Return
to Agenda
ITEM EX12
EXECUTIVE
– 1 OCTOBER 2002
GTE FOR
OXFORDSHIRE
Report
by Director of Environmental Services
Introduction
- The purpose of
this report is (i) to update the Executive on progress made on the Guided
Transit Express (GTE) Project since the last report to County Councillors
(Environmental Committee, June 2001); (ii) to set out the timetable
for further work to be completed by the end of 2002/03 and the work
programme for delivering the project; and (iii) to identify the funding
requirements for this work and to seek further County Council funding
support for GTE.
Background
- The GTE project
is the proposal to provide Oxford with guided busways alongside the
railway corridor, to allow an express bus network to connect the city
centre to key Park & Ride sites and surrounding towns (in particular
the County’s growth towns). Two guided busways are proposed, linking
Peartree Park & Ride to the city centre (the northern guideway)
and Redbridge to the city centre (the southern guideway). It is envisaged
that the two guideways would meet at Oxpens, where Oxford railway station
could potentially be relocated. Detailed plans of the guideway alignment
will be available at the meeting and a summary plan is attached as Annex
1.
- The aim of GTE
is to provide very high quality public transport facilitating direct
journeys from surrounding towns into Oxford (without the need for interchange)
and to support the growth and vitality of the city (for example the
proposed extension of the Westgate shopping centre and redevelopment
of the Oxpens area). GTE is a key scheme in the County Council’s future
programme identified in the Local Transport Plan (LTP). GTE is also
included in the first deposit draft of the Oxford City Local Plan Review,
with the alignment identified on the proposals map.
- GTE is being promoted
by a public-private partnership, through a special Project Company set
up in 1999. Oxfordshire County Council is one of the shareholders in
this Project Company, which is chaired by Councillor Bill Bradshaw.
Other partners include the City Council, rail and bus operators and
retail and academic interests. All partners have contributed (either
in the form of cash or in-kind work) to the development of the project
to this stage and a full list of partners and their contributions is
appended as Annex 2. This groundbreaking public/private partnership
has not only raised funding for the project but has also provided GTE
with unique links to key players in the transport industry and local
groups (for example the Oxford Preservation Trust).
- The Company has
employed specialist consultants to work on the different strands of
the project under the overall guidance of Project Managers, CJ Associates.
A key milestone in the Project was the production of a detailed Feasibility
Study for GTE in July 2001. The conclusions of this Study were that
the project was viable in engineering and financial terms with alignments
for the northern and southern guideways identified. The Study also set
out the requirements for the next stage of work, Project Definition,
which has been the focus of activity over the last year.
- Subsequent to
this, Marcus Lapthorn the former Oxford City Centre Manager, has been
appointed as General Manager for the GTE project, to develop the public
relations side of the project and act as a local point of contact for
all parties interested in and affected by GTE.
Project
Definition – Stage 1
- A significant
proportion of the further work outlined in last year’s report to Environmental
Committee has been completed, despite the uncertainties surrounding
the rail industry in general and the rail infrastructure requirements
through Oxford in particular. Oxfordshire County Council has contributed
£150,000 to the cost of this work. The main work areas are summarised
below.
- Northern Guideway:
A preferred alignment for the northern guideway between the A34 and
Bicester North junction has now been identified, between the railway
and the Oxford canal.
- Southern Guideway:
The Feasibility Study identified an alignment predominantly to the west
of the rail corridor, utilising spare railway land in the Hinksey sidings
area. However, the disadvantage of this is that it would require the
guideway to cross the railway on an elevated structure (with associated
embankments/earthworks). Having crossed the railway, some GTE services
(e.g. those serving Redbridge Park & Ride) would then need to cross
back, using Old Abingdon Road. It is recognised that an alignment wholly
to the east of the railway would overcome most of these difficulties;
however, the current rail formation means there is insufficient space
for a twin-track guideway within the rail corridor. The project’s engineering
consultants Arup have therefore developed east and west options for
the southern guideway. Their conclusion is that to achieve an eastern
alignment, the rail formation would need to be slewed to the west and
that within the overall width of the rail corridor this is feasible,
even allowing for proposals to four-track the railway line through Oxford.
To deliver this solution, a holistic approach to the rail corridor is
needed, such that upgrading of the railway, renewal of signalling and
provision of GTE are all planned and implemented together. The relocation
of Oxford Station is also central to meeting these objectives. The cooperation
of and close working with the Strategic Rail Authority (SRA) will therefore
be required and discussions with them are ongoing. Arup’s report on
the southern alignment has been placed in the Members’ Resource Centre
and the Executive Summary of this report is appended as Annex 3.
