|
Return
to Agenda
ITEM TIC16
TRANSPORT
IMPLEMENTATION COMMITTEE – 6 DECEMBER 2002
GROVE,
OXFORD LANE - TRAFFIC CALMING
Report
by Director of Environmental Services
Introduction
- Consultations
have been carried out on a traffic-calming scheme for Oxford Road, Grove,
which has been included in the 2002/2003 Community Safety (Transport)
programme. The scheme includes footway build-outs, speed cushions, and
a double mini roundabout on a raised table at the junction of North
Drive and St John’s Road.
- Following initial
consultation the scheme was modified by replacing the footway build-outs
with speed cushions. A formal consultation on the speed cushions and
mini roundabout resulted in only two objections, both making the same
point. The report recommends that the modified scheme should be implemented.
Consultation
- The initial consultation
was carried out in August 2002 and 30 letters detailing objections were
received. The points raised by the objectors and officer comments on
each point are tabulated in Annex 1.
- The majority of
objectors acknowledged that traffic speeds needed to be reduced but
objected to individual aspects of the scheme, or raised other concerns
such as the absence of parking restrictions. The main objections were
to the footway build-outs as it was considered that these could cause
traffic congestion.
- Although it is
considered unlikely that congestion would occur with present traffic
flows, the Draft Local Plan proposes significant further development
in this area of Grove which could lead to traffic congestion in the
future. It was therefore considered preferable to replace the footway
build-outs with speed cushions.
- Formal consultations
were carried out on the provision of the speed cushions and mini roundabout,
which resulted in only one objection.
Discussion
- The traffic-calming
scheme will make a major contribution to the safety of school children
going to and from Grove Church of England Primary School. The scheme
has been modified by replacing the proposed footway build-outs by pairs
of speed cushions. As detailed in Annex
1, I do not consider the objections to be
sufficient reason for not proceeding with the scheme, which is supported
by the Parish Council and the Police.
Financial
and Staff Implications
- There is sufficient
funding in the 2002/03 Community Safety (Transport) schemes budget for
this scheme. Our consulting engineers, Babtie, are designing the scheme
and will supervise the construction.
RECOMMENDATIONS
- The Committee
is RECOMMENDED to authorise the Director of Environmental Services to
proceed with the implementation of the modified scheme as shown in Annex
2 (download as .doc file) to this report.
DAVID
YOUNG
Director of
Environmental Services
Contact
Officer: David Deriaz Tel: Oxford 815666
Background
papers: Copies of letters received from members of the
public in response to consultation have been placed in the
Members` Resource Centre. A 1:500 scale drawing will be on
display at the meeting of the Transport Implementation Committee.
November
2002
Return
to TOP
|