|
Return
to Agenda
ITEM EX7
EXECUTIVE
– 17 APRIL 2002
TRANSPORT
CAPITAL PROGRAMME 2002/03 TO 2004/05
Report by
Director of Environmental Services and Director of Business Support &
County Treasurer
Introduction
- This report seeks
approval for the schemes proposed to be included in the Transport Capital
Programme for 2002/03 under the six main budget headings set out the
Local Transport Plan (LTP) and identifies those schemes that are proposed
to be included provisionally in the programmes for 2003/04 and 2004/05.
Background
- At its meeting
on the 22 January 2002 the Executive agreed a Capital Programme that
included £18,613m for transport and resolved that the allocation for
Structural Maintenance should be maintained at broadly the same level
as in 2001/02 (£10.5m) and the allocations to the remaining programme
areas be reduced in proportion to the previously approved allocations
for 2002/03, taking into account existing commitments, and the availability
of On-Street Parking Surpluses and Developer Contributions.
- The allocations
of the transport element of the Single Capital Pot (SCP) between the
6 main budget headings for 2002/03, set out in
Annex 1, were approved by the Executive
at its meeting on the 19 February, as a basis for developing the detailed
programmes for each budget area. In addition, Annex 1 shows the provisional
allocations for the main budget areas for the period 2003/04 to 2005/06
that were approved, as a basis for developing future year’s programmes.
- At the 19 February
meeting, the Executive was also advised of the proposed overall funding
available for the 2002/03 Transport Capital Programme, including developer
contributions, On Street Parking Surpluses (OSPS) and funding from other
authorities. There are constraints on how this additional funding, both
in timing and location, can be allocated and these constraints have
been taken into account in developing the proposed programme for 2002/03
and future years.
Development
of the 2002/03 Programme
- A key factor in
developing the proposed programme for 2002/03 is the feasibility of
actually incurring the expenditure within the financial year. Unlike
the SCP, which is only valid for one year, Supplementary Credit Approvals
(SCA) were valid for two years, providing some flexibility in the programming
of schemes. The timescale requirements for informal and formal consultations,
design and procurement, impose severe constraints on including new schemes
(i.e. those where some work has not already been undertaken) in the
2002/03 programme.
- The 2002/03 programme
has also been developed without the benefit of a comprehensive assessment
framework for evaluating and comparing requests for schemes. However,
the proposed programme takes account of previous commitments, policy
objectives, deliverability and community concerns. It is recognised
that for future programmes new systems are required to enable a better
correlation between needs and allocations. A report later on this agenda
proposes a comprehensive assessment framework for dealing with requests
from local communities which, if approved, will be used to develop the
programme for 2003/04 and beyond.
- In previous years
the Transport Capital Programme has not been approved until the May
meetings of the former Highways & Road Safety and Public Transport
Sub-Committees, after the out-turn figures for the previous year were
known and the amount of unused SCA from the previous year that could
be used to support the new year’s programme was known. It is currently
estimated that there will be an end of year underspend of the £18,454m
SCA for 2001/02 (valid for 2 years) of between £2m and £3m. This has
been recognised in developing the County Council’s 2002/03 Revenue and
Capital budgets and £2m of this 2001/02 SCA has been used to fund maintenance
schemes carried out in 2001/02 that otherwise would have been funded
from revenue, reducing the amount of 2001/02 SCA being carried forward.
Consequently, it will be necessary to re-finance some of the 2001/02
schemes that have yet to be completed.
- As the approval
of the programme has now been brought forward to mid April, the detailed
out-turn figures for 2001/02 are not yet known and therefore the exact
expenditure on the schemes funded from the 2000/01 SCA, but undertaken
during 2001/02, or the expenditure of the 2001/02 SCA to the end of
March is not known. However, any unused SCA from 2000/01 will be allocated
towards funding 2001/02 schemes, as it has to be spent by the end of
March 2002 or it is lost, thus releasing an equivalent amount of 2001/02
SCA to support the 2001/02 schemes that have already been completed.
- This will mean
that there may be some additional 2001/02 SCA available to support 2001/02
schemes that are either in progress or are programmed to start during
2002/03. In the absence of the final out-turn figures it has been decided
to re-finance any 2001/02 schemes that had not started by the 31 March
2002 and include them in the 2002/03 programme. It will not be until
all the 2001/02 schemes funded from 2001/02 SCA have been completed
later in the year that the amount of any additional funding that may
become available to support the 2002/03 programme will be known. It
is proposed to report on progress on the transport Capital Programme
later in the year and, if appropriate, proposals for how to deal with
any additional funding that is available will be put forward.