- Environmental
Assessment: Those involved in the GTE project is determined to be
transparent about environmental issues. An initial assessment by Oxford
Brookes University was included in the Feasibility Study work and a
full Environmental Assessment is now being undertaken. GTE has procured
the services of leading consultants ERM for this work, following a selection
process that involved the Oxford Preservation Trust and Brookes (demonstrating
the strength of the partnership approach). As a first stage, ERM have
produced and consulted upon a Scoping study setting out the framework
for this Assessment and they are now starting work on a level 2 ecological
survey. ERM have also been working closely with Arup on the development
of options for the southern guideway, which have been assessed on environmental
as well as engineering criteria. Their work is expected to be completed
by the end of 2002.
- Revenue and
Patronage Forecasting: The Origin-Destination surveys undertaken
in Oxford in November 2001 are being used to update the GTE patronage/revenue
forecasting model. Specialist consultants the TAS Partnership has been
engaged to undertake this work, which is expected to be completed this
autumn.
- Operational
issues: Whilst no firm decisions have been taken, it is expected
that the guideways will be open access, ie available for use by any
bus operator provided that their vehicles are able to meet specified
quality criteria, for example accessibility (low floor vehicles) and
emissions (probably directly linked to the appropriate EURO engine standard).
Ticketing systems and number of entry/exit points may also be included,
depending on whether any intermediate stops are provided on the guideway
(this issue is considered further below). The guideway would be constructed
so that both double-deck and articulated buses could use it. Depending
on project financing, an access charge for use of the guideway may be
levied on operators.
Project
Definition – Stage 2
- Further work has
been identified for the remainder of the 2002/03 financial year, to
largely complete the Project Definition stage of GTE. These work areas
are outlined below:
- Refinement
of alignment options: These will be developed in consultation with
the rail industry, as outlined in paragraph 9 above. Specific aspects
to be considered include the feasibility of providing one or more stopping
points on the guideway. For example, a potential stop on the northern
alignment in the Trap Grounds area has previously been identified. Without
prejudicing this possibility, a key objective of GTE is to provide an
express service into Oxford, and journey time savings (compared with
current bus operations on radial routes) will be critical to making
the business case for the project stack up. Any stopping points would
therefore need to be off line to prevent queuing on the guideway, thus
increasing land requirements. GTE stops in certain locations would also
undermine commercially operated bus services in these areas.
- Investigation
of a potential southern extension of GTE alongside the southern bypass
to the Heyford Hill roundabout/the Oxford Science Park: Funding
for this work is being sought from developer contributions linked to
the Science Park development, whose owners are a partner in the GTE
Project Company. Expressions of interest in this work are currently
being considered.
- Assessment
of the effects on GTE on travel patterns: This work includes an
assessment of likely mode switch and quantifying the effects of GTE
on the local bus and road networks. Expressions of interest in this
work are currently being considered.
- Consultation:
Preliminary discussions have already been held with key groups (e.g.
British Waterways). Detailed consultation is planned for early 2003,
once certain key aspects of the project have been clarified (in particular,
a preferred alignment for the southern guideway).
- Public Relations:
Under the guidance of the GTE General Manager, PR Agency Dickers MacDuff
has been retained to work on this aspect of the project and a PR Strategy
is currently being devised. Other key elements of this work include:
- Creation of
a brand/identity so that the project is more easily recognisable and
marketable;
- Development
of a GTE Website (a family of addresses has already been registered);
- Production and
distribution of a new brochure;
- Targeted meetings
with interest groups, e.g. local residents’ associations;
- Briefings for
Councillors, MPs and key agencies – for example GOSE/DfT.
Links
to Other Projects
- Enhancement
of railway infrastructure and services through Oxford: The interface
of GTE with the railway is critical and represents the principal risk
to the project. There are a number of projects proposed which will all
affect GTE to some extent – within the timescale for GTE these include
the proposed Station relocation, four tracking of the main line through
Oxford and the East West Rail project. In the longer term, other projects
such as the potential reopening of the Oxford-Princes Risborough line
for passenger use will also need to be considered.
- Potential future
extensions: In addition to the Science Park, a further potential
extension to GTE is along the A40 corridor (in view of the recent work
on the Oxford – Witney - Brize Norton rail corridor, which identified
the potential for guided bus as an alternative to heavy rail). I will
be reporting on the review of the A40 Strategy – and how GTE fits in
with this - at the 15 October meeting of the Executive. It is important
that any proposals agreed as part of this strategy, such as a link road
between the A40 and the A34/A44 (which could run parallel to the proposed
GTE alignment) are developed with GTE in mind and priority for buses
in this area maintained.
