|
Return
to Agenda
ITEM EX7
EXECUTIVE
– 15 MARCH 2005
RAISING
OUR PERFORMANCE 2
Report by
County Council Management Team
Introduction
- This is the fourth
formal quarterly monitoring progress report on RoP2 implementation,
and covers progress between 1 October and 31 December 2004.
- A full monitoring
report showing the details against each of the success criteria is in
the Members’ Resource Centre and is available for public inspection.
(RAISING OUR PERFORMANCE 2 FOURTH QUARTERLY MONITORING REPORT - Schedule
- download as .doc file)
Executive
Summary
- Significant progress
has been made towards Oxfordshire’s goal of being an outstanding local
authority in 2004 as a result of the RoP2 improvement plan. At the end
of the year many of the challenging and aspirational success criteria
have been fully achieved, with several more on track to be achieved
in the immediate future.
- Notable successes
include:
- an improved
Oxfordshire plan with fewer, more focused, priorities and robust plans
for delivery;
- service plans
that provide staff with clear and achievable objectives and performance
indicators to enable organisational improvement;
- a significant
improvement in the quality of the appraisal process combined with
a very significant improvement in the proportion of employees who
have appraisal;
- excellent progress
towards the community strategy, voluntary sector compact and community
safety objectives;
- strong progress
on improving corporate governance within the authority;
- the development
and implementation of customer service, HR, finance and procurement
strategies.
Current
Position
- The third quarterly
report recorded that, out of four success criteria with achievement
dates between July and September 2004, one had been fully achieved,
two had been largely achieved and one was not achieved. During the period
of October to December out of twelve success criteria with achievement
dates in this quarter six were achieved, one was not achieved, two were
partly or largely achieved and three are on track to be achieved but
have not been to date.
- The overall position
of all success criteria in RoP2 to date shows:
- 54% of RoP2
targets have been achieved/ partly achieved – an increase of 16% since
the third quarter;
- 31% of RoP2
targets are on track to be achieved – a decrease of 14% since the
third quarter, which reflects the increase in targets achieved;
- 10% of RoP2
targets are deemed too early to say – the same as the third quarter;
- 5% of RoP2 targets
have not been achieved or are unlikely to be achieved – the same as
the third quarter.
- The one area where
the success criterion was not achieved during the fourth quarter was
Action 1.3: CPA core service score of 3 achieved for Social Services.
- Success criteria
were partly or largely achieved in the following two cases:
- Action 3.1:
Priorities have robust plans for delivery - on the whole this
criterion has been achieved with the exception of an action plan for
Safe and Supportive Communities.
- Action 14.1:
CPA score of 4 achieved in Auditor Scored Judgement for ethical
framework and legality was not wholly achieved. Whilst the score
of 4 was achieved for implementing new legislation the Audit Commission
were unwilling to increase the overall score of three for legality.
A score of four was given for ethical framework.
- Three actions
are considered on track to achieve their success criteria but have amended
target dates:
- Action 1.1:
CPA rating improved from Fair to Good has been delayed due
to the appeal against the original CPA judgement.
- Action 1.2:
All auditor scored judgements for Use of Resources to be 3 out
of 4 is on track to be achieved in 2005. Actions required to address
known weaknesses have been incorporated into action plans.
- Action 9.1:
Users believe MIS is working more effectively was given an
original target date of October 2004, but this date has since been
revised to May 2005. Progress against this criterion continues, but
success is dependent on the progress of phase two.
- For criteria with
achievement dates in 2005 and beyond:
- Action 11.3: 90%
of targets achieved remains unlikely to be achieved. At the second
quarterly monitoring just 56% of BVPIs were on target to be achieved.
The mean average of all corporate targets currently stands at 41% achievement.
- Action 11.5: Corporate
approach [to project management] implemented remains unlikely to
be achieved. It is anticipated a corporate approach will be achieved
in 2006, but incremental progress towards this goal will be made throughout
2005.
Overview
of RoP2 over 2004
- Analysis of achievement
over the year shows that 15 (44%) of the actions have been fully achieved;
three actions (9%) have not been achieved (at least one success criterion
has not been achieved); 10 (30%) of the actions are predicted to be
fully achieved but have not been as yet; and 6 (17%) of the actions
are still deemed too early to judge.
- The analysis of
progress against the action points highlighted the issue of revised
target dates. In total twelve (34%) action points were given revised
completion target dates across the quarters, some more than once. The
reason for this high level of alteration to targets can partly be attributed
to the targets in the plan not fitting with the SMART methodology, with
many targets being highly aspirational.
- Having completed
the first year of RoP2 this is an opportune time to undertake an analysis
of the plan with a focus on the targets within the plan to ensure future
improvement targets are SMART and to learn from other local authorities
with Excellent status to consider what improvements could be made. CCMT
have commissioned Performance & Review to undertake such a review
in partnership with Business Managers and key workstream managers.
Schedule
for progress reports
- Arrangements are
under way to amalgamate the reporting schedule for RoP2 and quarterly
performance monitoring. It is currently intended that the two be aligned
at the fourth quarter in the financial year (the fourth quarterly performance
report) with a report on outstanding criteria coming to the Executive
on 6 September 2005.
RECOMMENDATION
- The Executive
is RECOMMENDED to note the report, and in particular the proposal to
analyse RoP2 leading to recommendations for the next organisational
improvement plan.
County
Council Management Team
Background
Papers: Nil
Contact
Officers:
Sue Hunt Tel: (01865) 816036
Susan Roberts Tel: (01865) 815425
March
2005
Return to TOP
|