Delegate authority to the Director of Transport and Infrastructure in consultation with the Head of Legal and Deputy Monitoring Officer to finalise the target cost and programme for Stage 2 (Construction) and issue a Notice to Proceed to Milestone Infrastructure Ltd under the existing NEC 4 Engineering and Construction Contract for the Tramway Accessibility Improvements
Decision type: Key
Reason Key: - Capital Expenditure >£1m;
Decision status: Recommendations Approved
Notice of proposed decision first published: 02/04/2024
Explanation of anticipated restriction:
None
Decision due: 26 Sep 2024 by Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy
Lead member: Cabinet Member for Infrastructure and Development Strategy
Lead director: Corporate Director Environment & Place
Contact: Cris Butler Email: cris.butler@oxfordshire.gov.uk.
Plan Reference: 2024/096