|
Return
to Agenda
ITEM EX17
EXECUTIVE
– 10 DECEMBER 2002
PILOT HOME
ZONES
Report by
Director of Environmental Services
Introduction
- This report summarises
the results of the consultations that were carried out during September
2002 in the four potential pilot Home Zones. The reason for selecting
these four areas was to trial schemes at different levels of intensity
of treatment, so that if the County Council pursues Home Zones in the
future, resources can be most effectively used.
- As was authorized
by the 23 July 2002 Executive, the consultation was conducted to measure
the level of "in principle" support for introducing a Home Zone in these
areas (i.e. people were not given details of possible schemes). The
report recommended that, because of the need for Home Zones to have
community involvement in their design and use if they are to be successful,
the County Council would only move forward where at least 50% of questionnaires
were returned and where, of those returned, a minimum of 70% would need
to be in favour of a Home Zone being introduced in their streets.
- It has become
apparent that the requirement of 50% return rate was probably too high.
As evidence of this, the County Council’s consultants working on the
Saxton Road Home Zone scheme conducted an intensive house to house survey
which only resulted in a 49% response. Postal surveys alone would be
expected to have a lower return rate. In light of this experience, I
have come to the view that the required return rate should be lowered
to 40%, but that a 70% positive response from those replies received
should be maintained.
- The four areas
or streets that were approved for investigation were:
- Hughes Close/Sturt
Close – Charlbury
- Stapleton
Road – Headington, Oxford
- Silver Street/Golden
Street/Barnet Street/Catherine Street/Hertford Street/Essex Street
and Percy Street – East Oxford
- West/East/North/South
and Center Streets – Grimsbury, Banbury
- It should be noted
that in the 23 July report the approximate cost of the East Oxford scheme
was given as £150,000. This should have read £450,000 (1.8km @ £250/m).
Results
of the Consultation
- A consultation
pack consisting of a letter explaining the proposal being consulted
upon, a leaflet explaining the Home Zone concept and a prepaid return
questionnaire was delivered to each property in the four areas. It was
considered important that the questionnaires for the four areas be as
similar as possible to each other, in order to allow results to be compared
between them, but slight variations in the exact questions asked were
necessary to reflect the specific nature of each area.
- A summary of the
main results from the consultation is given in Annex
1. A more detailed analysis has been placed
in the Members’ Resource Centre. The conclusions drawn from the analysis
are presented below for each of the four areas in turn.
Hughes
Close/Sturt Close – Charlbury
- Out of the 93
households in the two closes, (44%) responded and of these 93% were
in favour of the scheme. There was a slight difference in the response
between the two streets: in Hughes Close, 25 of the 50 households responded;
while in Sturt Close, with 43 households, 16 responded. In both areas
there was overwhelming support to the idea of introducing a Home Zone
from those who replied. The issues of speeding and parking were highlighted
by respondents as being the main areas of concern.
Stapleton
Road – Headington, Oxford
- Although the report
to Executive of 23 July referred only to Stapleton Road, the area of
the consultation was subsequently widened at the request of the Local
Member. This was to include streets that might be affected by traffic
diverting away from Stapleton Road. These streets are All Saints Road,
Barrington Close, Bickerton Road, Cecil Sharp Place, Latimer Road, Lime
Walk, Nursery Close and Old Road. In total 448 households were consulted.
Two questions were asked: first if people would support a Home Zone
for Stapleton Road alone, and second if they would support a Home Zone
in Stapleton Road if a 20 mph zone were introduced on the surrounding
streets.
- There was a varied
response in the area, both in terms of response rate and support for
the either option. Stapleton Road itself had a 78% response rate and
of these there was a very high yes vote of 91%. There were much lower
levels of return and support for a Home Zone from the other roads, particularly
the side roads. There was a greater degree of support from other streets
for a Home Zone in Stapleton Road if surrounded by a 20mph zone. However,
it is difficult to conclude that a Home Zone within a 20mph zone has
widespread support and I would expect to draw this out during more detailed
consultation on the specification of the Home Zone at a later date.
It is also worth acknowledging that the HAMATS strategy includes proposals
for traffic calming measures in the Lime Walk area.
