|
Return
to Agenda
ITEM EX6
EXECUTIVE
– 15 MARCH 2005
SAP REVITALISATION
Report by
Director for Resources
Introduction
- The SAP Revitalisation
Programme was established following two consultancy reviews delivered
to the Authority during 2004. RSM Robson Rhodes concluded a report on
financial management and control within the Authority. This report highlighted
where the Authority fell short of best practice financial management
and control standards and recommended actions to attain this level of
control. The second report, a gap analysis review by IBM Consultancy
Services, confirmed SAP as a competent choice enterprise level financial
and resource management system for Oxfordshire County Council. This
review confirmed however that the existing implementation of SAP fell
short of expectations. In its then current state SAP would not be able
to support organisational change and development and would not be able
to underpin effectively the actions to gain financial control recommended
in the RSM Robson Rhodes report.
- In September 2004
the Executive approved proposals for a two phase programme to address
shortcomings in the Authority’s implementation of SAP and to enable
effective exploitation of the investment made. The Executive agreed
a virement of £1m in 2004/05 for Phase One of the Project; Council on
15 February agreed funding of £2m for each of the three financial years
2005/06 to 2007/08 to undertake Phase Two.
- This report is
intended to:
- record the progress
made to date;
- confirm the
overall approach to the substantive programme of work;
- identify and
recommend a programme of work, commencing in April 2005, to maintain
project momentum, achieve early identified benefits and provide foundations
for future business change; and
- identify the
resources required to continue with the immediate programme of work
pending consideration of the full set of proposals and Business Case.
Phase
One: Work to 1 April 2005
- Following a competitive
tender LogicaCMG, having solid SAP and Business credentials, were appointed
as the Business Partner to work with an internal team to manage and
develop the project.
- A joint Programme
Management Team has been assembled with specialist LogicaCMG consultants
for each of the functional areas working alongside Oxfordshire County
Council staff in providing lead, direction and focus for each area.
Relevant Heads of Service are the business owners for each area. The
Authority and LogicaCMG have each appointed a Programme Manager and
a Business Change Manager for the programme.
- Overall programme
governance and ownership is focused through the Director for Resources
who is the Programme Sponsor. A SAP Programme Board, comprised of senior
members and officers of the County Council and senior supplier representatives
meets at least monthly to guide and direct the conduct of the SAP Revitalisation
Programme.
- The prime deliverables
in the first stage of the project are to:
- define and implement
a common chart of accounts for use by all directorates,
- establish a
basic operational reporting structure and methodology for future reporting,
- deploy standardised
budgeting,
- create sustainable
SAP support environment,
- create a focused
SAP development authority,
- analyse the
options for meeting the needs of Schools and
- study and verify
business cases for the deployment of e-Procurement, integrated human
resources functionality (including integrated payroll, and Employee
and Manager self service) and a shared service approach.
- There has been
specific focus on the work required to address the core requirements
to make SAP a reliable and consistent financial system for the Authority.
This will be the foundation for further development throughout the 2005/2006
financial year and is consistent with the implementation of the RSM
Robson Rhodes recommendations. The project team have worked with a range
of staff in order to develop a coherent and workable approach for which
internal ownership exists.
- By 31 March 2005
the SAP Revitalisation Programme will have delivered the following in
the Finance Area:
- A revised and
significantly reduced chart of accounts, with some 330 fewer non pay
general ledger codes used. This is applied in a consistent manner
across all Directorates. Further simplification and rationalisation
of coding will be achieved progressively through operational business-as-usual
activities. There is further scope to significantly reduce employee
related codes as part of the work in the HR area.
- An agreed process
for the authorisation and management of additions and changes to the
Code structure and the standard application of agreed changes across
all Directorates.
- Remodelled cost
and profit centre hierarchies have been defined and implemented with
a consistent and standard structure across Directorates. This is aligned
to and reflects the management structure of the organisation and will
enable improved budget monitoring and reporting.
- An agreed, documented
and mapped standard budget setting process.
- A common timetable
and process for the production of budget monitoring reports and associated
period end processes.
- An initial training
programme to support the changes being made and address remedial requirements
to improve overall competency and understanding in SAP.
- A review of
all systems that interface with SAP, with prioritised recommendations
on the work to be undertaken on each to ensure the auditable and consistent
collation of financial information. This may include transfer of the
financial functions into SAP. This is based on the principle that
SAP is the master source of financial information for the Authority
and is to be the sole source of accurate reporting.
- A roadmap of
activities for the 2005/6 financial year to build on the initial work
and develop financial management, control and reporting derived from
SAP to the levels expected from the recommendations in the RSM Robson
Rhodes report.
- Recommendations
for the continuation of the programme of work in the finance workstream
are included later in this report.
- It is recognised
that accurate financial reporting and commitment accounting can only
be achieved by the adoption across the Authority of the consistent use
of e-Procurement functionality within the SAP environment. It has been
determined that there are three complementary strands of activity.
- To utilise existing
SAP procurement processes for defined areas of expenditure where full
e-Procurement would not be applicable.
