Return
to Agenda
ITEM TIC9
TRANSPORT
IMPLEMENTATION COMMITTEE – 7 JULY 2005
WHEATLEY
TRAFFIC CALMING: PHASE 2A: CHURCH ROAD
Report
by Interim Head of Transport
Introduction
- This report describes
a scheme to raise the kerb height of the south footway of Church Road,
Wheatley (from Holloway Road junction to east of No 84) and the widening
of its narrow sections. The background to the scheme is given in outline.
- This report summarises
the comments received during public consultation and seeks authority
to proceed with the scheme.
Background
- Wheatley is a
large village which is bypassed by the A40 dual carriageway. The centre
of the village is characterised by narrow streets. Unfortunately many
car drivers travelling between the M40/A40/A418 junction and the Oxford
Eastern Bypass travel through the centre of Wheatley in order to avoid
delay at the A40 Headington Roundabout. Also many vehicles (both through
traffic and local traffic) travel in Wheatley at speeds which are excessive
for the road conditions.
- In July 2002 a
public exhibition showing proposals for traffic calming measures for
Wheatley was held in Wheatley village hall. Subsequently the proposals
were modified in the light of comments received. Construction of Phase
1 was completed in the summer of 2004. Streets included in Phase 1 were
London Road (Church Road junction to The Triangle), Friday Lane, High
Street (east end) and Ladder Hill.
- Phase 2a was planned
in 2004 to comprise the proposed scheme in Church Road and two other
schemes in London Road (between the two junctions with Old London Road)
and Old London Road. However, following public consultation, it became
necessary to reappraise the two other schemes because there were many
objections to them. Also a review of the County Council’s Transport
Capital Programme permitted construction of only one scheme in Wheatley
in the financial year 2005-06. The proposed scheme in Church Road was
the obvious choice for further work, as there were no objections from
local residents and businesses, only from bus operators.
The Proposed
Scheme
- In Church Road,
the south footway is the more heavily-used footway. However, it is very
narrow in two locations and almost non-existent at the corner of Holloway
Road. The kerbs are low, and when parked vehicles make it difficult
for moving vehicles to pass each other, westbound vehicles tend to mount
the south footway. Most of the buses serving Wheatley pass along Church
Road; the majority also use the northern section of Holloway Road, turning
left in to Church Road and right (when going in the opposite direction)
into Holloway Road. For most of each day in the Oxford Brookes University
term (except Sundays) there are six or seven buses per hour in each
direction along Church Road.
- The proposed scheme
would increase the kerb height generally to 100mm and widen the narrow
sections of footway to 1.5 metres (but only 0.9 metre alongside the
building at the corner of Holloway Road). The footway widening would
reduce the carriageway width with three pinch points. The extent of
the proposed scheme, and the locations of the pinch points (marked A,
B and C) are shown on the plan attached at Annex 1 (download
as .doc file). The area around pinch point A is shown at a larger
scale on the plan attached at Annex 2 (download
as .doc file).
- At pinch point
A, where the footway width would be only 0.9 metres, the carriageway
width would be 5.015 metres. At pinch point B the carriageway width
would be 4.925 metres and at pinch point C 5.1 metres.
- The only bus stop
within the proposed scheme is the westbound (ie Oxford-bound) stop in
Church Road about 30 metres from pinch point A and about 40 metres from
the junction with Holloway Road. Here, as agreed with bus operators,
the kerb height will be about 140mm so that wheelchairs and pushchairs
can be easily pushed on and off the low-floor buses. Also the floor
of the adjacent bus shelter will be given a new surface finish.
Consultation,
Objections and Officer Comments
- Public consultation
on the proposed scheme was carried out in December 2004 and January
2005. In addition, residents and businesses in the affected length of
Church Road received an update, inviting further comments, in May 2005.
