ITEM
EX19
EXECUTIVE
– 11 DECEMBER 2001
RADIO REPLACEMENT
PROJECT
Report by
Chief Fire Officer
Introduction
- There is a national
requirement to transfer from the present emergency radio frequencies
by 2005 due to the commercial sell-off of the existing frequencies and
changes in technology globally. This has resulted in a regional procurement
approach being recommended by the Home Office for the purchase of new
systems. Her Majesty’s Fire Service Inspectorate has now set up a special
project team and is developing a national radio strategy to support
such initiatives.
Current Position
- The two latest
publications from the Home Office develop a framework of Memorandum
of Understanding and a model for regional apportionment of costs for
the replacement scheme. The model Memorandum of Understanding has been
designed to provide identified review points where individual participants
must decide either to proceed with the project or withdraw. It acknowledges
that brigades do not have delegated decision-making powers to bind each
other within a group and that project decisions to progress the procurement
process will need to be referred to elected members in each individual
Fire Authority. (Oxfordshire is a member of the South East Region with
eight other brigades.) The stated aim of this approach is to facilitate
the objectives of the national radio strategy and to encourage partnering
as an option for local government service delivery and for securing
best value.
- The regional approach
has been to appoint a project manager and board together with individual
user groups to examine the implications of adopting any particular technological
solution. Oxfordshire Fire Service has already appointed a Board member
to the regional project group and will continue to support this approach.
The Brigade will also ensure that it has a fall-back position by utilising
its own county-wide GSM telephone system which it has progressed in
the last 3-4 years, based on some of the network of telephoning masts
sited on fire station drill towers.
Funding Issue
- Within the cost
apportionment model, several alternative models are given which will
cover capital and operating costs of new equipment, maintenance rental
and on-going service charges etc, together with the project running
costs (Annex 1 attached). The four alternatives
provide different options according to weightings based on such parameters
as the number of Control Room operators per brigade, area of brigades,
incidents and number of fire stations. The percentage spread of costs
between the alternatives for Oxfordshire range from 8.74 to 9.72. At
this stage, it is too early to determine the scale of final project
costs. This is because on a national basis no replacement scheme has
yet been developed. One region (the South West) has now completed its
tendering process but the contract has yet to be awarded.
- The cost apportionment
for Oxfordshire is in the scale from £87,400 to £97,214 per million
pounds cost of the project. This is a differential of £9,814 between
best and worst case per million pounds.
- To date the best
estimate of the capital purchase cost to this Council is approximately
£1.8m. This has previously been reported to Committee and included in
the capital preparation programme. It should be emphasised that this
estimate may need to be revised in the light of the cost of the first
contracts being awarded in the rest of the country.
- Within the next
few months it is anticipated that the Project Board will be reconvened
in order for discussion and agreement to be reached on which cost apportionment
model will be applied to the project. As there are nine brigades involved,
it is anticipated that this will be a difficult process, particularly
given the potential differentials for the other eight brigades which
are considerably greater than that faced by Oxfordshire.
- Both the Memorandum
of Understanding and apportionment of costs framework documents have
been referred to the Solicitor to the Council for validation. Assuming
these are in order, it will then be necessary to progress the project
which will be set against tight timescales if all brigades in the region
are to have their replacement schemes in being before 2005. It will
therefore be necessary for the officers of the brigade to progress the
project whilst referring back to the Executive at relevant milestones.
In order to progress the project to the next stage, the Chief Fire Officer
therefore seeks authority to negotiate Oxfordshire Fire Service’s position
within one of the four cost apportionment models illustrated in Annex
1.
- It should be noted
that initial project costs (to develop the specification for the new
system) will shortly start to accrue. There is current provision of
£120,000 in the main capital programme with £60,000 in the preparation
pool (this is in addition to the £1.8m referred to above). This provision
will be reviewed as the project details and application of cost apportionment
is progressed.
RECOMMENDATION
- The Executive
is RECOMMENDED to authorise the Chief Fire Officer to negotiate and
(subject to consultation with the Executive Member for Community Safety)
agree Oxfordshire’s share of the costs of the radio replacement scheme
project, within the parameters of the four options in the apportionment
of costs model summarised in the Annex to the report.
JOHN
PARRY
Chief Fire
Officer
Background
Papers: Nil
Contact
Officer: John Parry (tel: Oxford 842999)
November
2001
Return to TOP
|