|
Return
to Agenda
|
Division(s):
Witney North and South
|
ITEM EX7
EXECUTIVE
– 23 DECEMBER 2003
WITNEY INTEGRATED
TRANSPORT AND LAND USE STRATEGY
Report by
Acting Head of Transport
Introduction
- The purpose of
this report is to update Members on the progress made on developing
the Witney Integrated Transport and Land Use Strategy and to seek approval
for the revised Strategy. Copies of this document (and the original
Strategy it updates) have been placed in the Members’ Resource Centre
and are available for public inspection.
Background
- Consultants Llewelyn-Davies
were commissioned jointly, by Oxfordshire County Council, West Oxfordshire
District Council and Witney Town Council, in 1996 to carry out the Witney
Integrated Transport and Land Use Study (WITS) and produce a strategy.
A strategy was approved by the County Council on 11 June 1997 but not
by West Oxfordshire District Council or Witney Town Council. A subsequent
bid for government funding via a Transport Policies and Programme package
bid for Witney was unsuccessful.
- Funding has since
been allocated for the implementation of transport measures in Witney
from the Local Transport Plan. However, due to the indeterminate position
of WITS (as it was never formally adopted by the District Council or
the Town Council), it was not felt possible to develop a comprehensive
programme of schemes until a revised Strategy was agreed.
- To enable a programme
to be identified and additional funding allocated, the Strategy needed
to be reviewed and agreed by all three Councils. A Joint Members Steering
Group (comprising three Members from the County Council, three Members
from the District Council and one Member from the Town Council) was
therefore reconvened in January 2002 to oversee the development of the
Strategy.
- The background
to the development of the Strategy is set out in more detail at Annex
1.
Principles
of the Strategy
- There were three
main overarching principles for the review of WITS:-
- that a Strategy
must be agreed by the Joint Members Steering Group and by all three
Councils;
- that there must
be an agreed statement / set of objectives; and
- that the Strategy
must be consistent with National and Local Transport and Planning
Policies and other major schemes planned for the town and the surrounding
area.
- The Strategy document
includes a statement / set of agreed aims (which are reproduced at Annex
2) and these aims accord with relevant national
and local planning policies, as explained in more detail in the main
Strategy document.
The Strategy
- The Strategy has
been developed as a package of measures that work together to help to
improve safety, the environment and access for all modes. It includes
a number of key proposals:-
- proposals for
the improvement of the High Street / Market Square;
- a Parking Management
Strategy;
- improvements
to cycling and walking (for example the development of new routes
and crossing facilities);
- public transport
Improvements (such as measures to assist buses); and
- changes to the
road system e.g. traffic management.
- Much of the original
Strategy has been retained. Revised work has focused on areas that could
not be agreed previously, notably the proposals for High Street / Market
Square and Parking Management.
High Street/Market
Square
- The need for a
scheme to improve the environment in this area of the town has arisen
for a number of reasons which include: -
- Witney will
continue to see a growth in population which will have implications
for the town centre;
- there is a need
to redress the balance between vehicular traffic and pedestrians in
the town centre; and
- enhancements
to the environment will ensure that the town centre remains attractive.
- It was therefore
agreed to develop options for an Environmental Improvement Scheme for
High Street / Market Square, with the following aims: -
- to maintain
accessibility to Witney town centre for all users in order to protect
and enhance its vitality and viability;
- to maintain
and enhance the attractiveness and pleasant environment of the town
centre for shoppers and all users; and
- to reduce unnecessary
traffic using the High Street as a through-route by encouraging it
to use other available routes.
- In order to determine
principles of a scheme for High Street / Market Square for inclusion
in the Strategy, consultation was undertaken with the public and stakeholders.
Respondents were asked to state their preferred scheme from a choice
of three options which were: -
- Option One
- A maintenance based scheme with some limited environmental improvements.
- Option Two
- Pedestrian enhancements (such as carriageway narrowing and pavement
widening) with complementary measures designed to reduce through traffic
(for example banning certain vehicle turns).
- Option Three
- Pedestrianisation between Market Square and Welch Way (with exemptions
for some vehicles, e.g. buses).
- More details of
the consultation exercise, which also covered other transport issues,
are provided in paragraphs 18 to 20 of this report and Annex 4 (download
as .rtf file). There was a clear message from respondents that
improvements are needed in High Street / Market Square with the majority
voting for either Option Two or Three, as shown in table A3, Annex 4.
