ITEM
EX12 - ANNEX 1
EXECUTIVE
– 30 SEPTEMBER 2003
VULNERABLE
ROAD USER AUDIT
Scheme Categories
Stage
B: Brief
Stage
1: Feasibility and/or Preliminary Design
Stage
2: Detailed Design
Stage
3: Pre-opening
Stage
4: Post Opening
|
CATEGORY
A SCHEMES
|
Stage
B, 1, 2, 3 and 4 Audits required for all schemes
|
- New Footways
and Footpaths
- New Pedestrian
Crossings
- New Cycle
lanes, tracks and crossings
- New Junctions
- Junction
Alterations (geometrical and/or control)
- Traffic
calming by vertical or horizontal deflections
- New Bus
Lanes/Priority measures
|
|
CATEGORY
B SCHEMES
|
Stage
B audit carried out by Auditor and further audit stages subsequently
determined by Auditor for each individual scheme
|
- New Pedestrian
phase at existing traffic signals
- Advance
cycle stop line
- Visual traffic
calming (signing/lining features)
- Major highway
maintenance works
|
|
CATEGORY
C SCHEMES
|
Stage
B audit carried out by Project Manager and scheme subsequently referred
to Auditor as category A or B scheme, if required
|
- New Speed
Camera
- Speed limit
changes
- Road re-alignment
(e.g. at bend in rural location)
- Minor maintenance
works
- New or altered
Road Markings
- New Safety
Fencing
- New traffic
signing
- New Street
lighting schemes
- Surface
treatment works
- Traffic
Regulation Orders
- All un-categorised
schemes
|
|
CATEGORY
D SCHEMES
|
Proposals
reviewed by Auditor (based on Stage B audit) to determine the audit
stages required for each particular scheme
|
|
|
Return to TOP
|