Return
to Agenda
ITEM EX13
EXECUTIVE
– 23 JULY 2002
CORNMARKET
STREET, OXFORD
Report
by Director of Environmental Services
Introduction
- This report discusses
the construction failure of the environmental enhancement scheme in
Cornmarket Street, considers possible options for improvement and their
impact on the out-turn costs and the programme for the implementation
of the scheme. It also recommends the preferred way forward.
Background
- The County Council’s
appointed consultants, Landscape Design Associates (LDA) and Peter Brett
Associates (PBA), carried out the design and supervision of construction
of the environmental enhancement scheme in Cornmarket Street. Site works
commenced early in July 2001 and cracks in the granite block paving
began to appear from mid-September onwards. Although several measures
were taken by the consultants to see if the cracking could be halted,
cracking still continued up to the end of October 2001 when the agreed
break for the Christmas shopping was taken.
- The design consultants
called in an independent expert to establish the reason for the failure
and to suggest a way forward. Various tests were carried out and a series
of interim reports followed, culminating in a final report at the end
of January 2002. Because of the complex nature of the failure, the County
Council engaged two additional independent experts to advise on the
findings in the report. The views of these two experts were received
in March 2002 and considered by the officers of the City and County
Council, and also passed to the design consultants for information.
Meantime further work in Cornmarket Street was suspended. Counsels’
advice has been taken throughout (hence the apparently slow progress)
to minimise liability for the County Council given the complex contractual
arrangements.
- LDA have considered
the various findings and produced their suggested proposals for the
way forward. These proposals formed the basis of a presentation to relevant
County and City members at a meeting at County Hall on 26 June 2002.
A copy of the slides presented at that meeting is in the Members’ Resource
Centre.
Possible
Options
- Three possible
options were described in detail at the consultants’ presentation. All
three options feature an enhanced specification for the footway and
carriageway construction. In broad terms, the distinction between the
options lies in the use of different materials for bedding and jointing
of the granite blocks, as details for the enhanced footway construction
are common to all three. Construction details of the possible options
are summarised in Annex 1.
- Enhanced specification
details have a significant bearing on the construction costs of the
scheme. The consultants’ estimates of construction costs for them vary
between £2.94m for Option 1 to £3.21m for Option 3. These estimates
can be compared with an original budget construction cost of £1.96m
and the present projected budget of £2.49m, which includes current contractor
claims (including for instance those arising from problems with public
utilities work) under the existing construction contract.
- On-site and off-site
trials and tests would be required for any of these 3 options. This
would significantly delay completion of the work. However, even with
the enhanced specification, LDA are unable to give a guaranteed design
life for the new construction as the specifications have not yet been
tried and tested. It is likely that all options would require the purchase
of new granite blocks that are cut to stricter tolerances. Given the
new specification, the final granite paving will offer difficulties
to re-instatement following any public utility works.
- The City Council
introduced the Public Realm Strategy (PRS) for Oxford in September 2000.
The County Council agreed to adopt the principles of PRS for the Cornmarket
Street scheme. This strategy, for principal streets with restricted
traffic, seeks to have either large granite setts (or blocks) or
asphalt with coated granite. Although the PRS indicated that Cornmarket
Street should have a paved surface, the use of a flexible surface, as
on similar principal streets, would appear to be a reasonable alternative.
- As the success
of the large granite blocks cannot be assured and their use would incur
further significant delay, it is suggested that a fourth alternative
is considered - Option 4 summarised in Annex
1. This can be implemented without any trials or testing and
its construction costs will be cheaper than the other three options.
The current estimate of construction costs for Option 4 stands at £2.629m
(see Annex 2).
The only departure from the City’s PRS guidelines would be the type
of surface of the carriageway as it is intended that all the other elements
of the PRS relating to the Yorkstone footways and street furniture would
be accommodated with this option. This flexible carriageway option has
the added benefit of enabling future maintenance repairs (following
public utility openings etc.) to be carried out almost seamlessly and
with the minimum additional extra costs to the County Council.
- The estimated
date for completion of the three options suggested by LDA is July 2004
as due account has to be taken of the time required to test and trial
the new specifications, both off and on site, and the time needed to
order and supply the new granite blocks. This assumes that no further
delays are encountered during the construction. The work could start
in October 2002, subject to the County and City Executives’ decision
and agreement of financial contributions. Testing of materials in the
laboratory with trials in the contractor’s yard and in Cornmarket would
provide results during May 2003. Depending on positive results of the
tests and following ordering of new granite blocks, construction could
then re-start in July 2003 and last until October 2003 to allow for
the Christmas shopping break. It would then re-start again in February
2004.
- On the other hand,
the work on Option 4 could also start in October 2002 but as it would
not require any tests or trials, works could be completed in July 2003.
This would still include a similar Christmas break as in the other three
options.
Scrutiny
Committee Views
- The Environment
Scrutiny Committee considered the position in the light of a report
on the LDA/PBA presentation (which some of the members had been able
to attend). At the invitation of the Chair and Deputy Chair of the Committee,
members of the City Council’s Environment Overview & Scrutiny Committee
also participated in the discussion.
