ITEM EX5 - ANNEX 4

EXECUTIVE – 15 APRIL 2003

TRANSPORT CAPITAL PROGRAMME 2003/04 TO 2005/06

Resource Appraisal (download as .doc file)

DETAILED PROJECT APPRAISAL

APPRAISAL NO: H170

NAME OF SCHEME: Highway Maintenance Programme Schemes: 2003/04

Proposed Start Year: 2003/04

Basis of estimate: Contract rates and recent prices for similar work

1. DESCRIPTION OF PROJECT

The project comprises the following carriageway reconstruction and resurfacing schemes in the approved Highway Maintenance Programme 2003/04.

 

Construction Cost

 

2003/04

2004/05

 

£000’s

£000’s

A4130 Didcot to Milton Heights

1,000,000

30,000

A417 Ardington

500,000

15,000

Design and Supervision Fees

120,000

10,000

 

1,620,000

55,000

2. NEED FOR PROJECT/CONSISTENCY WITH STRUCTURE PLAN

The schemes have been assessed as being needed to preserve the existing road network in a safe and satisfactory condition. They are consistent with the objectives and targets for Highway Maintenance set out in the Council’s Local Transport Plan.

3. PREFERRED OPTIONS/DETAILS OF SCHEME

The schemes consist of strengthening failed or weak roads. The A4130 scheme will be carried out together with the construction of a cycle track alongside the road over the length of the scheme.

4. FUNDING

Funding uses the agreed Transport element of Single Capital Pot credit approval.

5. FINANCIAL/STAFF IMPLICATIONS

The total cost, including fees, is estimated at £1.620m. The works are all programmed to be completed in 2003/04. Some contract payments will be made in 2004/05.

Babtie Group Ltd will design and supervise both the schemes.

6. ENVIRONMENTAL IMPLICATIONS

Noise reducing road surfacing will be used where appropriate.

7. RESOURCE APPRAISAL

The Resource Appraisal is attached. (download as .doc file)

RICHARD DIX
Assistant Director (Highway Management)

CHRIS GRAY
Head of Finance

Contact Officer: Richard Dix, Tel: (01865) 815663