|
Return
to Agenda
ITEM EX7
EXECUTIVE
– 6 JULY 2004
LOCAL TRANSPORT
PLAN – ANNUAL PROGRESS REPORT 2004
Report by
Head of Transport
Introduction
- The Government
requires each transport authority in England to submit an Annual Progress
Report (APR) on its Local Transport Plan (LTP) to the Government Regional
Office by the end of July each year. The purpose of this is to inform
the Government of how the authority’s LTP is being implemented, how
the funding allocations made through the LTP process are being used
and how well the authority’s own local and the Government’s national
targets are being met.
- The APR is also
used by the Government as the basis on which the indicative allocation
for future funding is confirmed or amended. This allocation in turn
forms a significant part of the County Council’s Supported Capital Expenditure
(SCE) (see Capital Programme Report 16 March 2004). The Government now
uses the rating given to each authority’s APR as an important component
for the Environment score of the Comprehensive Performance Assessment
(CPA). The APR is also the mechanism through which funding applications
for Major Schemes (i.e. schemes >£5 million) are made to the Government.
- The County Council’s
submission last year was highly successful. It was rated in the "Well
Above Average" category, with a score of 82%. This gave Oxfordshire
the ninth (equal) highest score out of the 123 authorities who produce
LTP’s. From this the County was given an allocation of £23.957 million
for 2004/05 including reward funding of £2.4 million (for demonstrating
good progress in the delivery of schemes and achievement against targets)
and a £0.336 million bonus for demonstrating particularly strong year
on year performance.
Requirements
- The latest Government
guidance has made it clear that, in this year’s APR, there is a strong
emphasis on delivery. The Government wants to see that the County Council
is meeting what it set out to do through its programme for 2003/04.
A copy of the guidance has been placed in the Members’ Resource Centre.
Compared to last year’s guidance the requirements are much more prescriptive:
they indicate not only what information should be included but also
how the Government wishes to see that information presented and how
it expects the document to be ordered. The Government wishes to see
the use of specified tables, graphs and pro-formas for the presentation
of the required data.
- APRs will be assessed
on 3 criteria:
- Delivery
on the ground
- Progress
towards targets and objectives
- An effective
spending programme
Unlike
the guidance requirements for the last APR, there is no requirement
for the County Council to provide case studies as evidence of how
it is meeting both national and local targets. Neither is there the
requirement to demonstrate improvement nor the use of consultation
and best practice to deliver the programme.
- There are three
new requirements for this year’s APR:
- A report
on the uses of performance-related funding;
- Trajectories
for targets and objectives (i.e. a graphical representation of
whether the targets are on track to be met); and
- Consideration
of the shared priority for transport.
Programme
- The programme
which will be set out for 2005/06 will be based on that provisionally
approved by the Executive on 16 March 2004 and would be confirmed by
the Executive in March 2005. A summary of this programme is set out
in Annex 1 .
This gives a total expenditure of £28.055 million. This figure is an
increase of £3.115m from the approved £24.94 million single capital
expenditure allocation for 2004/05; the major individual elements of
this increase are the start of town centre measures in Abingdon and
Witney and major expenditure on Green Road Roundabout. Delivery of this
programme would therefore depend on a funding increase being agreed
by the Government.
- As was stated
in last year’s APR, two schemes have been investigated as potential
major scheme bids for this year’s submission to Government: Expressway
Oxford (more commonly known as GTE) and Marcham Bypass. Neither of the
schemes would have required funding support this coming year - either
submission would have asked for an ‘in principle’ support from Government
with the scheme being conditionally accepted for funding subject to
it meeting all statutory requirements for its construction.
- As has been widely
reported, the feasibility study into the viability of the GTE scheme
has provisionally concluded that the proposal, as currently envisaged,
would not meet the Government’s indicative economic target for acceptance
as a major public transport scheme. However, the rationale for the GTE
scheme, the provision of reliable (congestion-free) and efficient public
transport links from Oxfordshire’s larger towns and Park and Ride sites
into the City Centre to support growth pressures and aspirations, is
still highly relevant. Studies are therefore underway to ascertain whether
a revised scheme that would meet Government economic criteria can be
devised. Consequently it is not considered that there is any purpose
to be gained by completing and submitting the bid at this time.
- Work on Marcham
Bypass is progressing towards a planning application being made later
this year. The current indicative programme for this scheme is as follows:
September
2004 Planning Application
January 2005 Determination
of Planning Application
Spring 2005 Publication
of Orders
Late 2005 Public
Inquiry
Late 2006 Secretary
of State’s Decision
Early 2007 Start
of works
- Whilst it is not
essential for Marcham Bypass to be submitted in this year’s APR, there
would be clear advantages in having it accepted as part of the current
Local Transport Plan rather than carrying it forward for a decision
to be made as part of the next LTP programme. In particular the Government
stated in the guidance for this LTP period that "few authorities could
expect to have more than one … major scheme approved during the five
year plan period." It is likely that a similar restriction will apply
in the next LTP period. Consequently it is considered that a major scheme
submission for Marcham Bypass should be made this year.
