ITEM EX7
EXECUTIVE
– 28 OCTOBER 2003
TRANSPORT
CAPITAL PROGRAMME 2003/04 TO 2005/06
Report by
Assistant Director (Highway Management)
Introduction
- The main purpose
of this report is to provide an update on the 2003/04 programme approved
by the Executive on 15 April 2003 and to consider the implications on
the programme of making a contribution to balances. It also seeks approval
to "kick start" the 2004/05 programme by agreeing the core schemes for
which design briefs can be issued early.
- This report also
discusses the overall priorities for the Transport Capital Programme
up to and including 2005/06 and the scope to change those priorities.
Background
- The overall balance
of the approved 5 year programme (2001/2006) is broadly in line with
the bid originally included in the Local Transport Plan (LTP), other
than that a greater priority has been given to Single Capital Pot (SCP)
expenditure on maintenance to reflect the administration’s strategic
priorities. This has been helped by the availability of other sources
of funding to support the overall programme. Progress on the delivery
of the LTP programme has been fully reported to the Government, and
members, through the Annual Progress Reports (APRs).
- The approved 2003/04
programme comprises over 340 schemes to a total value of £28.251m. This
was made up from £19.927m Single Capital Pot (SCP) allocation from the
Government, over £3.5m of developer funds, £750k from On-Street Parking
Surpluses (OSPS) and, importantly, £2m of "over-programming" to allow
for some slippage in the programme and to ensure all the SCP allocation
is spent. Annex 1 shows
the detailed allocations to each of the main budget headings and the
split between the various funding sources.
- With a programme
of this size and complexity it is inevitable that the unforeseen will
occur and that changes to the detail of the programme will need to be
made. Consultation provides both an opportunity and a reason to make
changes, external influences change and detailed investigations bring
to light factors which need to be taken into account. The overall programming
and financial implications of a multitude of issues must be constantly
monitored and managed.
Financial
Constraints
- The Council’s
budget for 2002/03 assumed a contribution to the Budget Reserve by capitalising
£1m of the structural highway maintenance budget. However, because of
an overspend on the rest of the Transport Capital Programme, the proposed
revenue/capital switch could not be made and the shortfall had to be
met temporarily from balances. In order to allow the shortfall in balances
to be reinstated the revenue/capital switch would have to be made in
2003/04. This £1m contribution along with £2m contributed in 2001/02
is due to be returned to the Transport Capital Programme in equal instalments
over the next two years to ensure that the full credit approval is used
over the term of the LTP.
- The consequences
of this drop in the capital sum available are significant in relation
to the schemes that can be started in 2003/04 and are of particular
concern to our consultant and contractor for whom there are significant
operational implications.
- The SCP allocation
must be spent in full by the end of March 2004 or it will be lost. It
is therefore imperative that sufficient flexibility is retained in managing
the various funding sources in the programme between now and year end.
Of the other sources, developer contributions, whose availability is
dependent on the terms of individual planning agreements as well as
on the pace of development, are perhaps the least prescriptive in their
application. There is generally some degree of flexibility in the allocation
of this funding to specific schemes and in the timing of the expenditure.
It can therefore be used in a limited way to balance expenditure between
funding sources.
- OSPS as at 1 April
2003 was £1.114m. First call on this surplus is the operating cost of
the Park and Rides. This is estimated to out-turn at £365k for the year,
of which £150k will be funded from the revenue budget and £215k from
OSPS. Of the remaining £885k, £60k is allocated to cover the advance
design of the proposed upgrade to the Thornhill Park and Ride and £585k
is allocated to cover outstanding costs on the Water Eaton and Thornhill
Park and Rides. This leaves £254k to fund ITS schemes which meet the
conditions for use of OSPS.
The Current
Programme
- For a number of
reasons, not least being the need to repay the £1m to balances, the
full programme as presented to Executive in April cannot now be pursued
this financial year.
- When the 2003/04
programme was put forward for approval in April, performance over recent
years suggested that slippage would delay some 10 percent of the schemes
included. The £2m "over programming" was introduced to allow for this.
At the same time efforts were concentrated on improving service delivery
through the better application of programme and project management.
Service delivery has improved and the degree of slippage which has occurred
is less than that envisaged. As a consequence some schemes which could
have been built this year will have to be carried over into 2004/05.
- The cost of implementing
schemes has risen in general and a number of projects are individually
exerting a significant influence on the programme. Annex
4 provides a more detailed account of these.
- The scale of the
remaining financial commitment to schemes in the 2002/03 programme carried
over into the current year was not fully anticipated and in some cases
costs are still being incurred.
- In short there
are insufficient funds to support the agreed 2003/04 programme and the
current position is as shown in summary in
Annex 2 and in detail in Annex
3.
- Annex 3 in particular
shows progress against individual schemes, indicating which schemes
are expected to be completed this financial year, which schemes are
likely to start this year and be completed in 2004/05 and which schemes
will need to be carried forward to be implemented as part of the 2004/05
programme.