- It is unlikely
that new schemes other than maintenance schemes will be able to be added
to the programme because of the longer lead times of schemes requiring
consultation. Also, there are still some uncertainties in the cost of
the 2001/02 and 2002/03 programmes, eg the cost of the Henley Market
Place scheme and the possible final cost of the Cornmarket Scheme given
the current contractual dispute. It may be prudent not to commit any
additional funding until these issues are resolved. However, it should
be noted that there is some flexibility in how schemes where developer
contributions are involved are funded, and it is considered that it
will be possible to spend all of the £18.613m of SCP on transport during
2002/03.
Proposed Programmes
for 2002/03
- The proposed programmes
for the 6 main budget areas and the sub headings within them are set
out in Annexes 2 to 7.
Annex
2 - Proposed
Structural Maintenance Programme 2002/0
Annex
3 - Proposed Integrated Transport Strategy Programme 2002/03
Annex 4 - Proposed Sustainable Transport
Programme 2002/0
Annex 5 - Proposed Community Safety
Transport Programme 2002/03
Annex 6 - Proposed Casualty Reduction
Programme 2002/03
Annex 7 - Proposed
Major Schemes Programme 2002/03
In general the allocations
have been made to named schemes but where block allocations are listed,
eg for "rapid response" measures (included to provide the
opportunity for dealing with minor issues that arise during the year),
it is suggested that the selection of schemes should be undertaken in
consultation with the Executive Members for Transport and Strategic
Planning & Waste Management.
- Other schemes,
funded from developer contributions relating to existing or new planning
agreements, are also being developed in consultation with developers
and District Planning authorities. These may need to be added to the
approved Transport Capital Programme at short notice to meet developers’
programmes. It is proposed that they should be added to the programme,
as appropriate, following consultation with the Executive Members for
Transport and Strategic Planning & Waste Management.
- Individual schemes
will be reported to the Executive where approvals are required and,
in any event, any additions to the programme will be included in the
proposed update and review of the Transport Capital Programme to be
reported later in the year.
Provisional
Programmes for 2003/04 and 2004/05
- Work is in progress
to develop three-year programmes for all budget areas. It must be recognised
that it will not be possible, or desirable, to approve firm three-year
programmes in all areas, eg Casualty Reduction – where each year’s programme
must take account of the latest casualty figures; or Community Safety
– where the assessed programme will need to be kept under review to
ensure that the highest scoring schemes are included.
- However, in view
of the long lead times on developing some schemes, it is important to
identify the programme on a provisional basis so that work can commence
at the earliest opportunity. Annexes 8 to 13 identify schemes provisionally
included in the 2003/04 and 2004/05 programmes, including sites to be
assessed.
Annex 8 - Provisional
Maintenance Proamme 2003/04 and 2004/05
Annex
9 - Provisional
Integrated Strategy Programme 2003/04
Annex
10 - Provisional Sustainable Transport Programme 2003/04
Annex
11 - Provisional Community Safety Transport Programme 2003/04
Annex 12 - Provisional Casualty Reduction
Programme 2003/04
Annex 13 - Proposed
Major Schemes Programme
These programmes are
not comprehensive but show the latest position. It is hoped that, as further
transport planning and assessment work is undertaken, future years’ programmes
will become better defined. They will always need to be kept under review
to reflect the annual SCP allocations, availability of additional funding
and programme changes.
-
Financial and Staff
Implications
- The financial
implications are as set out in the report. Assessment, promotion and
design of schemes in the programme will be undertaken by a combination
of existing staff and Babtie, the County Council’s term consultant for
engineering design. The increasing size of the transport capital programme
is putting pressure on client resources, especially as it is proving
difficult to recruit experienced staff in the face of a national skills
shortage. Babtie are already providing some client project management
staff and this is likely to have to increase in future.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:-
- approve
the 2002/03 transport capital programme set out in Annexes 2
to 7, subject to any additional schemes, for which finance is
available, being added following consultation with the Executive
Members for Transport and Strategic Planning & Waste Management;
- approve
the provisional programmes for 2003/04 and 2004/05 set out in
Annexes 8 to 13 as a basis for the development of future programmes;
and
- ask
the Director of Environmental Services to update the Executive
on progress on the transport capital programme in October 2002.
DAVID
YOUNG
Director of Environmental Services
CHRIS GRAY
Director of Business
Support & County Treasurer
Background
papers : Executive 22 January 2002 – item EXC6 – Supplement
Executive
19 February 2002 – item EX14
Executive
19 March 2002 – item EX19
Contact
Officer : Eddie Luck - Tel: 01865 815845
April
2002
Return
to TOP
|