|
Return
to Agenda
ITEM EX6
EXECUTIVE
– 4 MARCH 2003
GREEN ROAD
ROUNDABOUT, HEADINGTON – IMPROVEMENT OPTIONS
Report
by the Director of Environmental Services
Introduction
- The Local Transport
Plan and work on the Headington and Marston Area Transport Strategy
have identified the need for improvements at the Green Road Roundabout,
Headington, aimed at reducing traffic congestion, improving bus priority
and journey times and addressing accident and safety issues. Consultants
Faber Maunsell were appointed to carry out a study of the roundabout
and this report reviews the consultants’ suggested options with a view
to identifying possible short/medium/long term improvements.
Background
- The A40, including
the Green Road Roundabout, was a trunk road which was the responsibility
of the Department for Transport until April 2002 when it was transferred
to Oxfordshire County Council. The roundabout has been improved several
times by the Department of Transport over the years and consideration
was also given to an alternative means of improving congestion here
by providing an A40 Barton northern bypass. The latter was ruled out
principally on environmental grounds. The Department of Transport also
considered an A40 flyover or underpass at the roundabout but again these
were discounted at an early stage because of the cost, disruption to
pedestrians and detrimental environmental impact on local residential
properties.
- Local County and
City members, together with County Council officers, had long felt that
there could be less expensive and less environmentally damaging options
available and therefore a commission was issued in May 2003, immediately
following the detrunking, for a detailed traffic study to be undertaken
by the consultants, Faber Maunsell.
- Faber Maunsell
provided an interim report in October 2002. Officers felt that some
additional information and clarification was required and Faber Maunsell
were asked to prepare a final report for February 2003. This has now
been received (a copy is in the Members’ Resource Centre) and is summarised
below.
Synopsis
of Faber Maunsell Traffic Study Report
- The Faber Maunsell
report is a comprehensive report on their investigations and findings
on the complex Green Road roundabout. It provides background to and
analysis of the existing situation and sets out the aims and objectives
as agreed with the County Council officers. A number of options are
investigated in the light of the aims and objectives and recommendations
put forward. The key objectives of their report were to assess options
that would:
- reduce queuing
and delay for all the traffic at the roundabout;
- provide improved
bus priority and reduce bus journey times through the roundabout;
and
- reduce the likelihood
of accidents.
The
consultants were asked to identify options for short, medium and long-term
measures, and while focusing mainly on the peak time congestion (am
and pm) also provide a high level of bus priority facilities throughout
the day.
- Faber Maunsell’s
report has set out the results of their investigations into the current
situation at Green Road roundabout and it highlights the existing traffic
problems. The results and analysis confirm that the traffic demand at
the roundabout is greater than its current capacity during both peak
periods. There may also be other traffic that presently takes alternative
routes to avoid the congested roundabout – officers are aware of ‘rat
running’ through estate roads in Risinghurst and also further afield
through Headington Quarry, Wheatley and Water Eaton. This ‘suppressed
demand’ could revert to the Green Road roundabout if improvement measures
create a significant reduction in the present congestion.
- Their report considers
a number of possible improvement options that tackle accidents, delays
and congestion and bus priority. It contains robust discussion and analysis
of the options and includes supportive data and plans.
Accidents
- The Council’s
accident statistics show that this junction is top of the ‘black spot’
list in the County for numbers, although the severity rate is low. However
the consultants’ view is that the 3-year accident rate is no higher
than would be expected from this type of complex 5-legged roundabout
and the accident rate is average given such high traffic flows. To reduce
accidents, they have suggested certain road safety measures that could
be provided in the short-term. These are anti-skid surfacing, amended
road marking and enhanced signing. These measures need to be considered
in the light of any medium and long term measures that may be introduced.
They would not, on their own, reduce congestion or improve journey times.
- Faber Maunsell
conclude that the existing underground pedestrian and cyclist facilities
are well used, in good condition and offer a safe environment. Any attempt
to provide ‘at grade’ (at existing ground level) crossings, with any
of the considered options, would result in a detrimental impact on general
traffic and bus services.
Options
to Relieve Congestion
- Faber Maunsell
investigated seven options which they thought would relieve congestion.
These varied between widening the approach widths, signalisation of
the existing roundabout, conversion into a signalised junction and modifying
the present layout to form a Hamburger Roundabout. (A ‘Hamburger Roundabout’
is a relatively new development whereby the roundabout is signalised
but also introduces a straight-through section of carriageway for one
of the major routes – this creates a plan view somewhat like the cross-section
through a hamburger) The analysis of a signal-controlled roundabout
on its present layout (see Annex 1) (download
as .doc file) indicated that this would not relieve the present
congestion or improve bus journey times because there is insufficient
space available within the roundabout, which would result in the worsening
of the current situation. Similarly, converting the roundabout to a
signal-controlled junction produced results that indicated that the
junction would operate at over capacity with severe queuing and delay
on all arms except London Road.
- A full grade-separation
option was also considered and the consultants have concluded that only
this and the A40-A40 ‘hamburger’ option meet the aims and objectives
set out in the traffic study. As Faber Maunsell point out, the grade-separation
option is significantly more expensive (it could cost upwards of £40M)
than the hamburger roundabout (approximately £2M). The grade-separation
junction would require land acquisition outside the highway boundary
and it would have severe environmental impact on the area around the
existing roundabout. An economic assessment of these two options shows
that the hamburger roundabout is more cost-effective and would therefore
deliver better value to the Council. (An illustration of the proposed
layout of the hamburger roundabout is shown in Annex 2) (download
as .doc file).
- Any scheme greater
than £5m would be regarded by the Department of Transport (DfT) as a
major scheme and would be subject to a separate bid for funding. It
is doubtful whether a £40m scheme could be justified and in any event
would take many years to complete.
