|
Return
to Agenda
|
Division(s):
Headington, Quarry, Old Marston, Wheatley
|
ITEM EX15
EXECUTIVE
– 7 SEPTEMBER 2004
A40 HEADINGTON/GREEN
ROAD ROUNDABOUT IMPROVEMENTS
Report by
the Head of Transport
Introduction
- This report:
- summarises the
technical case for and the results of consultation on improvements
to the Green Road Roundabout, which was held in May and June 2004;
- seeks approval
to include the development of contract stage for the long term measures
in the 2005/6 Capital Programme to achieve a target construction start
in spring 2006, subject to adequate funding in the following year;
and
- outlines a procurement
route and seeks the retention of Transport Consultants Faber Maunsell
as design consultants for the contract procurement and detailed design.
Background
and Technical Case
- The westbound
A40 approach to the Green Road Roundabout suffers from heavy congestion
at all times of the day with average queues of approximately 1100 metres
forming during the morning peak period. Long queues also form on the
southbound A40 and the A4142 Eastern Bypass during morning and evening
peak periods.
- Faber Maunsell
have investigated the best form of improvement to the existing Green
Road Roundabout. This work was put before the Executive at the 4 March
2003 meeting. The Executive agreed that the long term measures to signalise
the roundabout be developed further and consultation undertaken.
There are also short and medium term measures, an eastbound bus lane
on the A420 London Road approach to the roundabout and traffic signals
on the two junctions of Waynflete Road with Bayswater Road. These were
approved for implementation by the Transport Implementation Committee
on 8 January 2004 following consultation and exhibitions in late September
2003.
- New traffic surveys
were conducted on Thursday 16 and Friday 17 October 2003. These were
to establish more robustly what the unsuppressed demand flows were on
all approaches of the junction for every day of the week. Additional
queue length surveys were also carried out on all five arms of the roundabout
during morning, off-peak and evening peak periods. This new survey information
was used to remodel the signalised junction proposal prior to the scheduled
spring public exhibition on the long term proposal. For this an active
VISSIM computer model simulation of the proposed new layout was prepared
by Faber Maunsell. The conclusion of this technical assessment is that
the signalised ‘throughabout hamburger’ roundabout improves the junction
operation significantly at peak times. The junction operates within
capacity up to the year 2019.
- The main reason
that the proposed ‘throughabout’ roundabout works is that it allows
both (eastbound and westbound) A40 traffic flows to go in the same phase
of the signals. The ‘throughabout’ reduces into 3 stages what would
have to be a 4 stage signal operation on a standard roundabout. This
produces significant capacity improvements which are demonstrated by
the computer model.
Consultation
- The VISSIM model
and the other consultation materials were prepared in consultation with
the Executive Members for Transport and Sustainable Development.
- Public exhibitions
showing the proposed long term scheme (see Annex 1) (download
as .doc file) were organised on 26, 27 and 28 May 2004 and held
in areas most affected by the proposed changes, namely Barton, Headington
and Risinghurst. Most exhibition materials, including the questionnaire,
were also published on the County Council website. The closing date
for receipt of comments was 30 June 2004 and Faber Maunsell have analysed
all of the qualifying responses and written a report of the findings.
The report is in the Members’ Resource Centre with key findings being
detailed in paragraph 9 below. A full size drawing showing the long
term proposals will be displayed at the meeting.
- The analysis of
all responses generally confirmed the results of the earlier consultation
in September 2003 which showed strong support for the proposed improvements.
(See Annex 2) (download as .doc
file).
Key Findings
- The key findings
of the consultation demonstrate that the majority of local people are
convinced of the merits of introducing a signalised ‘throughabout’ to
resolve the safety, capacity and operational problems at Green Road
Roundabout:
- Nearly three quarters
of respondents were in favour of the proposed conversion of the Green
Road Roundabout to a signalised ‘throughabout’.
- Two thirds of
the respondents were in favour of the bus pre-signal with just under
a fifth being opposed.
- Nearly two thirds
of respondents were in favour of the temporary closure of Access 1.
- Over three quarters
of respondents were in favour of the signalisation of Collinwood Road.