- County Council
Premium Routes Strategy: Proposals for (in particular) links between
Oxford and Abingdon and for the north/south radials into Oxford that
are being developed as part of this Strategy are being developed in
partnership with the GTE Project.
Project
Programme and Funding
- 2002-03 Financial
Year: The cost of Project Definition was estimated last year as
up to £300,000. The contribution of £150,000 agreed by Environmental
Committee in June 2001 has therefore met half this cost but this will
only fund work until the end of October 2002. However, the Project Appraisal
approved by Environmental Committee also included an allowance for a
further £150,000 of County Council funding towards the project in 2002/03.
- To allow development
work on GTE to continue, I therefore propose to initially allocate £110,000
of funding from already-identified 2001/02 revenue underspends to GTE.
It is currently predicted that these funds would run out at the end
of December, with a further £30,000-40,000 required for the remainder
of 2002/03. It is therefore proposed that I review the GTE work programme
later in the year and, if necessary and if funding is available, identify
up to a further £40,000 from within Environmental Services capital or
revenue budgets to meet this shortfall, making up the total County contribution
of £150,000 for 2002/03.
- Beyond 2002/03:
Annex 4 identifies the GTE Activity and Expenditure Programme from the
2003/04 financial year through to operation in 2008/09. The key milestones
in the project are expected to be as follows:
- Project Definition
completed by June 2003
- Project Authorisation
(Transport & Works Act submission and Public Inquiry) 2003-06
- Procurement
(Selection of Consortium to Construct/Maintain guideway) 2005-07
- Construction
2007/08
- Operation
2008/09.
- The total cost
of this work, excluding the capital costs of the guideway and associated
traffic management and other infrastructure, is estimated to be
£2.6 million (including a 20% contingency). This figure is consistent
with the June 2001 Project Appraisal, which identified funding requirements
of £2 million for authorisation and procurement, and included an indicative
contribution of £500,000 from the County Council towards this cost (£250,000
of capital expenditure in each of the 2003/04 and 2004/05 financial
years).
- Of this £2.6 million,
Annex 4 shows that approximately £1.8 million would be required to take
GTE through to the end of the Project Authorisation Stage, covering
the 2003/04 to 2005/06 financial years, with £0.8 million of this required
for 2003/04.
- Assuming that
the County Council contribution of £0.5 million is confirmed, this still
leaves a funding shortfall of about £1.3 million over these three years.
Other than County Council funds, it is difficult to see where this shortfall
could be found. Although the private sector has contributed significantly
to the development of GTE so far (to the value of around £300,000) these
contributors have not received anything for their money and the chances
of securing additional funds from the existing partners must be regarded
as slim. New partners may be attracted to join the Project Company and
contribute – for example, Capital Shopping Centres (the developers of
the Westgate extension) have expressed an interest, although this is
only likely to be followed up if planning permission is granted for
this development. Discussions with the SRA will also explore what, if
any, funding they may be able to contribute.
- In March 2002,
the Government issued guidance to local authorities on preparatory costs
for LTP Major Schemes. Whilst the government is prepared to contribute
such funds, (subject to a bidding process and availability of funding
in any given year), there are several ‘catches’, notably:
- Funding will
only be granted after a scheme has been fully accepted - i.e.
when it has passed all the Government’s appraisal tests, as well as
passing through all necessary statutory and planning permissions;
- Only a maximum
of 60% of the total eligible costs will be funded (up to a
maximum of £850,000)
- Eligible costs
are limited to detailed design and work on preparing the scheme appraisal
for submission to the Government. They specifically exclude
costs associated with preparation and completion of statutory procedures,
e.g. public inquiry.
This
funding source is therefore considered to be of limited use, as it
could only provide at most one-third of the costs likely to be incurred,
and even then this money would need to be secured and claimed back
retrospectively once acceptance had been obtained
- As a transport
scheme, GTE might be viewed as the responsibility of the Highway Authority,
with the burden of the development costs to be borne by the County Council.
If this were agreed, then such costs would need to come from the revenue
budget or the Single Capital Pot (SCP).
- At this stage,
it is proposed that approval in principle is given for the County Council
to fund the £1.8 million required for GTE work through to the end of
Project Authorisation (2005/06), with an initial allocation to the project
of £800,000 to be made in 2003/04. A further £1 million would be identified
in the Sustainable Transport budget (from SCP allocations) in 2004/05
and 2005/06 for major public transport schemes. This would be available
for GTE should the project proceed. This funding commitment would be
reviewed annually and allocated on the understanding that:
- further contributions
to the project may be secured from the private sector that would reduce
the public funding element required;
- some of these
costs may be recoverable from central government if the project gets
approved;
- any such funding
spent on GTE could be lost if the project does not proceed.
