|
Return
to Agenda
ITEM PN9
PLANNING
& REGULATION COMMITTEE – 17 OCTOBER 2005
MINERALS
AND WASTE LOCAL PLAN
PROGRESS
REPORT ON THE APPLICATION FOR NON-COMPLIANCE WITH CONDITION (A) AND SCHEDULE
B PART 1 (4) OF PLANNING PERMISSION REFERENCE W142/84 TO EXTEND THE END
DATE OF CONCRETE BLOCK WORKS TO 31 DECEMBER 2028 AT CONBLOC, DIX PIT COMPLEX,
STANTON HARCOURT, APPLICATION NO. W2001/1189
Report by
Head of Sustainable Development
Introduction
- On 18 July 2005
this Committee considered a report on possible action to be taken regarding
an application for development at the Conbloc site (see plan)
(download as .doc file).
The Committee had originally granted permission for the application
in October 2002, subject to routeing and 106 agreements, which have
not yet had been finalised (Minute 37/05). When this matter was discussed
at the September meeting the Chairman suggested that a further report
on the latest position be brought to this meeting.
- On 18 July 2005
the Committee resolved to grant permission for the development subject
to a routeing and a section 106 agreement being concluded within one
month of the date of the Committee or such later date that the Solicitor
to the Council might advise. Permission was subject to (and I paraphrase):
- departure from
the Development Plan procedures
- legal agreements
to cover:
(i) routeing
away from Sutton and Stanton Harcourt
(ii) financial
contributions to necessary and reasonable highway improvements;
(iii) imports
of sand and gravel only from Lower Windrush Valley quarries; and
(iv) a
permissive footpath along the River Windrush.
- rewording of
condition (A) and Schedule B part 1 (4) of permission W1421/84 to
allow the development to continue to 31 December 2028 with restoration
by 31 December 2029; and
- updating of
other conditions.
In
addition, Committee resolved that in the event that the agreements
had not been concluded within the timescale stated, then the Director
for Environment & Economy was authorised to refuse application
W2001/1189 for the following reasons:
- it was contrary
to policy SH2 of the Minerals and Waste Local Plan in that the
development could lead to an intensification of traffic levels
and intrusion in the villages of Sutton and Stanton Harcourt.
- it was contrary
to policy SH4 of the Minerals and Waste Local Plan and T6 and
T8 of the Oxfordshire Structure Plan 2016 Deposit Draft (as modified)
in that necessary and reasonable improvements to the B4449 and
A415 would not be achieved.
- it was contrary
to Oxfordshire Structure Plan 2016 Deposit Draft (as modified)
policy T8 in that the development could cause adverse transport
impacts.
- it was contrary
to policy SH5 and SH6 (b) of the Minerals and Waste Local Plan
in that the establishment and long-term management of a permissive
footpath along the River Windrush has not been secured.
- Officers were
also authorised to take any necessary enforcement action to end unauthorised
development.
Progress
on the Application
- The reason that
the application was brought back to the July meeting of this Committee
for further consideration was because of the delay in signing the legal
agreements. The aim had been to achieve a swift conclusion and indeed
it has had the effect of securing significant progress. Wording on the
proposed agreements has been finalised and fair copies sent to parties
for signing. However, at the time of writing this report no planning
permission has been issued as the agreements have not been signed and
completed.
- A briefing note
was circulated to Councillors at the end of September explaining progress
on the preparation and signing of the agreements. (Annex 1) (download
as .doc file).
- The departure
procedures mentioned in the minute had been carried out earlier and,
in December 2002, the Secretary of State wrote to say he did not want
to call in the application for his determination. Therefore, if the
agreements are completed soon then the permission can be issued before
the date of this meeting of the Committee and the latest position on
that can be reported orally at the meeting.
- It was reported
at the last meeting of this Committee that the signing of the agreements
was expected to happen soon and consideration should be given to refusal
if the agreements had not been concluded by the date of this Committee
(see minute 40/05 – Item 3 on this agenda).
Possible
Actions if Agreements have not been signed by the date of this Committee
- It is recognised
that since these agreements involve another party (Steve Hill Ltd),
in addition to the applicant, there is potential for delay in concluding
the agreements. However, if the third party does unduly delay the signing
then the application could be refused. A decision to refuse permission
should not be taken lightly since there is, in this case, a strong likelihood
of appeal. The appeal process can be time consuming and cannot guarantee,
if the appeal is upheld, the same conditions and agreements we are seeking.
There is also a risk of costs if the matter is proceeded unnecessarily
to Inquiry. In addition, once a refusal is issued, even if the agreements
are completed, the appeal process must be completed, or a new application
made and processed, if permission is to be forthcoming. If more time
is allowed now to complete the 106 agreement and the routeing agreement
the same outcome may be achieved much earlier and time and money saved
on appeals and on processing a new application.
- The absence of
planning permission for this development means that the development
taking place is unauthorised. The alternative to refusing permission
is to serve an enforcement notice requiring the development to stop
and the site to be cleared in accordance with the provisions of the
original permission W1421/84. Enforcement action forms part of the Committee’s
resolution of 18 July 2005. Taking enforcement action recognises that
there is a breach of control. It would be expedient to take action as
the matters set out in the proposed legal agreements (see paragraph
2) have not been secured. Hansons could appeal any notice but the current
application would still be extant. The appeal process would still leave
time for the permission to be issued if the agreements were to be signed,
but would enable the breach of planning control to be addressed if they
were not. In my view, the avoidance of an enforcement appeal at which
the delay in signing agreements would be the prime consideration, would
be in Hanson’s interest and be likely to precipitate the signing of
the agreements, resulting in a positive outcome. In any event, a Planning
Contravention Notice (PCN) has been served to gather information which
is necessary in the Enforcement process.
Conclusion
- In the event that
the agreements relating to application W2001/1189 have not been signed
then the County Council should not refuse the application but take enforcement
action against the unauthorised development at the Conbloc site and
the clearance of the site.
RECOMMENDATION
- It is RECOMMENDED
that, if the routeing and section 106 Agreements relating to planning
application W2001/1189 have not been signed by the date of this Committee
then:-
(a) the
Head of Sustainable Development be authorised to take enforcement
action to require all the operations on the Conbloc site to cease
and the site to be cleared in accordance with planning permission
W1421/84;
(b) if
the agreements are subsequently signed, to confirm that the Head
of Sustainable Development be authorised to grant permission subject
to:
(i) rewording
of condition (a) and schedule B Part 1 (4) of permission W1421/84
to read:
The
development hereby granted shall be for a limited period expiring
on 31 December 2028 or for the life of the adjacent landfill
site subject of planning permission 0293/93, whichever is
the sooner. The site shall be restored in accordance with
an approved restoration plan to be submitted within one month
from the date of this permission and approved in writing by
the Minerals Planning Authority and implemented by 31 December
2029 or within one year of the end of landfilling (whichever
is the sooner) in the area subject of planning permission
0293/93; and
(ii) updating, as appropriate, of the other conditions imposed
on permission 0293/93.
CHRIS
COUSINS
Head of Sustainable
Development
Contact
Officer: John Duncalfe Tel: Oxford 815356
Background papers: File ‘Conbloc Stanton Harcourt Variation of Condition
consent no. W1421/84’ reference 8.5/4004/3 in Planning Implementation
Group Office, Speedwell House, Oxford
October
2005
Return to TOP
|