- Two responses
have been received. One from operators of buses serving Church Road
and the other from the Vicar of Wheatley Parish Church. The objections
were expressed verbally at a meeting held on 24 February 2005 to discuss
bus operation problems in Wheatley. The bus operators’ concern is that
the three pinch points in the proposed scheme would make it impossible
for a bus to pass another large vehicle and would therefore cause delay
to services.
- At present, parked
cars reduce the width of available carriageway to a single lane intermittently
along almost the whole length of the proposed scheme, including at pinch
points B and C and buses frequently have to stop in order to give way
to oncoming vehicles. Parked vehicles rarely take up more than 2 metres
of carriageway width. Even at the proposed narrowest point (pinch point
B), where the width of carriageway would be reduced from about 5.5 metres
to 4.925 metres, there would still normally be 2.9 metres available
for a bus (of maximum width 2.55 metres) to pass a parked vehicle.
- A late objection
has been received from the vicar of St Mary’s Church. His concerns are
that the proposed widening of the footway opposite would make it more
difficult for buses to pass funeral corteges and wedding cars parked
outside the church and that vehicles would then be more likely to mount
the south footway opposite the church in order to avoid having to wait.
- However the narrowest
point in the carriageway outside the church would be at pinch point
C, where the width would be reduced from about 5.45 metre to 5.1 metre.
Even if the special cars, parked against the north kerb of Church Road,
take up 2.2 metres of that width when parked, there would still normally
be 2.9 metres available for a bus (of maximum width 2.55 metres) to
pass them. Also the increased kerb height on the south side would greatly
discourage vehicles from mounting that footway.
- At pinch point
A, large eastbound vehicles which have turned left from Holloway Road
have not fully straightened up and on both sides of the carriageway
there is a parking prohibition ("No Waiting at any time"). Eastbound
vehicles wait here when giving way to westbound vehicles, because there
are usually parked cars on the north side from about 6 metres further
east (Annex 2). The proposed footway widening would reduce the carriageway
width from about 5.65 metres to 5.015 metres, making it necessary for
large eastbound vehicles turning left from Holloway Road (such as buses)
to wait a few metres further back.
- The proposed south
footway widening to 0.9 metres at pinch point A would cause additional
delay to some eastbound buses – anything from a few seconds to more
than a minute. However many local people have requested that the almost
non-existent footway be widened to a usable width, and 0.9 metres is
the minimum width which can accommodate most wheelchairs and child-buggies.
Therefore the recommendation is that the proposed footway widening at
this point should be included in the proposed scheme.
Other
responses to the public consultation
- Several local
residents commented in favour of the proposed scheme but in addition
expressed concern about excessive parking and/or the large number of
buses. Both of these concerns are under investigation and discussion
with interested parties. In the short term, consultation on proposals
for minor extensions of the parking prohibitions in Church Road is expected
with a report to this Committee within the next few months.
Financial
and Staff Implications
- The predicted
total out-turn cost of the scheme is £130,000, comprising £76,000 for
construction and £54,000 for fees, £12,000 of which was spent in the
financial year 2004-05. £110,000 is allocated for this scheme in the
2005/06 Capital Programme: Community Safety-related schemes budget,
leaving a possible shortfall of £8,000. The construction estimate includes
20% of contingencies equated to around £13,000 and it is anticipated
that the possible shortfall in funding will be covered by those contingencies.
- Supervision of
construction will be carried out by the County Council’s term consultant,
Jacobs-Babtie. Management of the schemes can be accommodated within
existing Environment & Economy staff resources.
RECOMMENDATIONS
- The Committee
is RECOMMENDED to authorise implementation of the scheme as set out
in this report and Annex 1 (download
as .doc file) to it.
RICHARD DIX
Interim Head
of Transport
Background papers: Copies of letters and e-mails received about the
scheme in response to consultation. Notes of the meeting between representatives
of Oxfordshire County Council, Wheatley Parish Council, Oxford Brookes
University and four bus companies, held on 24 February 2005.
Contact
Officer: David Deriaz Tel: Oxford 815666
June
2005
Return to TOP
|