|
Return
to Agenda
ITEM EX8 -
Supplement
EXECUTIVE
– 18 MARCH 2003
TRANSPORT
CAPITAL PROGRAMME 2003/04 TO 2005/06 - SUPPLEMENTARY REPORT
Report by
Director for Business Support & County Treasurer, and Assistant Director
of Environmental Services (Transport Development)
- This report provides
some additional information on Oxfordshire’s involvement in the National
Traveline, Telephone and Internet Enquiry Service, which is likely
to impact on the Transport Capital Programme. It has been made necessary
by the late receipt of a letter from the south east regional co-ordinating
authority (Buckinghamshire County Council), which is attached as Annex
1. (Download as .doc file).
Background
- Traveline is a
regionally organised service, and the detailed data on which it relies
(bus timetables, bus stop locations and so on) is provided by its member
local authorities. Twenty-two such authorities have come together in
the south east and are known collectively as SELTA (South East Local
Transport Authorities). Costs of providing the service are shared between
local authorities and the region’s bus operators.
- The capital costs
of setting up the service, such as securing accommodation and purchasing
computer hardware, are met by the local authorities, while day-to-day
running costs are funded by operators. The revenue costs of data management,
funding a full-time Data & Systems Manager, and a proportion of
the time of the Chair of SELTA, are also met by the local authorities.
- The costs allocated
to each authority are based on its percentage of the population of the
region – Oxfordshire’s share is currently 6.43% of the total.
- The computerised
Enquiry Management System (EMS) used to drive the data to the telephone
operators is due to be replaced this year, as a result of the present
contractor being unable to provide technical support for the system
currently in use, and because of the increased capacity needed to handle
the more detailed data being added incrementally to the system.
Project
Timescale and Costs
- The contract tendering
process was put in the hands of consultants, and tenders are due to
be returned on 24 March. The contract is due to be awarded in April,
to allow testing of the new system prior to its installation in September
(which has to be seamless with the termination of the current system).
- Initial capital
costs were estimated at £500,000, based on experience in other regions,
and the figures in our Capital Programme were based on this amount.
Total revenue costs were expected to be around £200,000. An early "in
principle" commitment to support our share of those costs was made last
year.
- However, it now
looks likely that capital costs will be nearer £750,000, due to the
complexity and size of the system proposed, and Oxfordshire’s share
will increase accordingly. Rather than a capital contribution of £32,000,
our percentage may be nearer £48,000, and ongoing revenue costs could
be £20,000 per annum as opposed to the £13,000 originally estimated.
- The exact figure
will not be known until tenders are received, but a commitment to the
funding for the replacement system is required from all the regional
authorities on or before 24 March, as the new contract cannot be awarded
without prior agreement to the funding.
Financial
and Staff Implications
- The impact of
Oxfordshire effectively withdrawing from the Traveline Consortium would
be far-reaching. Not only would there be a "gap" in the information
available for the south east, but other systems proposed by the Department
for Transport (DfT) such as Transport Direct, which is based in large
part on the information in Traveline, would also be compromised. DfT
would be very concerned if any local authority were to unilaterally
withdraw funding, and in addition to being poorly received, it could
influence future Local Transport Plan funding settlements.
- If Oxfordshire
did withdraw from Traveline, there would be increased pressure to provide
our own telephone and internet enquiry service, with increased capital
and revenue costs falling directly to the County Council, although it
may be possible to share these with bus operators. However, this possibility
has been investigated before, and found to be prohibitively costly.
- For these reasons,
it is considered that the County Council should continue to fully co-operate
with and participate in the Traveline project and make the required
sums available. The potential £7,000 increase in revenue expenditure
would fall on the Public Transport Revenue Support Budget of bus services.
If the contract is to be awarded in early April there is a need to allocate
£48,000 from the Capital Programme in advance of the full programme
being considered at the 15 April meeting of the Executive.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- confirm Oxfordshire’s
continuing commitment to traveline;
- approve the
£7,000 increase in the cost of operation of the traveline system to
be funded from the Public Transport Revenue Support Budget; and
- approve the
allocation of £48,000 capital contribution to the traveline project
from the 2003/04 Transport Capital Programme.
EDDIE
LUCK
Assistant Director of Environmental Services (Transport Development)
CHRIS GRAY
Director for
Business Support & County
Treasurer
Background
papers: Letter from Buckinghamshire County Council (attached as Annex
1)
Contact
Officer: Eddie Luck – Tel: 01865 815845
12
March 2003
Return to TOP
|