Return to EX7


ITEM EX7 - ANNEX 3

EXECUTIVE – 28 OCTOBER 2003

TRANSPORT CAPITAL PROGRAMME 2003/04 TO 2005/06

INDIVIDUAL SCHEME PROGRESS GAINST MAIN BUDGET HEADINGS

STRUCTURAL MAINTENANCE INTEGRATED TRANSPORT STRATEGIES

SUSTAINABLE TRANSPORT COMMUNITY SAFETY TRANSPORT

CASUALTY REDUCTION SCHEMES

STRUCTURAL MAINTENANCE 2003/04 APPROVED PROGRAMME PROGRESS

Richard Dix (Assistant Director)

 

Scheme

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Carriageway Schemes

 

 

Principal Roads

 

 

A4130 Didcot – A34 Milton Interchange

Completed

 

A4144 Oxford – Abingdon Road Part 1

Completed

 

A417 Ardington

Delay to 04/05

 

A4095 Bladon

Work started

 

A417 Challow

Work ordered

 

A44 Woodstock Oxford

Delay to 04/05

Complete in ¾

Design and supervision fees

Completed

 

Non-Principal Roads

 

 

Oddington, Islip to Merton Road

Delay to 04/05

Complete in ¾

South Moreton, Fulscot

Work ordered

 

Upton, Hollow Way

Work completed

 

B4445 Sydenham, Sydenham & Towersey Turns

Work completed

 

Cumnor, Tumbledown Hill

Work started

 

Banbury, High Street

Delay to 04/05

Complete in ¾

North Newington, Shutford Rd

Work started

 

Britwell, Turners Green

Completed

 

Adderbury, The Green

Completed

 

Great Tew, The Lane

Completed

 

B4044 Cumnor, Eynsham Road

Completed

 

 

 

 

Bicester, Churchill Road

Completed

 

Surface Dressing

Completed

 

Patching with Surface dressing

Completed

 

Highway Drainage

Complete in 03/04

 

 

 

Scheme

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Footway Schemes

Complete in ¾

 

Bridge Strengthening Schemes

 

 

Barns Road Edge Beam Strengthening

Completed

 

Lauren Bridge Strengthening

Completed

 

A422 Hillary Bridge Plate Bonding

Design in ¾

 

Barford St Michael Strengthening

Design in ¾

 

Wycombe Way Subway Infilling

Design in ¾

 

Shillingford Structural Maintenance

Design in ¾

 

Other Schemes

Complete in ¾

 

Completion of Assessment of Railway Bridges

Complete in ¾

 

 

INTEGRATED TRANSPORT STRATEGIES 2003/04 APPROVED PROGRAMME PROGRESS

Dariusz Seroczynski (Group Manager)

ABINGDON ITS – SCP BUDGET

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Colwell Drive - cycle link improvements

Design only

 

Drayton Rd/Ock St/Spring Rd – traffic signals

Design only

 

Drayton Rd - ped/cycle crossing facilities

Design only

 

Marcham Road - widening phase 1

Construction Q4

 

Marcham Rd - phase 2 inc Colwell drive roundabout

Design only

 

Minor Jnc - Dunmore Rd/Boulter Drive

Design only

Design and Construct

Radley Road area - Barton Court cycle links

Design only

 

Shippon - Village Traffic calming

Design only

Design and construct

South Abingdon - area cycle links

Design only

 

Thames View - cycle improvements

Complete

 

Town Centre - Schemes Development

Design only

 

Twelve Acre Drive - cycle improvements

Complete

 

BANBURY ITS – SCP BUDGET

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Bear Gardens traffic calming

Complete

 

Clearway Signing

Complete Q3

 

Ruscote Ave/Beaumont Rd signals

Design only

Complete with Dev funding

 

 

continues

 

Signing Strategy - Hennef Way

    • Town Centre

Complete Q4

Defer Q1 04/05

Complete build

Station Improvements including Bridge St

Complete Q3

 

Station Dev – lift for disabled

Completed Q2

 

SCOOT

Complete 04/05

Complete build

Core Pedestrian routes study

Defer 04/05

 

Cycle route study including railway bridge

Defer 04/05

 

Parking Strategy study

Study complete Q3

 

North Bar/South Bar

02/03 work complete

 

Coopers gate ext to Spiceball park

Design only

 

BANBURY ITS – OTHER BUDGETS

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

George St/Cherwell St Bus priority

Completion Q1 04/05

 

Hanwell Fields 1 (Warwick Rd Toucans)

Completed Q2

 

Hanwell Fields 2 Toucans + cycle path

Complete Q4

 

Hanwell Fields 3 Southam Rd

Complete Q4

 

M40 Junction 11 – signal improvements

Complete Q4

 