Principal
Local Issues
- Although the bulk
of the detail from the latest consultation is given in Annex 2
(download as .doc file) and
the background document report by Faber Maunsell, the three main issues
related to residential areas immediately affected by the works require
comment here in the main body of the report.
Access
from Bayswater Road for Barton
- There are concerns
about the queuing on Bayswater Road and that this is exacerbated by
significant wider use by non-local traffic. Although a signal phase
cannot be provided in the scheme on this exit the overall queuing is
predicted to be much lower than at present because phasing of lights
on other exists would create sufficient gaps for Bayswater Road traffic
to emerge.
- This view has
created some doubt among residents of Barton and therefore it is necessary
to give an account of why Bayswater Road cannot be signalised. This
is mainly due to the physical road layout and space restrictions of
the storage area on the circulating carriageway of the roundabout, opposite
Bayswater Road, which would not be sufficient to accommodate even a
very small number of vehicles queuing at the stop line. During the red
phase for that stop line exit to Bayswater Road would be blocked by
those vehicles which would cause grid lock of the whole system.
- Some clarification
can also be made to the proposed pedestrian measures north of the roundabout
below Waynflete Road. The existing Pelican crossing on Bayswater Road
will need to be repositioned nearer to the roundabout, however a pedestrian
phase at the proposed Waynflete Road signals will be provided to maintain
a convenient crossing point for students, and enhance the existing provision
overall.
Risinghurst
Issues
- It is important
to acknowledge the concerns Risinghurst residents have about their own
access, servicing of the shops and use of the area by non local traffic.
It is predicted that improved performance of the newly signalised roundabout
will significantly reduce the need for through traffic to divert through
the area. Traffic Management measures developed during detailed design
will consider appropriate traffic restraining measures within Risinghurst.
While some traffic restraint may be necessary during the road works
construction officers consider that there is no need to impose severe
restrictions on accessibility for local residents in the long term.
- There was strong
support (76%) for the Signalisation of Collinwood Road, the two gap
closures and bus Pre-signal were also supported. This is detailed more
fully in Annex 2.
- The temporary
closure of Access 1 is essential during the works and the permanent
closure of Access 2 is required to provide the bus pre-signals.
- There is enough
support for the temporary closure of Access 1, but making it permanent
attracts less support and the intention is to monitor traffic behaviour
on The Roundway and make a decision on permanent closure of this access
way once construction works have been completed and traffic levels stablised.
- The junction with
Collinwood Road is currently used as a diversion route when queues ahead
at the roundabout are observed. It is also an important access and egress
point for residents, however the right turn in and out is hazardous
with an accident rate of 10 in the 3 year period 2001 to 2003. New signals
would effectively improve the safety of this junction including pedestrian
movements across the A40 between Risinghurst and Barton for local schools.
- The considered
view of officers is, however, that the performance improvements of the
main roundabout signalisation should be demonstrated before a decision
on the signalisation of Collinwood Road is taken.
Quarry
Issues
- There are some
Quarry residents who are very concerned about the impact of the construction
works on traffic levels through their narrow streets, however the consultation
results show that the majority of Quarry residents support the long
term proposals.
- While a permanent
traffic calming scheme for Quarry is included in the future OTS capital
programme (2007/2008), it is officers’ view that this should be brought
forward and progressed independently with the intention of implementing
it, subject to consultation, prior to the start of the main work at
the roundabout. If additional temporary restraint measures are identified
during the consultation process to deal with diverting traffic during
construction, these can be included for later removal.
Programme
and Procurement of Design and Construction
- The budget requirement
for the final third stage is of the order of £2.386M: see attached Project
Appraisal (Annex 3).
- Following the
strong support expressed during the consultation officers recommend
that measures are approved for implementation with a construction target
start in spring 2006, subject to funding. The construction phase is
likely to take 4-6 months due to the sensitivity, complexity and the
diversity of specialised teams required to undertake various elements
of the work.
Short
Term Measures
- The introduction
of a bus lane on the approach to the roundabout from Oxford is scheduled
for this financial year. The Legal Orders were published recently and
construction should be complete before Christmas.
