|
Return
to Agenda
ITEM EX10
EXECUTIVE
– 15 MARCH 2005
TRANSPORT
CAPITAL PROGRAMME
Report by
Interim Head of Transport and Head of Head of Finance & Procurement
Introduction
- This report seeks
the Executive’s approval to the 2005/06 Transport Capital Programme
as shown in the attached booklet. This is the final year of the current
Local Transport Plan 5 year period and the programme concentrates on
delivering the schemes developed over this time.
- The programme
takes as its starting point the provisional figures for 2005/06 that
were provided in the report on the Transport Capital Programme considered
by the Executive on 19 October 2004. That report reviewed the 2004/05
programme and the financial implications for 2005/06 of carrying forward
schemes currently being developed. Drawing up the programme therefore
has been about matching the planned spending to the capital allocations
from government for 2005/06 while taking note of the commitments and
the expectations that have built up over the last 5 years.
- This programme
booklet accompanying this report provides the list of specific transport
capital projects called for in the County Council’s decision on the
15 February in regard to the 2005/06 Capital Programme. Financing of
the programme is in line with the Transport Capital Settlement as required
by the Council decision.
- The report includes
an explanation of a revised approach to Better Ways to School and seeks
approval of this change. Also included is an explanation of plans to
advance the implementation of residents’ parking schemes in Oxford and
a revised Project Appraisal for the Cowley Road Oxford Demonstration
Scheme, both for approval of the Executive.
Background
- The total block
allocation awarded by the government for Transport in 2005/06 is £27.283
million. This total is made of £10.495 million for Integrated Transport
schemes and £16.788 million for Structural Maintenance. The Structural
Maintenance figure is further broken down into a formula allocation
of £13.097 million and a one-off allocation of £3.691 million for emergency
repairs to drought damage sustained in the summer of 2003. The award
of the money for emergency repairs results from a bid for extra funding
and an argument for equal treatment to other authorities affected by
drought damage who received emergency funds in 2004/05.
- Separately to
the block allocation, a further allocation of £3.595 million has been
given for major repairs to the recently de-trunked A40 between Cutteslowe
and Sandhills. This allocation is ringfenced to this particular purpose
having resulted from the nationally agreed method of funding works required
at the date of handover of de-trunked roads to local highway authorities.
- These block allocations
are given as Supported Capital Expenditure (Revenue) – SCE(R) – and
are the transport contribution to the cross-service Single Capital Pot.
However, as is now well established, the government expectation is that
sufficient money is spent to achieve progress towards the objectives
and targets in our Local Transport Plan (LTP) and meet them by the end
of the first LTP period in March 2006.
- The government’s
assessment of our performance on Transport is now firmly rooted in how
well we deliver the Transport schemes and in how successful those schemes
are in meeting the targets in our LTP. In practice this means that all
of the Transport funding needs to be directed to pursuing the full range
of our LTP objectives and delivering as many of the schemes as it is
possible to do for the money allocated. The need for this is heavily
underlined by the score given to last July’s Annual Progress Report
on the LTP which gave us a very sharp reminder that we need to deliver
what we have set down as our future programme and be able clearly to
demonstrate that we have done so.
- In addition to
SCE(R) funding, the Capital Programme includes funding from developer
contributions to transport schemes, On-Street Parking Account Surplus,
grants awarded for specific schemes, and the second £1.5 million instalment
of the repayment of a loan to corporate funds from Transport capital
in earlier years. The total value of the programme put forward for approval
is £39.608 million. The total for 2004/05 was £33.84 million so this
represents a considerable jump in the value of the programme. The two
main reasons for this jump are the award of money for drought damage
repair (£3.691m) and for the A40 maintenance schemes (£3.595m).
- As well as the
increase in the total there are also significant differences from last
year’s distribution of funding within the block allocation. The Integrated
Transport Schemes amount is £10.495 million as compared to £12.940 million
last year while the Structural Maintenance block has risen to £13 .097
million as compared to £11.017 million last year. Annex 1 (download
as .xls file) gives a breakdown of the available funding across
the various programme areas and a comparison to the provisional figures
provided in October 2004 based on carrying forward schemes in the course
of preparation. The differences are discussed later in the report.