- Following a lengthy
debate, the Committee agreed "to recommend the Executive to seek to
pursue in partnership with the City Council the option of an asphalt
carriageway surface, as offering the least risk in terms of capital
cost, performance, and future maintenance liability, with consideration
given to textured surfacing, trees and appropriate street furniture
and investigation undertaken for the longer term of the possibility
of a weight limit in the street"
Financial
Contribution Agreement
- The County and
City Councils have previously entered into a legal financial agreement
that specifies the duties and responsibilities of both councils in relation
to the implementation of the Cornmarket environmental enhancement scheme.
This agreement sets out the details of the scheme, the delivery dates
of various construction phases and also the level of financial contributions;
the City Council’s contribution towards the implementation of the scheme
is currently standing at £1.855m.
- Any departure
from this agreement, including changes to the original specification,
requires formal approval by both Councils. The current agreement specifies
31 July 2002 as the scheme completion date. Option 4 represents some
departure from the original design and it therefore needs to be agreed
with the City Council. It is possible that the City Council would wish
to re-negotiate the present legal agreement and amend the level of financial
commitments that it wishes to contribute towards the revised scheme.
The implementation of Option 4, or indeed any other option specified
by the consultants, depends therefore on both the City and County Councils
approving amendments to the existing agreement and on the level of financial
contributions by the City Council.
Way Forward
- Having reviewed
the options recommended by the LDA and taking into account the high
out-turn and maintenance costs, uncertainties and risks associated with
necessary trials and tests, and the impact of the construction time
on the overall scheme delivery programme, I cannot recommend any of
the three granite options for implementation.
- I have also considered
the possible scenario of the City Council not agreeing to any modifications
to the scheme that did not adhere to the full PRS standards (Option
4). In that situation, the City Council might choose to abandon the
scheme altogether and to withdraw their financial contributions. The
only option available to the County Council would then be to introduce
a standard highway scheme of black tarmac for the carriageway surface
and concrete paving slabs for the footway area.
- It is therefore
my view that the only viable option that would bring the best outcome
for the County and City Councils is the implementation of Option 4 and
the swift settling of the Financial Contribution Agreement between both
Councils.
- The City Council’s
Executive will consider its position in relation to the available options
at its meeting on the 22 July 2002. We have made all our information
available to City officers to advise the City’s Executive Board. I hope
to be able to report orally the outcome of that meeting to this Executive.
Following the meetings of the respective Executives there may be a need
for a further joint meeting in August 2002 where any supplementary information
can be provided.
Environmental
Implications
- The continuation
of the environmental enhancement of Cornmarket Street in accordance
with the City Council’s Public Realm Strategy principles will make a
major contribution to the visual amenity of the city centre and provide
a safer and more attractive environment for pedestrians.
Financial
Implications
- It is difficult,
at this stage, to calculate accurately the total out-turn costs for
implementing any of the possible options. However, a summary table of
the costs as can be best estimated at present is included in Annex 2.
These estimated figures show that the cost of implementing Option 4
stands now at £3.279m. On the assumption that the City Council’s contribution
stays the same, the remaining balance is £1.424m. Taking into account
the County Council’s original budget of £460k, it brings the remaining
balance to £964k. However, the County Council will pursue through appropriate
legal procedures costs attributed to the failure of the construction.
At this stage a reasonable assumption might be that the abortive costs
and fees which the County Council would claim are in the order of £600k.
On this basis the remaining cost would be approximately £364k. This
covers non-abortive work necessary for any improvement scheme and justifiable
claims mainly associated with the public utility work.
- The total out-turn
cost to the County Council depends on the amount of the City Council’s
financial contributions based on the Public Realm Strategy elements
of the scheme. It is possible that the City Council might seek to suggest
that it should modify its current contributions, in the case of Option
4, to reflect the reduction of the PRS elements of the original scheme,
and expect the County Council to balance this additional shortfall.
(The scenario in paragraph 17 above is an alternative option available
to the County Council).
- The proportion
of the increased implementation cost associated with Option 4 that would
require funding during this financial year would need to be accommodated
by reallocation of funds for the 2002/03 capital programme. The remaining
proportion of these costs would need to be set aside in the 2003/04
programme still to be agreed by the Executive.
- The decisions
reached by the Executive and the City Council’s Executive Board will
determine the future of the Cornmarket Street scheme. What determinations
will be necessary as to financial provision by the County Council (including
a project appraisal in respect of the expenditure, if appropriate) will
depend on those decisions, and specifically on which option is chosen
for implementation.
RECOMMENDATIONS
- The Executive
is RECOMMENDED to approve in principle a revised environmental enhancement
scheme for Cornmarket Street based on Option 4 described in the report,
subject to:
- completion
of an agreement between the City Council and the County Council
providing for financial arrangements for meeting the costs of
the scheme in a manner satisfactory to the Director of Environmental
Services and Solicitor to the Council, following consultation
with the Executive Members for Transport and Strategic Planning
& Waste Management and in the light of any further meetings
with the City Council;
- subsequent
determination of the funding within the capital programme 2002/03
and 2003/04 of the County Council’s share of the costs of the
scheme under the financial agreement;
- the
detailed scheme layout for implementation being agreed by the
Director of Environmental Services in consultation with the
Executive Members for Transport and Strategic Planning &
Waste Management.
DAVID
YOUNG
Director of
Environmental Services
Background
papers: Consultants’ report on options for te granite block
scheme; independent advisers’ reports on testing of granite
block construction
Contact
Officer: Dariusz Seroczynski Tel: Oxford 815629
July
2002
Return to TOP
|