- As well as the
returned questionnaires, Highfield Residents Association organised a
survey of its own amongst residents of Lime Walk and Bickerton Road
which showed clear opposition to a Stapleton Road Home Zone. Countering
this a petition in support of the concept was organized by some of the
residents of Stapleton Road and they managed to secure the signatures
of 74 of the residents of that street. Copies of both of these have
been placed in the Members’ Resource Centre. In acknowledging and welcoming
the strong support for a Home Zone by Stapleton Road residents, the
Council needs to be mindful of the potential for objection from elsewhere
and deal carefully with the next stages.
Inner
East Oxford
- Not all the streets
within the area bounded by Howard Street, Magdalen Road and Iffley Road
and including Essex Street were listed in the report to the Executive
of 23 July. However, the whole area, comprising some 485 households,
was consulted with the assistance of the Inner East Neighbourhood Association
(IENA) whose contribution is gratefully acknowledged.
- Discussions in
the past, prompted by the City Council’s earlier bid and work carried
out by East Oxford Action, led to a focus for the Home Zone consultation
being on Hertford Street. As with the Stapleton Road consultation a
further question seeking the level of support for a surrounding 20 mph
zone was included. This has subsequently proved to be a source of local
controversy and confusion as it seems that there was an expectation
that the consultation would seek views on a Home Zone covering the whole
area, rather than just Hertford Street. This may have led to a lower
return and neither I nor the local community would want this to lead
to the delay or abandonment of the proposal to develop a pilot scheme
in this area.
- However, what
is important, and has been difficult to get across up to now, is that
in order to qualify for funding under the Council’s Home Zone programme
(within the Community Safety Transport section of the Transport Capital
Programme) there would need to be an acceptance locally of a level of
treatment in part of the area that meets the Government’s and therefore
the County Council’s definition of a Home Zone. The main problem at
the present time is that the Government has yet to publish its Home
Zone guidelines. These are expected in the Spring. What is almost certain
however is that a Home Zone will be more than merely a 20mph zone.
- The overall response
was a 41% return and, of those, 78% would support just a Hertford Street
Home Zone while 85% of responses were in favour when asked if they would
support the introduction of a surrounding 20mph with the Home Zone in
Hertford Street. Two issues caused residents more concern and these
were parking and speeding. Perhaps surprisingly the residents of Hertford
Street itself were less enthusiastic about the idea than the area as
a whole, although even here 70% supported a Home Zone with a 20mph zone
surrounding it.
West/East/North/South
and Centre Streets – Grimsbury, Banbury
- In total 345 households
were consulted in this area. Only a section of West Street was surveyed,
that between North and South Streets. Overall there was a 34% return
rate and, while 83% said there were traffic problems in the area, only
62% of those returned supported the introduction of a Home Zone. This
falls short on both the level of return and the level of positive responses
required. The consultation identified issues of traffic volume and speed
as the main concern and, despite a greater degree of support for a Home
Zone in West Street (73% from 40% returns), it may be preferable to
leave these issues to be addressed by the Grimsbury Traffic Study which
is proposed as a follow-on to the Banbury ITS work. Indeed, funding
traffic management measures through the ITS element of the Transport
Capital Programme may be more forthcoming and timely than through the
pilot Home Zone programme.
- Following representations
made by Councillor Sandra Mold to the Executive in July regarding the
suitability of the area proposed for zoning in Banbury, Cherwell District
Council have confirmed their support for the Grimsbury area as the most
suitable area in Banbury for treatment
Moving
Forward
- The consultation
process has been successful in identifying three of the four areas as
potential pilot Home Zones. The strongest support came from Charlbury
followed by Inner East Oxford and then Stapleton Road. I therefore propose
that work on the next stage, setting up local liaison arrangements and
carrying out more detailed analysis of the areas before embarking on
design work, should commence in Charlbury this financial year and be
followed in 2003/04 by Inner East Oxford. As noted earlier, there are
some outstanding issues in the Stapleton Road area and we may learn
some lessons from the first two schemes which will assist in resolving
them.
- In Annex
2 a
set of processes and procedures for establishing a Home Zone developed
from our experience with Saxton Road is outlined. Stages one and two
have been completed and it is envisaged that stages three to eleven
will take about twelve months to work through for each scheme.