- Also identified
in Annex 3 is the effect on the programme of not making the £1m contribution
to reserves should the Executive choose this option.
2004/05
Programme
- The scope for
influencing the 2004/05 programme is constrained by the requirements
for assessment, consultation, design, statutory procedures and construction.
It is unlikely that any scheme of significance that has not already
been considered could now be included in the 2004/05 programme. There
are also strong public expectations, particularly in the Integrated
Transport Strategy (ITS) programme, where three-year provisional programmes
in the ITS towns have already been agreed by some of the Steering Groups.
- In order to ensure
a prompt start on the design and implementation of the core schemes
in the 2004/05 programme we are seeking approval for the early commencement
of design and consultation on the range of schemes listed in Annex
5 to allow our consultant to commit resources. This list, coupled
with the schemes carried forward from the current financial year, would
make up about two thirds of the 2004/05 Transport Capital Programme.
- This approach
brings several advantages. Firstly, it increases the chances of improving
our overall scheme delivery, due to work taking place in summer months
when the weather is more favourable. Secondly, it enables our consultants
and contractors to spread work more evenly through the financial year,
improving their performance. Thirdly, it increases the certainty of
spending all the allocated SCP on the programme originally agreed, rather
than needing to redistribute the SCP to other schemes merely to ensure
a fast spend towards the end of the year.
Scope
for Change - 2005/06 on
- The Executive
will have the opportunity of reviewing the allocations for the main
budget areas for 2004/05 and 2005/06 in March 2004 after the 2004/05
settlement is known. (The currently anticipated SCP allocations for
these years are set out in Annex 6)
The opportunity for changing the priorities in 2005/06 is still available;
but mainly relates to altering the balance of funding between the six
main budget headings and the choice of the minor schemes selected for
inclusion in the relevant programmes.
- We will not be
recommending making any really major shifts in the allocation of resources
between the various transport programmes in 2005/06. This is for two
reasons. Firstly, the Government will be assessing our next LTP in terms
of our performance in delivering the policies and targets that we set
out in the first LTP; and secondly, the development of the 2006/2011
LTP is about to start. Extensive public consultation is being planned
on both policy changes and priorities. Any significant shift in resources
made while this consultation is in progress could give the appearance
that the consultation was not meaningful.
Developing
the Future Programme
- The development
of the second LTP (for 2006-11) will provide a real opportunity for
the Executive to review its policies and set out a new and ambitious
programme for transport investment up to, and to some extent beyond,
2011. The transport programme is integral to the Council achieving its
Strategic Objectives and to supporting the emerging Structure Plan and
Regional Spatial and Transport Strategies, as well as the investment
plans of the Highways Agency and Strategic Rail Authority. It would
therefore not be unrealistic to consider bidding for a 5 year Government
funded programme of perhaps £150m (compared with a £90m bid in 2000)
and to include several major schemes identified through the Transport
Networks Review. With developer funds the overall transport capital
programme could well amount to £40m p.a.
- If there are to
be any major scheme bids included in the 2006-11 LTP it is essential
that these have been progressed to the preferred route stage before
the LTP is submitted in July 2005. This feasibility work, which cannot
be charged to capital, will need to be commissioned from the existing
transport planning term consultancy; but significant additional revenue
resources will be required from 2004/05 to fund this and the other transport
planning work. A revenue budget pressure of £250,000 p.a. has therefore
been included in the Directorate’s Expenditure Proposals for 2004/05
to 2007/08 so that this issue can be addressed in the budget debate.
Financial
and Staff Implications
- The financial
implications are as set out in the report. Assessment, promotion and
design of schemes in the programme will be carried out by a combination
of existing staff and term consultants contracted to the County Council.
The County Council’s transport aspirations as set out in the Local Transport
Plan require an increasing level of commitment from both client and
consultant if they are to be met. This exerts a pressure on the Capital
and Revenue budgets.
Conclusions
- If the aspirations
of the County Council and of the public in relation to the 2003/04 Transport
Capital Programme are to be realised and if we are to avoid seriously
compromising the commercial interests of our partners, we would recommend
the Executive not to take payment of the £1m contribution to balances.
In considering the implications of taking this course of action the
Executive will no doubt wish to seek the advice of the Head of Finance
regarding the effect of this on the County Council’s overall position.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- note
progress on delivery of the 2003/04 programme to date;
- decide
if the planned contribution to reserves is required in 2003/04;
- endorse
the changes to the programme for the remainder of the year and
the carrying forward of schemes into 2004/05 in the light of
their decision on (b);
- approve
the commencement of design for the schemes listed in Annex 5;
and
- acknowledge
the potential revenue consequences of the future Transport Capital
Programme.
RICHARD
DIX
Assistant Director
(Highway Management)
Background
Papers: Nil
Contact
Officers:
Richard Dix Tel. 01865 815663
Brian Fell Tel. 01865 815083
October
2003
Return to TOP
|