ITEM EX12

EXECUTIVE – 7 JANUARY 2003

EXTENSION OF WORKS CONTRACTS TO INCLUDE FURTHER WORK

REVISED DETAILED PROJECT APPRAISAL APPRAISAL NO. 573/3

NAME OF SCHEME: The Warriner School, Bloxham – New 6 Classroom Block

START YEAR: 2002/03

BASIS OF ESTIMATE: Atkins cost estimate based on agreed sketch scheme

  1. DESCRIPTION OF PROJECT
  2. The previous project appraisals detailed the overall site development strategy for The Warriner School given predicted growth, the large number of temporary classrooms and the number of suitability problems. The development of the 6 classroom block will be a free-standing building providing office space, toilets and disabled access to both floors.

  3. JUSTIFICATION AND ASSESSMENT OF NEED
  4. The Warriner School currently has a capacity of 1,048 but with 190 temporary school places. The current number on roll is around 1,100 and it is likely that the roll will be maintained at this level. This development will provide for 2 additional classrooms for basic need and replace 2 double temporary classrooms. There is a long-term need for permanent places at the school and the new block provides the opportunity of providing improved accommodation and bringing the permanent accommodation at the school closer together. The temporary classrooms are some distance from the main school buildings.

  5. OTHER OPTIONS
  6. The only other option for the Council would be for it to continue to provide temporary accommodation at the school and allow the existing temporary accommodation to remain and deteriorate, even though specific ACG allocations have been received for the development of the school buildings.

  7. FINANCIAL IMPLICATIONS (see attached resource appraisal)

(i) Capital

The current cost for the scheme is £631,000 inclusive of fees which is funded from the Authority’s ACG allocation. Officers propose to negotiate with the contractor currently working on site on another scheme around the use of the rates agreed as part of the original contract updated for inflation. The contractor has performed well and established a good working relationship with the school. The negotiated tender will have the following additional advantages.

  • Project completion for September 2003 can be achieved providing a good start to the next academic year with the removal of the temporary accommodation.
  • Any price risk and uncertainty will be removed by not tendering the project and by using existing tender rates with an open book agreement for any increases together with an overall cap of percentage inflation noted by BCIS. This will ensure that the scheme is more accurately cost planned to the budget.
  • The proposed extension to the proposed building is directly adjacent to the new music block. The contractors knowledge and experience of working in this area of the school can be utilised.
  • The project can be accelerated i.e. an early completion will reduce inflation.

(ii) Revenue

Day-to-do revenue costs will be met by the school through its revenue budget. The running costs of the new building will be less than those for the temporary classrooms.

  1. STAFF IMPLICATIONS
  2. There are none arising from this report.

  3. ENVIRONMENTAL IMPLICATIONS

The new buildings will be constructed according to county standards and in line with the planning consent secured for these works.

ROY SMITH
A cting Chief Education Officer

DAVID YOUNG
Director of Environmental Service

CHRIS GRAY
Director for Business Support & County Treasurer

Contact Officer: Keith Borien, Senior Education Officer, Tel: (01865) 428161

Date: December 2002