- Marcham Bypass
was approved by the former Environmental Committee on 19 September 2001
and officers were authorised to prepare the necessary Planning Application
and Orders. As part of the investigation for this, some amendments to
the scheme have been suggested. While the majority of these are minor
in nature and relate to ensuring that the bypass conforms to the current
design standards, it has been found that there are significant additional
benefits to be gained from extending the scheme to a new roundabout
junction with the A338, replacing the existing double traffic lights.
A plan showing this revised route will be on display at the meeting
and a revised project appraisal is being prepared for approval.
The Annual Progress Report
- Following receipt
of the guidance for the APR, officers have been working to produce an
APR which meets the Government’s requirements. The latest draft will
be placed in the Members’ Resource Centre. There are a number of issues
on which the advice of the Executive is sought before the text can be
finalised. These are set out below.
- Targets
– Stretching targets have been set for Oxfordshire’s transport network
and systems. There are a small number of the national and local objectives
that do not appear to be on track to fully meet the targets and therefore
a statement is needed in the APR as to what action the County Council
proposes to take as a result. It is considered that the best way to
handle these within the APR is to be open about the problems, explain
the actions already in hand and further actions for improving performance
against targets.
- Journey to
work – following confirmation of the 2001 National Census figures
the County Council is still not on track to meet its target for the
percentage of Oxfordshire’s residents commuting to work on foot or
by bicycle. In fact the percentage for those walking to work has decreased
from 11.5% in 1991 to 10.2% in 2001, the figures for cycling to work
has also shown a decrease from 8.8% to 6.7%. It should be reported
in the APR that the County Council will do all that it can to reverse
these trends and continue to actively promote these modes of transport.
However the background of increasing commuting to work distances does
mean that it is likely to become more difficult in the future to alter
this trend. It is clear that a reliance on the National Census does
not provide a useful benchmark to assess progress. The need to develop
a local survey methodology for measuring pedestrian and cyclist activity
will be covered in the next LTP, to be submitted in July 2005.
- Number of
Bus Journeys – The County Council agreed a Public Service Agreement
with the Government to increase the numbers of journeys by bus up
to 2006. Our monitoring has shown an increase of just under 0.6% between
2002 and 2003. This is encouraging but is slightly less than the rate
that would be needed to meet the PSA target thereby highlighting the
need for further work in this area as a priority.
- Road Condition
– The lack of funding for maintenance of unclassified roads through
the 1990s has left the County with an increasing number of roads which
are at or approaching the point where structural maintenance needs
to be considered. It had been anticipated that the proportion of this
class of road needing work would increase but this increase has been
faster than our target. Our target in the future has to be to stop
this deterioration from continuing, although this is likely to be
only possible with a combination of efficiency measures and increased
resources available for this type of work.
- Bus Punctuality
– The figure for the proportion of buses on the subsidised bus
network which arrive not more than 5 minutes late has increased to
87.1% from 85.3% last year. This improvement has to be seen in the
light of the fall from 91.6% recorded in the base year of 2001. In
the light of these results the accuracy of this baseline figure has
to be questioned, and consequently the appropriateness of the target
of achieving 94% of buses punctual to this degree.
- On a more positive
note, we have managed to achieve a 10% reduction in the number of reported
cyclists’ casualties. The target that was set for 2010 was 311 per year,
last year only 303 casualties were recorded. Therefore, a new target
will need to be set for this as part of the next LTP.
- The overall situation
with regard to our targets is that of the ten national core performance
targets we are on track with seven and not on track with two (the congestion
target does not apply to Oxfordshire) while for the local performance
indicators we are on track with eleven and not on track with three.
Conclusion
- After the success
of the APR last year, where the County Council made significant steps
forward in the implementation of its LTP, it is important that this
year’s report maintains that progress. This year’s report should reflect
this and in turn result in a good financial settlement for 2005/06.
There are a few areas where progress has not been as good as expected.
There are no easy or clear solutions to any of the problems identified
this year, apart from the County Council continuing to promote alternative
modes of transport.
- The revised total
expenditure figure of £28.055m is an increase on the approved £24.94m
allocation for 2004/5. Therefore, for the delivery of this programme
to be possible, a funding increase from Government would be necessary.
Financial
and Staff Implications
- The APR is a vital
part of the process whereby the County Council receives approval from
Government for its capital spending on transport. The report to the
Executive on 16 March 2004 outlined the challenges that there have been
to implement a programme, which has continued to grow over the LTP period.
Continued investment at these levels is critical if the County Council
is to meet its overall transport objectives.
RECOMMENDATIONS
- The Environment
Scrutiny Committee resolved on 12 May 2004 to convene a Panel to consider
this report before it was submitted to the Executive. The Panel will
meet on 24 June 2004 and their comments will be reported to the meeting.
Subject thereto the Executive is RECOMMENDED to:
- authorise
the Director for Environment & Economy, in consultation
with the Executive Members for Transport and Sustainable Development,
to finalise the Annual Progress Report for submission to the
Government by 30 July 2004;
- agree
that a major scheme bid should be prepared for submission to
the Government for the Marcham Bypass as part of the APR submission
this year;
- agree
that no submission should be made to the Government for the
GTE Scheme at present, and note officers will provide the Executive
with an update on the scheme and alternative options in September/October.
DAVID
MCKIBBIN
Head of Transport
Background
papers: Nil
Contact
Officers:
Roger O’Neill Tel: 01865 815659
Daniel Round Tel:
01865 815623
June
2004
Return
to TOP
|