Review
of 2004/05 performance and influence on 2005/6 programme
- The principle
of creating some headway between the design of schemes and construction
of schemes has worked well in 2004/05. Progress has been more reliable
and predictable than in previous years by identifying schemes to be
designed in one year with construction in the following year. There
are 234 individually listed schemes or groups of schemes in the 2004/05
Integrated Transport schemes programme with 127 of these programmed
to be built in the year. Applying the performance measures and targets
in the Transport Service plan gives the following forecast performance
at the end of 2004/05;
| Target |
Forecast
performance
|
| 80%
of schemes programmed to be built are built |
87%
|
|
75%
of schemes to cost within 54% +/-
20% of estimated cost
|
54%
|
- Scheme delivery
at 87% has moved little from the forecast performance in October but
the performance on the cost target has worsened from a prediction of
76% in October. There is more variation, both up and down, from the
estimated cost than was apparent earlier in the year. The detailed monthly
monitoring of the programme has enabled the financing of the programme
to stay within the available budget and still result in most of the
programme being delivered. The performance needs to be seen in the context
of the 234 separately listed projects, many of them relatively small
projects. Many schemes are included in the programme list in March on
the basis of a preliminary design, changes in the detailed design stage
and as a result of consultation will change the scheme cost. Improving
cost predictability is already a high priority in working with our consultants
and contractors and will continue to be as we develop the measures of
their performance. Two actions associated with this should be:
- to look again
at the risk contingency included at this early estimating stage and
how much estimating effort is worthwhile for smaller schemes;
- identify a point
at which estimates are more certain for use as performance data.
- Resource planning
and costing for the design stage is as important as the build stage
if we are designating schemes for advance design. No formal targets
were set for the programme as a whole but for comparison the figures
for all schemes listed in the programme – both design and construction
- are 88% of all actions planned will be achieved and 52% of these at
the estimated cost. Clearly we are doing well at managing delivery but
need to work on estimating and cost variability measures although many
of the scheme costs and the variations are relatively small sums.
Programming
issues
- The same principle
of forward programming by identifying schemes for design with construction
in the following years has been applied for 2005/06 where we are carrying
forward schemes within well developed programmes such as Integrated
Transport Strategies in towns or where a significant proportion of the
design work has been done. There is no element of over-programming and
no reserve schemes included in the programme.
- However, the changes
of emphasis for Transport objectives in the second LTP to be submitted
this year means that we need to look again at whether using the capital
allocations for the programme areas we are using at the moment are the
most appropriate for the future. For this reason a number of the schemes
listed in the programme for the start of design have "LTP2 appraisal"
written against them pending a review as part of the LTP development
work.
- With the guidance
for the second LTP, the government has issued indicative figures for
the 5 years after 2005/06. These are;
| |
06/07 |
07/08 |
08/09 |
09/10 |
10/11 |
| |
£m |
£m |
£m |
£m |
£m |
| Structural
Maintenance |
13.772 |
14.04 |
14.750 |
15.487 |
16.261 |
| |
|
|
|
|
|
| Integrated
Transport |
10.184 |
10.184 |
10.694 |
11.230 |
11.792 |
| |
|
|
|
|
|
- A forward programme
on the basis of these figures still has to be developed for the second
LTP and for this reason there are no indicative programmes for 2006/7.
It is clear though that the Integrated Transport Schemes block will
be under considerable pressure in 2006/7.
- The task this
year and for the future will be working within the guide figures whilst
striking a balance between;
- the Council
priority to improve the condition of local roads and pavements;
- the Council
priority to increase bus patronage;
- progress towards
reducing road casualties;
- expectations
created in towns with ITS’s and in other communities which request
schemes important to them;
- commitments
to major schemes built or planned;
- the need to
show progress across the whole range of LTP targets.
Proposed programme
- As mentioned in
paragraph 10, although the total allocation leaving aside the one-off
awards for structural maintenance is similar to last year, there is
a reduction in the block allocation for Integrated Transport schemes
compared to 2004/05. This means that the SCE(R) for Integrated Transport
Schemes of £10.495 million is only 61% of the £17.211 identified in
the October review as needed to implement all of the design and construction
work that it would be possible to include in the 2005/06 programme.
- The Structural
Maintenance budget has been set at the settlement figure of £16.788
million. This recognises the need to catch up on the drought damage
that took funds away from what otherwise would have been done in 2004/05,
the difficulty in making any progress towards improving local road conditions,
the need for costly bridge strengthening works, and the pressure on
the maintenance revenue budget to accommodate new demands for asset
management systems and to implement the duties of the Traffic Management
Act 2004. The settlement of £3.595 million for A40 repair is also in
the programme and additional to the block allocation money.