- I will be reporting
to the 15 October meeting of the Executive on a full review of the transport
capital programme for the period 2003/04 to 2005/06. Subject to the
Executive’s decision on this report, I intend to include £800,000 in
the proposed 2003/04 transport capital programme to fund the preparatory
work for GTE. A report seeking a final decision on the detailed programme
for 2003/04, including this £800,000 allocation, will be submitted in
April 2003 after the SCP allocations are known and the overall capital
programme has been agreed.
- Previously, funding
allocated to the project by the County Council has been granted to the
Project Company using the County Council’s powers under the Local Government
and Transport Acts, with this grant tied to conditions about how the
money must be spent. However, should the funding identified in this
report be agreed, in view of the significant increase in the level of
County Council funding for the project, further consideration would
need to be given to the mechanism by which it is spent and the control
procedures required to achieve this. This would be the subject of a
report to the Executive after the Capital Programme is considered in
October.
- As progress on
GTE continues to be made, officer involvement in the project is likely
to rise. Given the increasing pressures on transport planning staff
(with, for example the expansion of the Integrated Transport Study programme
to include Didcot, Henley and potentially Wantage / Grove), it is considered
that responsibility for the project should move from Transport Planning
to the Sustainable Transport (Special Projects) Group, who are responsible
for other major public transport projects. An additional post would
therefore be required in this Group to manage the GTE project and other
public transport development work.
- Scheme Implementation:
The capital costs of the project are estimated at £15 million for the
northern guideway, £7 million for the southern guideway (western alignment)
and £9 million for the southern guideway (eastern alignment). These
figures, which include a 20% contingency, suggest a total capital cost
for GTE of £22-24 million. However, additional costs such as land acquisition
and railway interfaces could add up to 50% to these figures, suggesting
a potential cost of £33-36 million for the complete scheme.
- It is likely that
some form of public-private sector partnership package would be developed
to fund GTE. However, the scheme costs are significantly less than some
other comparable Rapid Transit projects, and it is therefore possible
that the Government might consider funding the project in its entirety,
for example as a Major Scheme submission in the next (2006-2011) LTP.
Further discussions would need to take place with GOSE and the Department
for Transport to establish the most likely scenario.
Conclusions
- Significant progress
has been made on the GTE project. The alignment has been refined and
costs updated, a detailed Environmental Study is well underway, the
Business Case is being updated and a General Manager has been appointed
to spearhead the project locally. GTE is still very much viewed as viable.
- Work Programmes
have been identified for taking GTE forward in the short term (2002/03)
and medium term (2003-08) and the funding requirements of these specified.
Beyond the current financial year, the funding commitments required
to deliver the project are very significant and, should the County Council
agree to bear all or most of these, would require a significant funding
commitment from either revenue or SCP funds.
- To deliver GTE,
a holistic approach is required for the north-south rail corridor through
Oxford in particular. The opportunity exists for this corridor to be
comprehensively redeveloped to the benefit of both rail and GTE whilst
maximising integration and minimising costs.
Environmental
Implications
- The essence of
GTE remains provision of a very high quality public transport corridor
improvement that will provide a genuine alternative to car travel and
therefore encourage mode switch in line with LTP objectives, thus benefiting
the environment.
- The full environmental
implications of GTE are currently being assessed by the Project’s consultants
and the conclusions of their work should be available later in the year.
Financial
and Staff Implications
- Oxfordshire County
Council transport funding is required to continue to progress the project,
potentially to a very significant level as identified in paragraphs
24 to 32 of this report.
- Additional officer
resources will need to be secured to help deliver the project, as identified
in paragraph 33 of this report. It is proposed that this post should
be funded from the capital programme, up to a maximum of £40,000 per
annum including overheads.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- agree in
principle that the County Council will fund GTE work through to the
end of the project authorisation phase in 2005/06;
- ask the Director
of Environmental Services to include the sum of £800,000 in 2003/04
for GTE Project Development and Authorisation in the review of the
Transport Capital Programme to take place on 15 October and identify
the appropriate budgetary provision for GTE in 2004/05 and 2005/06;
- approve the
creation of an additional post within Transport Development to manage
GTE and other public transport development projects, funded from the
capital programme.
DAVID
YOUNG
Director of
Environmental Services
Background papers: Feasibility Study (CJ Associates, July 2001), Options
for Southern alignment (Arup, June 2002)
Contact
Officer: John Disley Tel: Oxford 810460
25
September 2002
Return to TOP
|