|
Return
to Agenda
Return
to EX9
|
Division(s):
Henley North, Henley South
|
ITEM EX9 -
ANNEX 1
EXECUTIVE
– 7 APRIL 2004
HENLEY INTEGRATED
TRANSPORT STRATEGY
Methodology
of the Study
The study was undertaken
in 4 stages, which are discussed below:
Stage
1(March – July 2003): understanding the existing situation
In
order to understand the existing issues in Henley a number of consultation
exercises were undertaken with local people in May 2003.
- A workshop for
key stakeholders was held;
- Face to face interviews
were undertaken in locations throughout the town and at different times
of the day;
- A focus group
was held at the Over 60s Club.
Each
of these consultation events was used to gain an understanding of how
local people viewed transport in Henley and also to ensure that any additional
schemes/improvements to be included were identified at an early stage.
The
results of the consultation exercises were presented by Halcrow at a Members’
Steering Group meeting held on 23 July 2003, and were also detailed in
the Stage One Report. The Group agreed those issues which were recommended
to be specifically addressed at Stage Two. An outline of the schemes which
could be used to address the issues was also included.
Stage
2 (July – October 2003): scheme reassessment and potential scheme proposals
This
stage looked in more detail at those schemes which were approved at Stage
One. The key tasks at this stage included a review of existing parking
policies, analysis of available traffic data, the consideration of traffic
management options and the development of a traffic model for the town.
The
output of Stage Two was a report detailing the work undertaken and concluding
with recommendations on which schemes should be pursued to Stage Three.
These recommendations were presented by Halcrow at the 29 October 2003
meeting of the Members’ Steering Group, where the emerging strategy was
approved. It is important to note that at this stage Halcrow recommended
that a separate parking study be undertaken for Henley, due to the complexity
of the parking situation in the town. Members agreed this approach.
Stage 3 (October
2003 to February 2004): consultation and scheme prioritisation
Further work was
undertaken in Stage Three to consult on and refine the output of Stage
Two. This further consultation included:
- A stakeholder
workshop, including the same people who attended the first workshop,
in November 2003;
- A public exhibition
in the Town Hall, which was attended by approximately 350 people, in
December 2003;
- An ‘open surgery’
for members of the Steering Group in January 2004.
At the stakeholder
workshop and public exhibition provisional scheme plans were presented
for consultees to comment on. The comments were then used to refine the
scheme plans before they were presented at the members’ open surgery event.
The details and conclusions
of Stage Three were presented in a Draft Final Report at the Members’
Steering Group meeting on 5 February 2004, along with a suggested implementation
programme.
Stage 4 (February
2004): final reporting
Following
the comments made on the Draft Final Report at the February Members’ Steering
Group meeting, a Stage Four Technical Note was produced which reflected
these comments and addressed the concerns which had been raised. It also
included the implementation programme which had been agreed at the meeting.
This updates the Stage Three Report and should be read in conjunction
with it.
Return to TOP
|