Rother Rd Bus Gate

Defer to 04/05

 

Hanwell Fields off-site junction

Feasibility only

 

Hanwell Fields 4

Design only

 

BICESTER ITS – SCP BUDGET

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

Banbury Rd 2 off Gateways

Complete Q3

 

Banbury Rd Toucan/Pelican

Complete Q3

 

Buckingham Rd/Banbury Rd

Complete Q3

 

 

 

continues

 

Buckingham Rd to Murdock Rd cycle route

Complete

 

Bure Park to Banbury Rd cycle track extension

Complete Q3

 

Longfields/Churchill Rd cycle

Complete Q4

 

Post Skimmingdish signs/wt limits

Complete Q2

 

Middleton Stoney Feasibility

Survey only

Babtie Design

Churchill Rd Lorry Gate

Construction on hold

Construct

George St cycle & pedestrian study

Held – land issues

 

London Rd Crossing

On hold

 

Cycle Links to Bicester North station

Joint study with transport development

 

BICESTER ITS – OTHER BUDGETS

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Banbury Rd Toucan/Pelican

Complete Q3

 

Banbury Rd / Rowan Rd

Complete Q3

 

Buckingham Rd to Banbury Rd cycle route

Complete

 

Market Sq interim safety measures

On hold

 

Wessex Way prelim design & planning

On hold

HENLEY ITS – SCP BUDGET

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Bell Street / New Street Ped crossing

Work in progress

 

Completion of existing schemes

Work in progress

 

Improvements to footway and lighting on station access to Industrial Estate

Complete Q3

 

 

 

 

Kings Road Pedestrian Crossing

Complete Q4

 

 

 

OXFORD OTS – SCP BUDGET

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Botley Road Cycle Improvements

Design only

 

Radial Route Signing

Complete Q4

 

Wolvercote Roundabout improvements

Design only

 

Banbury and Woodstock corridor study

Study only

 

Rapid Response schemes

Urgent Minimal works only

Recover further urgent work

Green Road Roundabout Improvement

Design only

 

Cornmarket Street Bollards

Complete Q3-Q4

 

Cornmarket Street/George Street traffic signals

Complete Q3

 

Oxford, Cornmarket refurbishment

Work in progress

 

OXFORD OTS – OTHER BUDGETS

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

Summertown RPZ

Design only

 

North Oxford RPZ

Design only

 

Girdlestone RPZ

Design only

 

Headington North East RPZ

Design only

 

 

 

 

Headington Quarry RPZ

Design only

 

Headington Central RPZ

Design only

 

Beaumont Street Ped/cycle crossing

Design only

 

Between Towns Rd/ Garsington Rd signal Ped Stage

Design only

 

Marston Rd/Headington Hill Signal Ped Stage

Complete Q3

 

 

 

continues

 

Old Road/Gipsy Lane signal ped stage

Complete

 

London Rd Nr Latimer Rd Pelican Conversion

Complete Q3

 

Girdlestone Rd/Churchill new cycle Link

Complete Q4

 

Old Rd/Lime Walk Traffic calming/ improvement and Pelican

Design only

 

London Road and bus detection study

Study only

 

Oxford Rd/Cherwell Dr/Marsh Lane/Horseman Close pelicans

Complete Q3-Q4

 

Headley Way-St Josephs & Woodlands Rd pelicans

Complete Q3-Q4

 

Garsington Road Roundabout Improvements

Design only

 

Parks Road/South Parks Road Cycle Track

Complete Q4

 

Butterwyke Place to Friars Wharf cycle link

Complete Q3

 

Oxford Mosque Manzil Way parking controls

Complete Q4

 

Oxford United parking controls

Complete

 

Becket street lighting improvement

Complete Q3

 

George Street/ Cornmarket Street Cycle Parking

Complete Q4

 

Observatory Street Traffic Calming

Complete Q4

 

Marston Rd/Headley Way Mini Roundabouts improvements

Complete Q4

 

Headley Way/JR access improvement

Complete Q4

 

Tourist coach provisions -Study/Consultation

Study only

 

Horspath Driftway cycle improvements (city scheme)

City programme

 

 

 

continues

 

Old Headington cycle safety measures (city scheme)

City programme

 

Fairfax Ave/Purcell Rd cycle link

Design only

 

Cowley Corridor study

Study only

 

Hamat’s Studies

Study only

 

Cumberland Road cycle measures

Deferred to 04/05

 

Cowley Road Cycle safety measures

Deferred to 04/05

 

Banbury Road North of St. Margaret’s cycle facilities

Deferred to 04/05

 

Banbury Road/Marston Ferry Road Junction improvement

Deferred to 04/05

 

Summertown traffic management

Deferred to 04/05

 

Bus Gate camera enforcement

Deferred to 04/05

 