- To help offset
the difference between demand and available funds for the Integrated
Transport Schemes, the £1.5 million repayment of loans to corporate
funds has been put towards this part of the programme instead of to
Structural Maintenance where it went last year. The allocation of funds
to the different programme areas was then done by reducing all of them
to 61% of the figure as it stood in October, adding the £1.5 million,
the developer contributions and all the other sources of funding available,
and adjusting the results to meet absolute commitments and high priority
areas of the programme.
- The Major Schemes
budget remains almost exactly at the October figure although this does
disguise the effects of some slippages in scheme timing. In particular
Witney, West End Link Stage 1, has slipped to 2005/06 because of the
land access problems and delays in agreeing the contractor’s final accounts
for Didcot, Milton Heights Stage 2 and Bicester, Skimmingdish Lane has
slipped the budget provision for these schemes into 2005/06. These changes
have been offset by the Didcot, Cow Lane subway scheme being slipped
to 2006/07 because of lack of progress with Network Rail in connection
with this scheme. All of the above schemes are funded by developer contribution
and these changes do not affect the use of the SCE(R) settlement in
the rest of the programme.
- Looking at the
Integrated Transport Strategies block, in Abingdon provision is made
to start construction of the Town Centre scheme but it has not been
possible to budget for a start on the Marcham Road Stage 2 scheme. The
plan is to complete design of this in 2005/06 for a start on construction
in the following year. In Henley, the budget provides for completion
of the design of the town centre traffic management scheme and a start
on construction. In the other towns, the programmes consist of the construction
of smaller schemes and design work on others with no major changes to
the road network resulting from these. Overall, SCE(R) is 63% of the
SCE(R) funding assumed in the October provisional figures. Much of the
Oxford and Witney ITS programmes are funded from developer contribution
and other funding.
- Within the Sustainable
Transport budget, a new approach to Better Ways to School is explained
later in this report. The Cycling Schemes continue schemes continue
those already under construction or being designed. Public Transport
schemes take forward the Premium Routes schemes and the completion of
the Real Time Information pilot project. The SCE(R) component overall
is 67% of the October provisional programme.
- The Community
Safety programme includes for the construction of Charlbury Home Zone
scheme, the completion of schemes in progress, schemes which have been
designed and approved by Transport Implementation Committee ready to
be built in 2005/06, and a group of schemes to design for construction
in 2006/07 or subsequently. The schemes for design are subject to a
review as to suitability for inclusion in LTP2. Because of the commitment
to schemes in train and expectations arising from approval by TIC, the
SCE(R) funding for this programme area is 69% of the October figure.
- The Casualty Reduction
budget has very little contribution to it from other funding sources
and would have been considerably below what was thought reasonable in
the light of the casualty reduction targets we are expected to meet.
For this reason the SCE(R) contribution to the programme area is higher
than in other areas at 87% of the October provisional figure.
Better
Ways to School: Revised Strategy
- A new strategy
is proposed for Better Ways to School (BWTS) in response to the government’s
target for all schools to have Travel Plans by 2010. The strategy will
ensure that Oxfordshire County Council meets this target, and adds value
to the government’s initiative by setting a target to achieve 3,000
less car journeys to school by March 2011. It is proposed to re-present
School Travel Plans as a ‘contract’ between schools and the County Council
for modal shift, and re-structure spending from the BWTS budget to offer
more support to more schools more quickly.
- A menu of revenue
and capital funded measures has been developed, which will offer practical
help to schools in developing travel plans. Access to the menu will
be controlled in order to focus spending where it will be most effective
in generating travel plans and/or modal shift. All schools will continue
to have access to the extensive range of support available to help them
to develop travel plans, whilst LEA schools will have access to the
government’s Small Capital Grant Scheme administered by the Council’s
Travel Plans Development Team. Access to more costly and resource-intensive
measures, such as cycle parking provision, bus and highway measures,
will be focussed on those schools with the greatest potential to generate
modal shift (the main programme), and those with a track record of success
or achievement, including schools with existing ‘approved’ travel plans.
A programme of schools identified as having high modal shift potential
will be selected by the County Council for each programme year, and
will be supplemented by ‘centres of excellence’. Other schools will
be able to approach the Council at any time and provided they can demonstrate
a record of achievement, will be eligible for capital funds. The overall
funding available in each category will be determined each year by the
Executive.
