport) programme includes funding for Minor Traffic Engineering
Schemes. These are schemes identified by the Area Engineers, usually
in response to complaints, which typically cost less than £5,000.
- Continuing negotiations
for developer contributions offer the opportunity of including new schemes
in the programme. In addition, some programmes include funding under
the heading of Rapid Response Schemes. It is proposed that the inclusion
of new schemes in the Capital Programme is delegated to the new Head
of Roads &Transport, subject to funding being available; and in
the case of schemes costing more than £10,000, in consultation with
the Executive Members for Transport and Strategic Planning & Waste
Management.
Project
Appraisals
- At the Executive
meeting on 18 February 2003 a commitment was given to bring forward
a full Project Appraisal for the Premium Bus Routes project which is
planned to be implemented over the next eight years. This is attached
at Annex 3.
- A Project Appraisal
for the Structural Maintenance Programme (A4130 Didcot and A417 Ardington)
is appended at Annex 4.
- The new Water
Eaton (North Oxford) Park and Ride site is now nearing completion. The
earthworks were undertaken in October and November, which proved to
be amongst the wettest months ever recorded. As a consequence, significant
additional areas of clay soil had to be excavated and filled with stone
beneath the car park and access roads, so that opening the car park
was not unduly delayed. Other significant cost increases have resulted
from adjustments to the new traffic signal-controlled junction on Bicester
Road, Gosford and a higher than allowed for cost of site supervision,
arising from use for the first time of the new NEC contract. Since the
Project Appraisal (H152) was approved in December 2001, there have been
other increases in the cost of the project, notably the decision by
the Executive to purchase and install pay and display ticket machines.
As a consequence the outturn cost of this scheme is now expected to
be £3.683m rather than the £3,084m originally approved.
Financial
and Staff Implications
- The financial
implications are as set out in the report. Assessment, promotion and
design of schemes in the programme will be undertaken by a combination
of existing staff, Halcrow, the County Council’s Term Consultant for
Transport Planning, other specialist consultants and Babtie, the County
Council’s Term Consultant for Engineering Design.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:-
- approve
the detailed programmes for 2003/04 and the provisional programmes
for 2004/05 and 2005/06, set out in the booklet accompanying
the report.
- delegate
the inclusion of new schemes within the main budget headings
in the 2003/04 Transport Capital Programme to the Head of Roads
& Transport, subject to finance being available and in the
case of schemes costing more than £10,000, to consultation with
the Executive Members for Transport and Strategic Planning &
Waste Management;
- ask
the Head of Roads & Transport to carry out a review of the
Transport Capital Programme and report back to the Executive
in October 2003;
- approve
the Project Appraisal for the Premium Bus Routes project included
at Annex 3 to the report;
- approve
the Project Appraisal for the Structural Maintenance Programme
(A4130 and A417 Ardington) included at Annex
4 to the report.
EDDIE
LUCK
Assistant Director (Transport Development)
CHRIS GRAY
Head of Finance
Background
papers Nil
Contact
Officer: Eddie Luck - Tel: 01865 815845
April
2003
Return to TOP
|