WITNEY ITS – SCP BUDGET

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

Bridge St, Mill St junc traffic signals

 

Design only

 

Burford Road/Downs Road

Design only

 

Coggs Footpath

Work in progress

 

Ducklington Lane to Henry Box, cycle route

Design only

 

Ducklington Lane cycle way

Complete Q4

 

 

 

 

Ducklington Lane, signals study

Study only

 

Moore Avenue & Dark Lane, traffic management

Prelim design and consultation complete. Further design/construction 04 – 05

 

Newlands/Oxford Hill cycle route

Complete Q4

 

Station Lane cycle route

Design only

 

Thorney Leys cycle route

Design only

 

 

 

continues

 

Thorney Leys pedestrian & cycle route

Design only

 

Town centre pedestrian improvements

Design only

 

Tower Hill, cycle path

Design only

 

Witney parking study

Design only

 

MAJOR PROJECTS

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

A40 Corridor

 

 

Banbury, Hennef Way dualling

Work in progress – other funding available

 

Finmere Diversion

Final Settlement other funding available

 

Marcham Bypass

Preliminary design other funding available

 

Oxford, Cornmarket

Work in progress - other funding available

 

Oxford, Thornhill Park and Ride extension

Complete – other funding available

 

Oxford, Thornhill Interchange

Design only – other funding available

 

Oxford, Water Eaton Park and Ride

Complete – other funding available

 

Witney, West End Link Road

Construction late Q4 – other funding available

 

 

SUSTAINABLE TRANSPORT 2003/04 APPROVED PROGRAMME PROGRESS

Noel Newson (Group Manager)

 

Scheme

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

Better Ways To School

 

 

To complete A, B and C programmes and start D programme

Completion of A and B programmes bar Abingdon and Watlington BWTS schemes, consultation and design of C programme and start D programme

Completion of Abingdon and Watlington BWTS schemes

Cycling Schemes

 

 

Horspath to Oxford

Completion Dec 03

 

North Leigh to Witney

Complete

 

Culham to Berinsfieldl

Deferred to 04/05

 

Hanborough to Bladon Pelican Crossing

Completion Nov 03

Ducklington to Witney, Stage 1

Completion 03/04

 

Abingdon to Drayton

Completion Feb 04

 

Benson to Wallingford, Stages 1 and 2

Design and construction start only

 

Sunningwell to Bayworth, Abingdon

Consultation and design only

 

Quick Response Schemes

Allocated to various projects

 

Development of Future Programme

Advanced consultation and design of future cycle schemes: inc. Ducklington to Witney (Stage 2), Wallingford to Cholsey, Thame to Shabbington, Wootton to Abingdon and Thame Town Network

 

National Cycle Network

 

 

Support for Sustrans Development of NCN

Contribution to various schemes

 

Public Transport

 

 

Rail Station Development

Hanborough improvements and development of proposals for Kidlington and Grove/Wantage

 

 

 

continues

 

Premium Routes

Scheme development for first routes and new shelters on Kidlington – Oxford corridor

 

 

 

Real-Time Passenger Information

Scheme development. Contract for pilot corridor (Kidlington – Oxford) awarded March 2004

 

Park & Ride Improvements

Development of Thornhill Interchange and Improvements

 

Bus Shelter Grants

 

 

Bus Enquiry Management System

Committed to Traveline database

 

Bus Stop Timings Database

Committed to Traveline

 

Lewknor Interchange & Improvements

£50k contribution deferred to 04/05

 

Cherwell Valley Taxibus Vehicle Grant

Committed

 

Wheelchair Accessible Bus Grants

Committed

 

Bus Stop Clearways - Phase 1

Implementated at locations highlighted in the Scrutiny Review

 

 

 

 

 

COMMUNITY SAFETY TRANSPORT 2003/04 APPROVED PROGRAMME PROGRESS

Brian Fell (Group Manager)

 

Scheme

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

A329/B480 Little Milton Route Action Phase 1 (Village Hall pelican)

Complete

 

A4185/Winnaway; Ped/Cyc Improvements

Contribution deferred to 04/05

 

A4260, Kidlington; Pelican Crossing

Complete

 

Adderbury, Oxford Road; Pelican Crossing

Consultation and design only

 

Appleton, Netherton Road; Footway

Completion Dec 03

 

CountryWays; 1st Pilot Project

Completion 03/04

 

Harwell, High Street; Pelican Crossing

Complete

 

Home Zones; Fees

Design fees only

 

Nettlebed, High Street; Pelican Crossing

Complete

 

 

 

 

Wantage, Charlton Rd; Pelican Crossing

Consultation and design only

 

Wheatley; Traffic Calming Phase 1

Completion of London Road and High Street sections. Ladder Hill section starts Feb 04.

