|
Return
to Agenda
ITEM EX26
EXECUTIVE
– 22 JANUARY 2002
BATH ROAD
AND BEARGARDEN ROAD, BANBURY:
TRAFFIC MANAGEMENT
MEASURES
Report by
Director of Environmental Services
Introduction
- This report details
the response to the latest consultation on traffic management measures
in the Bath Road/Beargarden Road corridor which was approved at the
Highways & Road Safety Sub-Committee on 23 August 2001. It reports
on the informal consultation in which three options were provided to
residents, allowing them to take an active part on the form that traffic
management measures should take.
Background
- As a result of
accident remedial measures exhibitions for North Bar/Horsefair/South
Bar, Bath Road and Beargarden Road were identified as needing traffic
management. Fears were raised at the North Bar exhibitions and subsequent
consultation that with the introduction of the measures on North Bar
increased rat-running and displacement of traffic flow along the Bath
Road/Beargarden Road corridor would result.
- Following the
initial North Bar consultation we also undertook a consultation in the
Bath Road/ Beargarden Road corridor on an initial traffic calming scheme.
The response to that consultation proved very positive with 63% of the
returning questionnaires being in favour of some form of traffic calming.
The original consultation plan showed humps and cushions. While not
all responses were in favour of this particular form of traffic calming,
they did support the principle. As a result of this response the Highways
& Road Safety Sub-Committee on 23 August 2001 agreed to consult
residents further on a series of options to gauge their support for
a particular design.
Consultation
- Three options
were offered to the residents:-
- Option A
(drg.no. BPN652/B3011), using primarily 15mm platforms, mainly
at junctions, with buildouts to either end of Bath Road.
- Option B
(drg.no. BPN652/B3012), a mixture of buildouts, give way priority
single traffic working, and low 15mm platforms.
- Option C
(drg.no. BPN652/B3010), using 70mm humps, tables, and speed cushions.
- Of the 265 frontagers
of Bath Road and Beargarden Road consulted, 54 replies were received,
of which nineteen preferred Option A, three Option B, and twenty
seven Option C. Five others responded did not offer a preference. Additional
comments were also made which have been listed in
Annex 1. These points will be considered when
we undertake detailed design.
Options
- Cherwell District
Council and local residents have represented that it is essential for
traffic management measures to be introduced in Bath Road and Beargarden
Road prior to the commencement of the major works on North Bar/ South
Bar, due to start after Easter 2002.
- The result of
the low response to this consultation is the difference of 8 between
Options A and C. This is not enough in my view to support construction
of road humps (Option C) as a chosen measure for traffic calming. Option
A (low 15mm platforms) might not be as effective in achieving the aims
of reducing speeds and volume of traffic along this busy corridor as
Option C, but it would allow for swift introduction prior to the major
works at substantially lower cost.
- Should monitoring
prove this to be ineffective the implementation of the full road hump
scheme could proceed, subject to further consultation, with minimal
abortive cost.
Financial
and Staff Implications
- The scheme will
be funded from SCA and developer contributions. The low platform Option
A would cost approximately £10,000 for both Bath Road and Beargarden
Road. The additional cost of implementing the full road hump scheme
(Option B) would be approximately £40,000.
- The County Council’s
engineering consultant, Babtie, is undertaking the design work. Project
management is being carried out by Environmental Services officers and
can be encompassed within current staffing levels.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to:
- authorise
the immediate implementation of Option A, as shown on drawing
No BPN652/B3011, subject to monitoring of the effectiveness
of the measures in terms of vehicle speeds and the level of
traffic using Bath Road and Beargarden Road as a through route;
- in
the event of monitoring showing that Option A has failed to
reduce vehicle speeds and through traffic, authorise formal
consultation on the introduction of possible further measures
in the form of Option C as shown on drawing No BPN652/B3010.
DAVID
YOUNG
Director
of Environmental Services
Background
papers : Nil
Contact
Officer : Mike Wasley Tel : Oxford 810464
January
2002
Return to TOP
|