- ‘East-west’ and
‘north-south’ hamburger roundabouts were also considered and rejected
on the grounds of reduced capacity, increased congestion and increase
in bus journey times.
Options
to Enhance Bus Priority
- Several options
were considered by Faber Maunsell for improving priority for buses travelling
through the roundabout. These options are described and discussed in
their report and three options are recommended for implementation with
an additional one if the hamburger roundabout scheme was to be constructed.
These are:
- To close the
exit from the Roundway service road, just west of McDonalds, into
the A40. This will remove the conflict of ‘queue-jumpers’ on the A40
using the service road to get to the front of the queue at the roundabout;
- To provide a
bus lane on the A420 London Road eastbound. This will reduce delays
for buses leaving Oxford centre. This option will have to consider
the effects on the existing westbound bus lane and cycle facilities;
- To provide traffic
signals at the junction of Bayswater Road and Waynflete Road. This
will facilitate buses exiting Waynflete Road to joint Bayswater Road,
especially in the morning peak period when queuing or slow moving
vehicles approaching Green Road roundabout block this junction; and
- To provide a
bus pre-signal on the westbound A40. This will allow an improved level
of bus priority approaching the roundabout, especially for the Thornhill
Park and Ride buses.
Each
of these measures is fully compatible with each other and represents
a step in enhancing bus priority. They are also complementary to the
measures suggested to relieve congestion and improve safety.
Recommendation
by Faber Maunsell
- Faber Maunsell
have carried out detailed assessments into various options for the improvement
of the Green Road roundabout. They conclude that the option that will
best meet the aims and objectives of the brief in the long term is the
provision of a ‘hamburger roundabout’ as shown in Annex 2. This
preferred option does not require land outside the highway boundary,
should have relatively small environmental impact, is best suited to
relieve congestion, is complementary to safety improvement measures
and when combined with suggested bus priority measures, provides the
best option to reduce bus journey times.
- Faber Maunsell
also suggest measures for short and medium term that could be implemented
independently, yet complement each other and lead to the construction
of a long term solution. These are:
- Short term –
closing the accesses to the A40 from The Roundway, improved signing,
anti-skid surfacing and, in case a preferred long term solution is
not accepted, spiral road markings.
- Medium term
– an eastbound bus lane on the London Road approach and signalisation
of the Bayswater Road/Waynflete Road.
A
large scale plan showing the proposed long term solution for the
Green Road roundabout, including other supportive measures, will
be displayed at the meeting.
Views
of Council Officers
- The officers have
studied the report by Faber Maunsell and they are encouraged that the
hamburger roundabout offers an opportunity to improve the Green Road
roundabout by reducing congestion and improving bus journeys. More work
is needed by the consultants to develop the scheme and its detailed
implications on buses, buildability, etc.
- It is clear that
there is a significant level of suppressed demand for travel through
the junction. Increased capacity at the junction would be likely to
fill quickly and would have limited benefits because of the restricted
capacity of adjacent junctions. However, capacity improvements at the
roundabout would provide the valuable opportunity to provide bus priority
and manage traffic with signals, without detriment to general traffic
conditions overall. There would be safety benefits both at the roundabout
and on other routes that are currently used as alternatives.
Proposed
Programme
- The officers agree
with the suggested three stage approach of improvements at the roundabout
and its vicinity. Subject to the approval of the 2003/04 Transport Capital
Programme, £50,000 will be allocated from the developer contributions
in the HAMATS area. That would enable the implementation of the described
short term measures in summer 2003 and to start the preliminary design
work on the medium and long term solutions, followed by the first round
of consultation.
- Following this
consultation the medium term measures can be designed in detail and
implemented in early 2004. At the same time a second round of consultation
on the long term solution can take place with a view to finalising its
preliminary design. It is intended to report the outcome of this further
consultation and a final detailed layout to the Executive with a view
to it being considered for inclusion in the 2004/05 and 2005/06 capital
programmes for the start of construction in early 2005.
- An illustration
of the proposed programme for improvements to the Green Road roundabout
in shown in Annex 3 (download as .xls
file).
Environmental
Implications
- Measures to reduce
congestion and improve bus journey times will improve the environment
in and around the Green Road roundabout. The detailed design will seek
to incorporate measures that mitigate traffic delays associated with
the construction of a hamburger roundabout and its overall environmental
impact.
Financial
and Staff Implications
- Current investigation
is financed from the 2002/03 Capital Programme. However no funding presently
exists for any future improvement to this roundabout. If the Executive
favours a scheme in principle, it would need to compete against other
potential commitments for a place in the Transport Capital Programme.
However, a provisional sum of £50,000 has been allocated in the proposed
2003/04 OTS Programme from developer contributions in the Headington
area. If successful, this would enable funds to be provided for design
fees in order to develop the scheme further, and for implementation
of short term measures identified in this report. Any further development
and implementation of the medium and long-term measures will need to
be a subject of future year Capital Programme funding allocation.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- approve
the long term measures shown on drawing No 30510/P001 in Annex
2 to the report as the preferred scheme for further development
and consultation;
- approve
the implementation of the short and medium term measures set
out in paragraph 16 of the report, subject to inclusion of the
schemes in the Transport Capital Programme and the consideration
of any observations or objections resulting from consultation
on the individual measures by the Transport Implementation Committee.
DAVID
YOUNG
Director of
Environmental Services
Background papers: Report entitled ‘Green Road Roundabout – Improvement
Options Report’ by Faber Maunsell dated February 2003
Contact
Officer: Peter Evans, Tel: Oxford 815836
February
2003
Return to TOP
|