FBC Decarbonisation Programme 2024-25

This paper provides an updated cost position associated with the proposed capital works for corporate properties, linked to the PSDS3c grant funding.

Decision type: Key

Reason Key: - Capital Expenditure >£1m;

Decision status: For Determination

Notice of proposed decision first published: 19/12/2024

Anticipated restriction: Part exempt  - View reasons

Explanation of anticipated restriction:
Exempt the table in appendix 1 as it contains budget details around sites which will be in a tender process

Decision due: 21 Jan 2025 by Cabinet

Lead member: Cabinet Member for Finance

Lead director: Executive Director of Resources & S151 Officer

Contact: Sam Thomas, Property Decarbonisation Manager Email: sam.thomas@oxfordshire.gov.uk.

Consultation process

N/A

Consultees

N/A

Plan Reference: 2024/367

Reason No Public Access: None

Confirm that your SLT representative is aware of the item: in progress

Confirm scheduled for DLT/ELT/ SLT/ Informal Cabinet as appropriate: SCB on the 9th Jan, will need to go onto informal cabinet agenda