- To include integration
of purchasing activity as part of the interface work emanating from
the finance workstream for each separate system that supports purchasing.
- As existing
SAP processes are not straightforward to use, to examine the adoption
of an e-Procurement approach for the majority of users.
A
business case is being constructed to examine the true potential of
this approach. However, this report recommends the early adoption
of the existing SAP purchasing process for a small number of expenditure
categories.
- The investigation
into SAP support activities will lead to the bringing forward of a proposal
for the development of a SAP Competency Centre as the appropriate means
to address the full support requirements for the operation of SAP. This
report includes recommendations for activities that will lead to early
improvements in the capacity to support SAP which are necessary in respect
of the other system changes that are being made.
- The detailed investigation
into the requirements of the schools has been supported by the active
engagement within the project of a secondary headteacher and a school
bursar. It is expected that proposals will be brought forward in the
business case that, if accepted, could lead to a significant improvement
in the ability of schools to be able to manage their own activities
together with an improved and streamlined interface with the County
Council.
- Business cases
are also being prepared for an integrated approach to the use of SAP
in support of HRand payroll activity, and for the potential for the
adoption of Shared Services arrangements within the Authority.
- In a complementary
piece of work external to the SAP Revitalisation Programme an investigation
into the interface between SAP and the Social & Health Care ABACUS
system has been undertaken. An initial assessment of the way forward
has been presented and a detailed proposal is currently being prepared.
Finance
Area work in 2005/2006
- The work undertaken
during this initial period lays the foundations for a stable and consistent
approach to financial management and control through a consistent application
of SAP. Throughout the next financial year there will need to be continued
systems, reporting and business process work to build on these foundations.
This will be complementary to and alongside the work to implement the
Financial Management Implementation Plan. Benefit and improvement from
system and process changes will be progressively obtained throughout
the year.
- The target outcome
for the programme is for SAP to be relied upon as the master financial
system for the Authority, with all reporting and financial management
emanating from the system. Progress towards achieving this is dependant
upon the roll out of procurement through SAP to enable accurate commitment
accounting. It also depends on the implementation of interfaces with
all financial systems external to SAP to gain the desired level of control
and financial visibility.
- The workplan for
2005/2006 will include:
- Progressive
inclusion of commitment accounting in line with the deployment of
Purchase Order functionality.
- Extending Cost
Centre Manager access to SAP.
- Agreed actions
in respect of external non-SAP systems through the development of
appropriate interfaces or the transfer into SAP as appropriate.
- Adoption of
a consistent and auditable approach to grants management.
- Rationalisation
of Payroll General Ledger codes.
- Inclusion of
Managed Bank Accounts.
- Developments
of Management Accounting, Budget Setting and monitoring techniques
through the standard use of SAP functionality, forecasting and planning
facilities.
- Extended training
and support.
- Improvements
in period end processes, especially around depreciation, recharges,
accruals, settlement and cash flow forecasting.
Business
Cases
- The Business Cases
and detailed workplan for the SAP Revitalisation Programme will be considered
by the SAP Programme Board at its meetings at the end of March and the
end of April. It is planned that these will then be brought forward
to the Executive early in the "new" County Council. It will not be feasible
to bring these forward at an earlier juncture.
- An outline three
year plan will be proposed for the implementation of system and associated
business changes together with benefits realisation.
- It is important
for the Authority that progress and momentum is maintained on the programme
during the period while the Business Cases and plan are being finalised
and considered. There are a number of activities that are essential
to continue, and a number of opportunities have been identified to initiate
activity to deliver early benefit that would not be in conflict with
any proposals coming forward as part of the Business Cases. It is the
intention within the programme to continue with these throughout the
period April to June 2005 pending consideration of the full Business
Cases and programme plan.
Immediate
Workplan
- The in-house Programme
Team that has been established initially on a temporary basis will be
confirmed as permanent for the coming year. This will provide the necessary
focus and continuity for the planned work. It will also enable the more
significant change programme arising from adoption of Business Cases
to be effectively defined, commissioned and prosecuted within the Authority.
The majority of this team has been established through transfer from
other duties. In some instances, duties do not directly translate into
programme activity so it is necessary to provide for backfill to ensure
operational continuity. This will attract a cost estimated to be £160,000
in 2005/2006. The associated costs with maintaining the LogicaCMG input
on Programme and Change Management over the period to June 2005 is estimated
to be in the region of £122,000.
- It is planned
in the period between April and June 2005 that the main areas of work
in the Finance Workstream will be:
- Complete a blueprint
design and prototype processes for Grants Management within SAP.
- Review cost
centres to identify the feasibility of simplifying the current cost
centre structure by making greater use of internal orders for analysis
of costs; implement a trial and initiate some live running of Real
and Statistical Internal Orders within SAP to ensure understanding
of the scenarios in which internal orders should be used.
- Undertake a
technical investigation into the use of Personnel Cost Planner which
is part of the HR/Payroll module; this can be used for salary forecasting
and forward planning.