- A copy of the
team’s Strategic Review and Action Plan for BWTS & School Travel
Plan Development can be found in the Members’ Resource Centre.
Development
of Controlled Parking Zones
- The County Council
has carried out a review of resources associated with developing controlled
parking zones (CPZs) in Oxford. It is now planned to engage consultants
to help with the design, consultation and legal processes needed to
develop new CPZs. A revised forward programme of CPZs for Oxford has
been developed taking into account this extra resource
- For clarity, the
forward programme of CPZs is summarised in two tables below. Table 1
lists the CPZs on which work has already commenced, and the projected
implementation timescale for these schemes. Table 2 lists the planned
new zones and their projected implementation timescale. The timescales
for implementation are based on the current committed staff resources.
Schemes have been prioritised, based on current policy. Any change in
this staff resource in future years could have an effect on the implementation
timescales.
Table 1: CPZs in Oxford
on which work has already commenced
|
CPZ
|
Projected
implementation timescale
|
|
Girdlestone
Rd/ Quarry
|
Mid
2006
|
|
Headington
North East
|
Late
2006
|
|
North
Summertown
|
Mid
2007
|
Table 2:
Planned CPZs for Oxford
|
CPZ
|
Projected
implementation timescale
|
|
The
Lakes
|
Late
2008
|
|
Northway
|
Early
2009
|
|
Marston
South
|
Mid
2009
|
|
Divinity
Rd/ Southfield Rd area
|
Mid
2009
|
|
East
Oxford Extension
|
Late
2009
|
|
Wood
Farm
|
Mid
2011
|
|
Lye
Valley
|
Late
2011
|
|
Marston
North
|
Late
2011
|
- The OTS Working
Party/ HAMATS Steering Group will have an opportunity to comment on
the priority of the planned schemes as shown in table 2 in advance of
the Executive on 15 March and any views will be reported to the Executive
at that meeting.
- In order to provide
certainty for future programming, the Executive is asked to endorse
the order of implementation shown in the tables.
Cowley
Road Demonstration Project – Revised Project Appraisal
- A revised Project
Appraisal for the Cowley Road scheme is attached as Annex 2 (download
as .doc file) for approval. This is one of 10 national demonstration
projects on "Mixed Priority Routes" and is supported by a £1 million
grant from the Department for Transport (DfT). As a demonstration project
there are regular reports to the DfT on progress and outcomes.
- The original project
appraisal was based on a preliminary design estimate by design consultant
Halcrow. Further work on detailed design and costing of the work by
the contractors Isis Accord has resulted in an increase in estimated
cost of construction. The first detailed costing of the scheme was higher
than the increase put forward for approval; savings of £162,000 were
identified in discussions with Isis Accord from changes in specification
resulting in a cost increase of £251,000 for the project. The main reasons
for the increase are an underestimate at preliminary design stage of
material prices and of the intricate nature of the traffic control needed
to deal both with vehicular traffic and pedestrian access to premises
fronting the road. The additional cost can be met from the capital programme
as set out in the Project Appraisal.
Financial
and staff Implications
- The financial
implications are set out in the report. Assessment, promotion and design
of schemes will be undertaken by a combination of existing staff, Halcrow
as our Term Consultant for Transport Planning, Jacobs Babtie as our
Term Consultant for engineering design, and by other specialist consultants.
RECOMMENDATION
- The Executive
is RECOMMENDED to:
- approve
the detailed programme for 2005/06 as set out in the booklet
accompanying the report (Annex 1);
- note
that there will be a review of the programme for 2006/07 onwards
as part of the development of the second Local Transport Plan;
- endorse
the revised approach to school involvement in the Better Ways
to School programme outlined in the report;
- approve
the order of implementation of Controlled Parking Zones in Oxford
as set out in Table 2 of the report;
- approve
the revised project appraisal for the Cowley Road Mixed Priority
Routes Demonstration Project (H174) Annex 2); and
- request
the Head of Transport to report on progress on the Transport
Capital Programme in October 2005.
RICHARD
DIX
Interim Head of Transport
SUE SCANE
Head of Finance
& Procurement
Background
papers: Nil
Contact
Officer: Richard Dix, Tel 01865 815663
March
2005
Return to TOP
|