Return
to Agenda
ITEM EX19
EXECUTIVE
– 23 JULY 2002
PEDESTRIAN
IMPROVEMENTS - SOUTHAM ROAD, BANBURY
Report
by Director of Environmental Services
Introduction
- This report details
the response to the consultation for a Pelican crossing outside St Mary’s
School, Southam Road, Banbury and the progress made to introduce pedestrian
phases on all legs of the Warwick Road/North Bar/Southam Road/Castle
Street junction.
Background
- The Headteacher
and parents of St Mary’s School have raised concerns about the safety
of the existing pedestrian crossing at the junction of Southam Road
and Warwick Road and requested that a safer option be investigated.
This had been previously reported to Highways and Road Safety Sub-Committee
on 24 May 2001. The existing pedestrian crossing adjacent to the Warwick
Road junction requires pedestrians to cross three lanes of traffic.
There are also some safety concerns with that location associated with
the possibility of vehicles failing to stop in time when turning left
from Warwick Road. The introduction of the proposed Pelican crossing
at St Mary’s School (see drawing No MP/4/001 Annex 1) will provide a
safer alternative for pupils attending the school as it relocates them
away from the potential conflict point at the junction.
- Currently there
is a school Crossing Patrol Officer (CPO) at this location who helps
pupils cross the road, however funding for the CPO was discontinued
by Cherwell District Council on 31 March 2001. As result of this and
the safety concerns raised over the existing crossing, the County Council
has agreed to continue to fund the CPO post until a safer alternative
can be provided.
Consultation
- Letters were sent
to the usual consultees and residents in the vicinity of the proposed
Pelican crossing and street notices erected. The consultation period
ran from 24 April to 24 May 2002.
- Of the eleven
responses received from the consultation six raised the same concern:
that the proximity of the Pelican to the signalised junction at Warwick
Road would increase congestion at this location. Four offered support
for the implementation of the Pelican and one offered no comment.
- The concern raised
had already been recognised and it is for this reason that the Pelican
will be linked to the Warwick Road signals to avoid increasing congestion
in this area. This linking will prevent undue delay to motorists.
- Banbury Town Council,
who did not object to the introduction of the Pelican, suggested that
a Puffin crossing could be more appropriate at this location as it would
minimise possible delays to vehicles. As explained in the paragraph
above, this will be achieved by linking the crossing to the nearby traffic
signals.
Warwick
Road/Southam Road/Castle Street/North Bar Signalised Junction
- As previously
reported at the Highways & Road Safety Sub-Committee on 24
May 2001, the North Bar/Horsefair/South Bar accident remedial
scheme was terminated at the Warwick Road junction to allow for further
modelling work of this junction to be undertaken. This work has now
finished and suggests that a scheme can be implemented that allows for
additional pedestrian crossings on Warwick Road, Castle Street and North
Bar without any increased delays to motorists at peak times.
- As the start of
the accident remedial measures has been delayed to coincide with the
maintenance scheme, there is now an opportunity to implement pedestrian
improvements at this junction within the same contract. This will provide
an overall cost saving, as the contractor’s establishment charge will
be minimised. There will also be a significant reduction in disruption
to the public by carrying out these works together with the main scheme
rather than revisiting the same site at a later date.
Financial
and Staff Implications
- Additional funds
are needed to implement both St Mary’s Pelican crossing (£40,000) and
pedestrian crossings at the Warwick Road junction (£70,000). These improvements
are not in this year’s Transport Capital programme as they were originally
planned for 2003/04.
- The out-turn of
the 2001/02 Transport Capital Programme has now been determined and
some Supplementary Credit Approval (SCA) underspend has been identified.
Allocation of those funds is under review in consultation with the Executive
Members for Transport and Strategic Planning & Waste Management.
- The work can be
accommodated within existing staff resources.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to approve the implementation of the St Mary’s School
Pelican crossing and the Warwick Road junction improvements as described
in the report, subject to the Director of Environmental Services, in
consultation with the Executive Members for Transport and Strategic
Planning & Waste Management (and in the case of (a) with the local
member):
- making
any detailed amendments appearing necessary as a result of safety
audit of the proposals; and
- identifying
funds to cover the cost of the respective schemes within the
2002/03 Transport Capital Programme.
DAVID
YOUNG
Director of
Environmental Services
Background
papers: Nil
Contact
Officer: Mike Wasley Tel: Oxford 810464
July
2002
Return to TOP
|