Medium
Term Measures
- Officers now consider
that the traffic signals on Waynflete Road should be completed with
the main works provided there are no serious unforeseen delays to the
implementation of the long term proposals. The signalised ‘throughabout’
considerably reduces queues on Bayswater Road and eliminates the need
for the second set of signals at the northern junction of Waynflete
Road with Bayswater Road, which were recommended to protect Wayneflete
Road from queue jumping traffic. The local member supports this strategy.
Supervision
and Accommodation of Traffic during the Works
- Supervision of
the construction of the scheme will be by our term consultant, Babtie
Group, with Faber Maunsell retained in a Project Manager role.
- The most critical
part of the construction of the scheme is the temporary traffic management
and minimising delay while achieving the fastest construction time.
For this reason early involvement of the contractor will be sought to
engage his particular expertise. By having the consultant and contractor
working together to produce the detailed design provides the best means
of achieving the lowest practical cost, cost certainty, and predictable
construction time. This can be awarded within the Contract Procedure
Rules by tendering at this preliminary design stage.
Selection
of the Scheme Contractor
- The contractor
will be asked to submit a "quality bid" which will concentrate on the
method of carrying out the works and a "price bid" based on the works
as drawn up at the moment (the design is sufficiently developed for
the work to be accurately assessed and priced). The contract award will
be made on a combination of quality and price with quality weighted
heavily in the evaluation. The cost of the detailed design when finally
developed will then be calculated and agreed using the prices the contractor
submitted at preliminary design stage. This has the advantage that the
price consequences of design decisions are known and the design can
be refined to minimise the cost.
- The initial contract
with the contractor will cover fee payments to assist and participate
in the design and associated accommodation measures. It will develop
the scheme and the start of works tender total based on agreed rates.
However the contract will allow the council to withdraw if there are
insufficient funds to start construction.
Retention
of Scheme Design Consultant
- Consultants Faber
Maunsell have a contract to produce the preliminary design, the stage
we are at now, because of their particular expertise in designing complex
signal controlled junctions. An extension is needed to carry out the
detailed design and project management. Faber Maunsell have submitted
a quotation for the additional work and officers believe it is in the
best interests of the Council to permit Faber Maunsell to project manage
and design the remaining parts of the scheme because the heart of the
scheme is the signal control and the inter-relationship of this with
the detailed layout of the new roundabout. To hand the preliminary design
on to another consultant for development, or to have Faber Maunsell
involved only as a specialist signals consultant, makes the design process
more complicated, allows for possible loss of control over all design
aspects, and risks not having the best solution to handle the traffic
through the junction.
Environmental
Implications
- Both early and
medium term measures give priority for buses. This will help to promote
public transport as an alternative to the private car. The provision
of traffic signals at Waynflete Road incorporating pedestrian phases
and relocation of the existing Pelican crossing will offer pedestrians
controlled crossing points of Bayswater Road linking the two halves
of the Barton Estate. The signals at the roundabout will also improve
safety and allow the junction to operate effectively for the next 15
years. The bus pre-signal enables buses from London direction to merge
safety with general traffic on the approach to the roundabout signals,
giving them at the same time priority with negotiation of the new roundabout.
Financial
and Staff Implications
- The total cost
of the scheme is £2.636M. £250K has been provided in 2003/04 and 2004/05.
A provision of £2.386M will need to be made in future Capital Programme
budgets as detailed in the Project Appraisal. The project is being managed
by existing staff with Faber Maunsell being retained as designers. Design
fees are included in the overall scheme cost.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- note
the outcome of the consultation as summarised in the report
and set out in more detail in the report of consultants Faber
Maunsell;
- approve
in principle the implementation of the long term measures as
detailed on the plan at Annex 1 to the report, with a target
construction start in spring 2006, subject to
consideration
of its inclusion in the Transport Capital Programme following
the settlement of the overall Budget and Capital Programme by
the Council in February;
- approve
the Project Appraisal attached to the report; and
- approve
in principle the acceleration of the Quarry Traffic Management
Scheme to 2005/06 subject to consideration of the necessary
adjustment to the Transport Capital Programme in the October
2004 update.
DAVID
McKIBBIN
Head of Transport
Background
papers: Faber Maunsell report on the latest consultation
Contact
Officer: David Clough Tel: Oxford 815743
24
August 2004
Return to TOP
|