 

A329/B480 Little Milton Route Action Phase 2

Consultation and design

 

CountryWays; 2nd Pilot Project

Consultation and design

 

Home Zones; contribution

Expenditure £50k with £100k deferred to 04/05

 

B4009/M40, Lewknor; Bus Interchange and Safety Improvements

Completion 04/05 (June 04)

 

Faringdon Market Place; contribution

Contribution to Market Place scheme

 

 

 

continues

 

Wheatley; Traffic Calming Phase 2

Design deferred to 04/05

 

Minor Traffic Engineering Programme

Programme budget halved to £137.5k

Programme budget reinstated TO £275K

Wallingford, Station Road; Raised Zebra Crossing

Completion Oct 03

 

South Newington, Barford Road; Traffic Calming

Completion Oct 03

 

Sandford-on-Thames, Henley Road; Traffic Calming

Completion Mar 04

 

Hanborough, Church Road, Long Hanborough; Traffic Calming

Consultation and design only

Completion 03/04

Cumnor, B4017 (Henwood); Traffic Calming

Completion Mar 04

 

Woodstock, A44 Manor Road; Traffic Calming

Consultation and design only

Completion 03/04

East Hanney, Steventon Road; Traffic Calming

Consultation and design only

Completion 03/04

Rollright, Hook Norton Road; Traffic Calming

Completion Mar 04

 

Bodicote, Whitepost Road; Zebra Crossing*

Scheme deferred to 04/05

Consultation and design only

Chinnor, Lower Icknield Way; Traffic Calming*

Scheme deferred to 04/05

Consultation and design only

Bampton, Various Roads; Traffic Calming*

Scheme deferred to 04/05

Consultation and design only

Sonning Common, Grove Road/Widmore Lane; Pelican Crossing*

Scheme deferred to 04/05

Consultation and design only

Kidlington, Bicester Road; Pelican Crossing*

Scheme deferred to 04/05

Consultation and design only

Grove, Brereton Drive/Sycamore Walk; Toucan Crossing*

Scheme deferred to 04/05

Consultation and design only

Kidlington, Morton Avenue; Traffic Calming*

Scheme deferred to 04/05

Consultation and design only

Bletchingdon, B4027; Traffic Calming

Consultation and Design only

Completion 03/04

 

 

continues

 

Wantage, Denchworth Road; Zebra Crossing*

Scheme deferred to 04/05

Consultation and design only

Wantage, Portway; Pelican Crossing*

Scheme deferred to 04/05

Consultation and design only

*Babtie presently undertaking consultation and design.

 

 

CASUALTY REDUCTION SCHEMES 2003/04 APPROVED PROGRAMME PROGRESS

Brian Fell (Group Manager)

 

Scheme

 

Assuming £1m Contribution made to Reserves

 

£1m Contribution Deferred

to 2004/05

 

 

 

A361, Wardington to Banbury; Route Action

Under review pending effectiveness of other works

 

A4095, Witney to Freeland; Route Action

Under review following reduction in accidents

 

A415, Newbridge to Standlake; Junction Improvements

Completion Dec 03

 

Abingdon, Wootton Road; Traffic Calming 20mph Zone

20 mph zone deferred to 04/05

 

Witney, Hailey Rd; Traffic Calming

Completion Feb 04

 

Accident Problem Sites Assessment Study

Study to define casualty reduction programme

 

Speed Management Strategy

Oxford and Thame 20 mph zones and 50 mph limits

 

Quick Response Schemes (in italics below)

See below

 

 

 

 

A4142 Oxford Eastern Bypass/Horspath Road and Horspath Driftway; Junction Improvements

Complete

 

B4009 Cottesmore Lane; Junction Improvements

Completion Oct 03

 

A3400 Great/Little Rollright; Junction Improvements

On hold due to structural maintenance issues deferred to 04/05

 

A415 Cokethorpe bends

Complete

 

A418 bend w of A329 roundabout

Completion Oct 03

 

A4095/Lower Road junction Hanborough; Safety Improvements

Completion Feb 04

 

A3400/B4026; Junction Improvements

On hold due to structural maintenance issues deferred to 04/05

 

 

 

continues

 

A338 Grove, Grove Park Drive

Completion Oct 03

 

A4074 Woodcote/Checkendon Cross Roads

Complete

 

A420 Thames Street/Link Rd/Speedwell St; Traffic Signals Modifications

Complete

 

A420 St Aldates/Speewell St; Junction Improvements

Design in progress

 

Bix Dual Carriageway Median

Completion 03/04

 

Abingdon, B4017 Drayton Road/Preston Road junction; Traffic Signals

Consultation, design and Mar 04 start only

 

A415/B4449 Yelford crossroads; Traffic Signals

Consultation and design only

 