Report
by Head of Transport
Introduction
- As part of the
development of a countywide network of Premium Routes and Interchanges,
the County Council is looking to expand Park & Ride services to
destinations other than the city centre.
(Detailed Project Appraisal)
(Resource Appraisal - download as .doc
file)
- The London and
Gatwick/Heathrow Airport services that previously stopped on the A40
are now operating from the site on a trial basis. A 30 minute frequency
service from Thornhill Park & Ride to the Churchill and Nuffield
Hospitals has also been in place since May 2003. Additionally, consideration
is being given to a new service to the John Radcliffe Hospital. The
Council also has aspirations to explore the possibility of using the
site as a terminus for other local bus services offering an interchange
with services to the city centre, the hospitals and the express services.
- The existing turning
loop struggles to cope with the large number of buses using the facility
which has led to congestion and difficulty for users as buses cannot
always stop in the most convenient locations. This leads to a potential
risk to pedestrians/passengers as they negotiate the turning area in
order to reach their bus. There is already a risk of disruption to services,
and with any further expansion of services the situation would become
unmanageable.
- To meet these
increasing demands a new bus terminus and upgrade of the remaining car
park area has been promoted. The terminal building would contain enclosed
waiting facilities, public toilets and an elevated office for staff,
giving good visibility over the site.
- In March 2004
the County Council’s Executive Committee approved a Project Appraisal
to the value of £1.97M for the provision of a new bus terminus and to
complete the upgrade of the existing car park.
- The initial design
and cost estimate was based on the car park receiving a surfacing overlay
with minimum changes to the existing car park foundation. The consultant
has since identified that the existing car park foundation is frost
susceptible and therefore would require replacement of all material
to a depth of 450mmm below finished car park level. Design was progressed
on this basis.
- A further addition
to the project was the provision of a temporary bus terminus to maintain
current bus services whilst the main construction works were carried
out.
- In preparing the
final contract documents a more detailed cost estimate was prepared
and the consultant reported that the overall cost had risen to £3.1M.
This was a significant increase on the approved project appraisal and
a review of the whole project was undertaken.
- This report details
the review process that was carried out, offers a recommendation on
how to proceed and seeks approval to the revised project appraisal.
Review
of the Scheme - Costs and Funding
- A review of the
costs of the individual elements revealed that the building costs had
not risen significantly and the major increase was attributable to the
works required to the car park upgrade, the introduction of the temporary
bus terminus area to maintain services during construction and the numerous
ancillary works such as lighting, drainage, landscaping and CCTV.
- Unless the permanent
terminal building is changed significantly there is little scope to
reduce the cost of its works. It is considered that the success of the
new interchange facilities relies heavily on the provision of the terminal
building as currently defined. Any reductions to the cost of the whole
project must therefore come from the works to and associated with the
car park area.
- Replacing all
the frost susceptible material to 450mm below finished road level added
some £275k to the car park costs. If this cost is to be reduced then
the original concept of an overlay to the existing car park would have
to be reconsidered.
- Site investigation
revealed that the existing drainage system was only a soakaway system
and in need of maintenance. If the overlay was applied to the car park
then a piped drainage system would have to be provided to cater for
the surface water run off.
- It became evident
that substantial savings could not be achieved to reduce the cost to
a level approaching the original £1.97M. The maximum saving on the earthworks
was only in the region of £200k and there are no other areas where major
savings could be gained. It was therefore concluded that with the level
of funding available it would not be possible to construct the original
proposals of a new bus terminus and building, upgrade of the car park
and all ancillary works. A lesser scheme would have to be considered
to match the available funding.
- Provision of a
new bus terminus layout with a building is considered the priority and
a new cost estimate has been prepared together with a revised project
and resource appraisal. An upgrade of the remaining part of the original
car park would be deferred until a later date when funding becomes available.
Some necessary minor repairs will be undertaken to areas of the car
park to maintain its serviceability until a major refurbishment is undertaken
in the future.
Environmental
Implications
- The proposal is
consistent with the latest national and local guidance in promoting
the use of public transport and Park & Ride. Environmental benefits
of the scheme include reduced traffic congestion within Oxford and on
routes into London, providing improved environmental conditions in the
City and surrounding area.
Financial
and Staff Implications
- As a result of
the design review process the start date for the project has moved from
2005/06 to 2006/07. This means there is an underspend of £200K in SCE
allocation for 2005/06, which has been identified by standard budget
monitoring procedures in Environment and Economy. To offset this underspend
action is already being undertaken in order to identify additional schemes
that can be built in this financial year.
- The cost estimate
to provide only the new bus terminal building and the bus turning loop
including all design and supervision fees is £2514k.
- Funding for the
scheme will primarily come from the On-Street Parking Surplus with support
from developer contributions and Credit Approval secured under the new
Local Transport Plan process. The scheme will effectively use up all
available on-street parking surplus in 2006/07.
- Design and supervision
will be carried out by consultants Atkins. The management of the scheme
will be undertaken by Oxfordshire Highways.
RECOMMENDATIONS
- The Cabinet
is RECOMMENDED to approve Project Appraisal H173/1 and the implementation
of the amended scheme as described in the report and Appraisal.
STEVE
HOWELL
Head of Transport