|
Return
to Agenda
ITEM CM8
COMMUNITY
SAFETY SCRUTINY COMMITTEE - 3 JULY 2006
FIRE SERVICE
COMMAND AND CONTROL ROOM – THE FIRECONTROL PROJECT
Report by
Senior Divisional Officer Colin Thomas
(Oxfordshire’s
Senior User for the FiReControl and Firelink Projects and Joint Regional
Project Board member)
Purpose/Background
- This note brings
Members up to date following earlier reports.
- Further information
is available via the national FiReControl and Firelink websites https://fire-control.org.uk/,
https://firelink.org.uk a new
FRS website https://frsonline.fire.gov.uk
and through a periodic local briefing note available on the OCC inter/intranet
(under Community Safety / Fire).
Project
Timescale
- The estimated
date for Infrastructure contract let for FiReControl has slipped
slightly from 1st/2nd to 2nd/3rd
quarter of 2006 although this has not led to any revision of the estimated
go-live date for the RCC which remains at 2008/2009. The earliest the
South East RCC is expected to become operational is early in 2009. We
are not aware of any other changes and the national project team have
said that they are expecting to move to the Best and Final Offers stage
soon in the process to let the Infrastructure Services contract.
- The Joint Regional
Project Board meeting, held on 25 May 2006, concentrated on Firelink
with presentations and displays by the Firelink project team. Following
contract award more detail is becoming available. We now expect the
initial background work to integrate Firelink into our existing control
systems to take place in 2007 with the fit-out of vehicles following
in 2008. The system will provide voice communications until the Regional
Control Centre comes into operation when full data services will be
activated providing information directly to a mobile data terminal in
appliances and officers’ vehicles. Work is still ongoing to determine
the costs of service provision and maintenance but it is already clear
that this could represent a considerable increase when compared to our
current radio system expenditure. DCLG will pay for basic system provision
and operation until the South East Regional Control Centre is fully
operational. Thereafter, DCLG should meet the additional costs of the
system within the overall revenue support grant to the Council but the
detail of this has yet to be confirmed.
Accommodation
- It is anticipated
that the ground breaking ceremony for the start of the build of the
South East RCC at the Kite’s Croft Business Park of construction work
will take place in October 2006. Construction work on all 3 of the first
wave Regional Control Centres (South West, East Midlands and North East
Regions) is now well underway. Details of the work can be found on the
FiReControl website.
Process
Work
- The FRS is undertaking
a major task to determine the implications of implementing the first
40 Convergence Outcomes as approved by Chief Fire Officers’ Association.
These are the actions necessary to standardise processes, terminology
and standards to allow a Regional Control service to operate successfully.
This is the first work for FiReControl to be undertaken under the direction
of the FRS Joint Implementation Group and has proved to be a good test
of the structures set up within the brigade to coordinate project work.
At the time of producing the report the assessment is still ongoing
but already it is clear that the work involved in developing new processes,
changing documentation and systems, data collection, any necessary modification
of existing systems plus training all personnel to ensure effective
operation is a major task which will impact right across the brigade.
The initial assessment work will be completed by 30 June 2006 and the
results from all 46 FRAs in England will be analysed by the national
project team. One possible result is that some of the more demanding
Outcomes may be simplified; a result we would welcome.
- Following the
earlier work on Out of Scope activities (tasks currently carried out
by our Control room that will not be undertaken by the Regional control
Centre) the national project has released updated process diagrams which
now incorporate changes to both ‘in scope’ and out of scope’ processes.
The Regional Project Board has tasked the Strategic Gap Work stream
to review the work done earlier to estimate the resource required to
meet Out of Scope work in brigades. The aim is to refine the estimates
and explore the potential for regional and sub-regional collaboration
to reduce costs. We plan to be fully involved in this work. The outcome
will be presented to the Regional Project Board later in the year.
Finance/Legal
- There is still
uncertainty over the costs for both FiReControl and Firelink. Although,
in the case of Firelink some more reliable costing information is expected
to be released in July 2006 that should allow us to assess the costs
for the options for the maintenance of the system. The Full Business
Case (FBC) for FiReControl is now not expected to be issued until autumn
2006.
- The Fire Lawyers
Working Group has put considerable work to look at the issues surrounding
TUPE, redundancy and wider personnel issues. However, whilst progress
has been made there is a divergence of legal opinion on several issues
concerning TUPE and how consultation should be handled and we await
firm guidance before we can reliably inform staff on these vital aspects
of the project. Much will still depend upon the decisions made on all
of these issues will be made by the Employing Entity for the RCC once
this is in place.
Governance
- The Cabinet discussed
the response to the DCLG Consultation Document on the governance of
the Regional control Centre Company on 6 June 2006. DCLG asked for general
comments on the suitability of the Articles and Memorandum of Association
and the Authority’s view on 7 specific questions. The stance taken was
developed as a result of detailed work by Council legal staff (and the
Fire Lawyers Network) and the Fire Executive. Following Cabinet direction,
a response was sent to DCLG by the 14 June 2006 deadline. The aim was
to provide positive criticism of the draft proposals. These still require
additional work as they fall short of the Fire Authority’s requirement
to ensure a robust governance structure that allows effective management
of the RCC whilst maintaining the level of FRA control to match local
accountability. The DCLG target is to have the governing entity structure
in place by the beginning of January 2007. This is a challenging timescale
with several significant issues yet to be resolved. The Fire Authority’s
response is attached at Annex 2 (download
as .doc file) for Committee members’ information.
(Annex 1 - download as .doc file)
People
and Organisational Design
- We continue to
maintain our policy to fully staff the Control Room. One of our experienced
control staff left at the beginning of June 2006 leaving the staffing
1 below establishment. The reason for leaving was uncertainty for the
future, primarily because of the FiReControl project. Subsequently,
we are in the process of recruiting 2 additional Control Room staff
to bring us up to 1 over establishment. However, the training and experience
necessary to become fully competent as a Control operator takes 2 years
- it is a demanding job requiring a high degree of knowledge, an ability
to operate accurately under pressure and deal with the unexpected. The
loss of experienced Control Room Operators and the subsequent reduction
in the overall experience of Control room staff is of concern and the
present lack of firm timescales and reliable information on personnel
issues such as TUPE and Redundancy/redeployment exacerbates the problem.
As the time left before the Regional Control Centre comes into operation
reduces, recruiting and retaining staff, in particular experienced staff,
is likely to become more difficult and is regarded as our highest risk
to maintaining our control service. In the meantime, we are actively
investigating the measures that can be taken to inform and reassure
staff. As part of this work we are investigating how to help staff take
advantage of any redeployment opportunities whilst maintaining the current
control service until the Control Room eventually closes.
COLIN
THOMAS
Service Support
Manager / FiReControl & FiReLink Senior User
Background
papers: Nil
Contact
Officer: Colin Thomas Tel: (01865) 855211
June
2006
Return to TOP
|