- Subject to funding
availability a timetable for the programme is envisaged as:
|
|
2002/03
|
2003/04
|
2004/05
|
2005/06
|
2006/07
|
|
Charlbury
|
Commence
local liaison and identify issues and options.
|
Detailed
design and consultation - commence implementation.
|
Complete
implementation.
|
|
|
|
Inner East
Oxford
|
|
Commence
local liaison and identify issues and options.
|
Detailed
design and consultation - commence implementation.
|
Complete
implehmentation.
|
|
|
Stapleton
Road
|
|
|
Commence
local liaison and identify issues and options.
|
Detailed
design and consultation - commence implementation.
|
Complete
implementation.
|
- Progress would
not be as fast with this programme as was previously envisaged and,
even with the completion of the Saxton Road scheme, could mean that
the Local Transport Plan target of having 5 Home Zones in place by 2006
would not be met. The detailed requirements for designating Home Zones
are not yet known. This may require the publication of Orders similar
to Traffic Regulation Orders. If this is the case then the time taken
to complete implementation may need to be extended to accommodate the
required statutory processes.
Update
on Saxton Road Home Zone
- Since 19 February
2002 Executive, the consultants MVA Limited, in association with architects
Building Design Partnership, have been appointed to carry out the project
management and public consultation elements of the project. So far good
progress on developing the Saxton Road scheme has been made. As recommended,
a Steering Group has been set up and has been holding monthly progress
meetings chaired by Councillor Fawcett, as local councillor, and made
up of representatives of the County and District Councils, the Police,
Vale Housing Association, Town Council representatives and a number
of residents of Saxton Road.
- The Saxton Road
scheme has been broken into three stages of consultation. The first
stage was carried out in mid June and comprised a household survey to
highlight problems that exist in the street from which ideas for improvements
could be identified. This information was used to establish the issues
that were dealt within Home Zone Workshops, held at the end of July
and beginning of August. The attendance at the Workshops was somewhat
disappointing but even so it was a valuable exercise from the perspective
of the residents and the consultants.
- The final stage
of the consultation was a public exhibition running from 10 to 12 October
held in Saxton Road. The purpose of this exhibition was to show the
residents a number of options that have been developed out of the ideas
that had been raised in the first two stages of consultation. Attendance
at this exhibition was much higher and comments were received on the
options display. From these a final scheme will be developed. A preliminary
plan showing the preferred option will be on display at the meeting.
Implementation is expected to begin in the Spring of 2003.
Financial
and Staff Implications
- Experience of
the emerging potential costs of the Saxton Road scheme, funded by a
specific grant from Government, has led me to the view that the present
indicative allocations in the Transport Capital Programme (Community
Safety Transport budget) for the next 3 years are likely to be inadequate.
Whilst at present it is difficult to anticipate total costs of the three
proposed pilot Home Zone schemes, as this will depend on the extent
and level of treatment of each scheme, I would now expect the capital
costs to be somewhere between £750k and £850k over approximately 4 years.
This would require adjustments to the latter stages of the 3 year programme
and indicative funding allocation. The funding identified for 2003/04
(£150k) is however considered to be sufficient to make progress on the
detailed design and consultation on the first two schemes and commence
implementation in Charlbury.
- I do not expect
to be able to meet the requirements for consultation and design using
existing staff resources and so would commission consultants. There
will be a need however to manage the consultants work and provide the
usual client officer support at public consultation events etc. All
the consultation, design and implementation costs are chargeable to
the capital programme.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- approve
the Hughes Close/Sturt Close, Charlbury; Stapleton Road, Headington,
Oxford; and Inner East Oxford areas to be taken forward as pilot
Home Zones in accordance with the report;
- authorise
the Director of Environmental Services to commence the next
stages of these schemes in accordance with the schedule of processes
and procedures in Annex 2;
- note
that the traffic issues in West Street, Grimsbury, Banbury will
be investigated as part of the ongoing Banbury ITS work; and
- note
the progress of work on the Saxton Road, Abingdon Home Zone.
DAVID
YOUNG
Director of
Environmental Services
Background papers: Pilot Home Zones: Initial Consultation, Analysis
of Responses
Contact
Officer: Ben Fryer Tel: Oxford 810451, Roger
O’Neill Tel: Oxford 815659
November
2002
Return to TOP
|