- Investigate
the application of the use of Planned Assessments for the allocation
of internal recharges; instigate a pilot trial.
- Undertake a
Training Needs Analysis to support the work initiated through the
Financial Management Implementation Plan in relation to the roles
and responsibilities of Cost Centre Managers leading to increased
financial competency and skill.
- Further refinement
and implementation of Standard SAP reporting resulting from the modification
to the Chart of Accounts and the re-modelling of Cost and Profit Centre
Hierarchies.
- Investigate
the possibilities of automatically transferring Statistical Key Figures
for output cost reporting from the information systems of other SAP
System application components; pilot a trial.
- Improve Period
End processes by completing technical investigations and preparing
plans for the introduction of monthly depreciation, improvements in
the allocation of recharges and the changes necessary to transfer
to monthly accruals.
- Investigate
the current procedures for forecasting cash flow and produce a blueprint
and prototype example for improved Cash Flow forecasting.
- Completion of
training in support of initial system changes.
It
is assessed that consultancy support from LogicaCMG for this work
during this period will amount to some £66,000.
- It is proposed
to implement in this period the existing SAP/R3 purchase functionality
for defined spend categories such as utilities and rates. The rationale
for selecting these particular expenditure categories is that they involve
a significant amount of expenditure; a small and manageable number of
users and processes defined now will not be in conflict with any future
developments such as e-procurement. The following benefits will be realised:
commitments will automatically be generated and updated; control and
visibility will be greatly enhanced; knowledge and expertise in the
operational use of SAP purchasing will be developed; and there is potential
for some efficiency improvements particularly around invoice processing.
It is proposed that the in-house team be supplemented with a permanent
position whose initial function will be to provide support to the roll
out of the existing SAP Procurement process. They will develop procurement
expertise and join the support team. This will attract a cost estimated
to be £32,000 p.a. Consultancy support required during this period is
estimated at £48,000.
- There exists only
a small cohort of SAP training expertise within the Authority. This
is insufficient to support the demands that the SAP Revitalisation Programme
will generate in future. Nor will it be sufficient to support the sustained,
consistent and effective use of SAP across the organisation. The SAP
Revitalisation Programme has sought to satisfy immediate training needs
through the identification and release of staff from operational duties.
This has proved ineffective and will not be sustainable over the longer
term. A continuation of this approach is likely to become a significant
risk to the Programme. It is intended therefore to appoint an additional
3 full time trainers to the SAP training team to provide organisational
capacity for the future. A cost of around £102,000 per year can be anticipated.
- It is important
that some early improvements in the arrangement for SAP support across
the organisation are achieved to overcome existing inadequacies and
to enable the improvements arising from the SAP Revitalisation Programme
to be supported. Five actions are proposed.
- To locate formally
the SAP support function as part of the Programme structure to achieve
alignment between support and programme activities.
- To initiate
process changes to ensure that the support centre is the agreed authority
for the management and support of SAP.
- To achieve separation
between operational and SAP support duties for those finance related
staff currently engaged in both activities.
- If necessary
to recruit up to 2 FTE to enable this separation and to recruit an
SAP HR specialist to ensure continuity of support on existing SAP
HR functionality where this is not provided at present (this will
incur an annual cost of up to £102,000 p.a.); and
- to initiate
an advanced training programme to raise the competency, understanding
and skills levels of those identified to involved in SAP support operations.
- Additional items
of expenditure likely to be incurred are assessed at this stage will
amount up to £50,000. These include additional ITNet costs and other
incidental expenditure.
Resource
Plan
- A supplementary
budget provision of £1m was made available during 2004/2005 to fund
the first phase of this programme. A further £6m budget allocation over
three years has been agreed to support the programme subject to acceptance
of the Business Cases and approval of intended work.
- Of the initial
allocation of £1m it is now forecast that approximately £800,000 will
have been used by the end of March. This is anticipated to be £700,000
consultants’ fees with LogicaCMG, £60,000 OCC staff-related expenditure
and £40,000 other incidental items (accommodation, ITNet costs, telephony,
IT, meeting rooms etc.). This will leave a balance of approximately
£200,000 at the end of the year.
- There is likely
to be an outstanding contractual commitment to LogicaCMG of approximately
£120,000 for the delivery of Phase One of the Programme.
- It is proposed
to carry the balance forward in support of the immediate work programme.
- The total cost
of the initial work programme outlined in this report is estimated to
be some £680,000. It is proposed that the difference between this and
the carry forward be met from an allocation of up to £480,000 from the
£2m budget allocated to SAP Revitalisation Programme for 2005/2006.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:-
- endorse
the immediate workplan outlined in the report;
- approve
the carry forward of the unspent Phase One project budget, estimated
to be £200,000, to support the identified work;
- approve
the expenditure of an initial £480,000 out of the £2m SAP Revitalisation
Budget for 2005/06 in the carrying out of this programme of
work.
JOHN
JACKSON
Director of
Resources
Background
papers: Nil
Contact
Officer: Mike King. SAP Programme Manager, Tel (01865) 816047
March
2005
Return to TOP
|