However, as there was no overwhelming support for any one option (particularly
in the context of individual comments given), it was agreed to keep
options open at this stage and agree the principles of the scheme through
the Strategy. Therefore, it has been agreed that the scheme should include
the following key elements: -
- environmental
enhancements;
- measures to
improve pedestrian facilities;
- measures to
reduce through traffic; and
- measures to
enable the northern and southern sections of High Street to become
more integrated.
- Detailed measures
could include: widened pavements, general improvements to surfaces and
signage throughout High Street/ Market Square, improved pedestrian crossing
points and / or more pedestrian crossings, restrictions on traffic entering
High Street / Market Square, traffic management / calming features in
the northern section of High Street and a review of on street parking
provision, including provision for disabled drivers.
- The Steering Group
identified the need to adopt an incremental approach to introducing
these measures. This would allow further improvements beyond those identified
above to be made at a later stage, for example some form of pedestrianisation
in High Street, should this be considered feasible and appropriate.
Parking
Management
- Local concern
was expressed about the parking proposals included in the original (1997)
Strategy document, which included proposals to introduce parking charges.
To enable the County Council to bid for funding for transport schemes
in Witney via the Local Transport Plan it was agreed (in 1999) that
a new Parking Management Strategy should be produced that would be monitored
and reviewed. The details of the Strategy that have been agreed so far
have focused upon off street public parking and can be seen at Annex
3. The updated Strategy proposes that "the
County and District Councils develop a more comprehensive Parking Management
Strategy for the town, to be consulted upon in more detail" to include:
-
- a detailed review
of the existing parking provision (looking initially at on-street
public parking); and
- a detailed study
of options for managing parking and their impacts upon the surrounding
areas, particularly the impact upon residential streets.
Major
Schemes
- In addition to
the schemes identified in the Strategy a number of major schemes for
the Witney area are being developed separately. These include Cogges
Link, the West End Link, the A40 / Downs Road junction and the A40 Strategy.
Whilst these schemes are not directly proposed by the Strategy it is
important that these are taken into consideration since they will have
an impact upon traffic management in the town.
Consultation
- A public consultation
exercise was held between March and October 2003, and comprised questionnaires
attached to an information leaflet (shown at Annex 4) (download
as .rtf file), a staffed exhibition in Witney Town Centre, unstaffed
exhibitions at Witney and Carterton Libraries, face to face interviews
undertaken by an independent market research company and a separate
consultation exercise with local businesses (specifically in the High
Street / Market Square area to obtain their views, particularly in relation
to the High Street / Market Square proposals).
- Two thousand and
ninety three responses were received to the questionnaires and household
surveys and 700 people attended the exhibition over the course of three
days. The results of the consultation exercises are shown in tables
A1 to A9 (Annex 4) (download
as .rtf file).
- Further consultation
will take place on the individual schemes contained within the Strategy
when these have been designed in detail.
Strategy
Approval
- The Strategy was
approved by the Witney ITS Joint Members’ Steering Group on 21 October
2003 and is due to be considered by West Oxfordshire District Council’s
Cabinet and Witney Town Council on 3 December 2003. Their views will
be reported orally.
Progress
so Far
- As identified
above, some Local Transport Plan funding has already been allocated
for Witney in 2002/03 and 2003/04, enabling some schemes to be designed
and implemented in advance of an agreed Strategy. Annex 5 (download
as .rtf file) identifies the schemes that have already been
constructed in Witney or are proposed for implementation shortly, and
also includes those schemes approved by the Members’ Steering Group
for feasibility, design and design and construction in 2004/05.
Strategy
Monitoring and Review
- A comprehensive
annual monitoring programme has been developed to help ensure that the
Strategy and the schemes contained within it are effective in achieving
the aims and objectives of the Strategy. A copy of the 2003 monitoring
report has been placed on deposit in the Members’ Resource Centre.
- The Joint Members’
Steering Group will also continue to meet (on a six monthly basis),
to oversee the Strategy implementation process and the approval of further
schemes and measures.
Financial
and Staff Implications
- There are no direct
implications arising from this report. Expenditure on individual schemes
in support of the strategy will be subject to programming and the availability
of funds in the usual way.
RECOMMENDATION
- The Executive
is RECOMMENDED to approve the revised Witney Integrated Transport and
Land Use Strategy.
RICHARD
DIX
Acting Head
of Transport
Background Papers:
(i) The original 1997 Witney Integrated Transport and Land Use Strategy
(ii) The
revised 2003 Witney Integrated Transport and Land Use Strategy
(iii) The
Witney Integrated Transport and Land Use Strategy Local Transport Plan
Monitoring 2003
Contact
Officer: Suzanne Roberts Tel: (01865) 815933
December
2003
Return to TOP
|