(1)
Change of use of the
materials recycling facility which is the subject of planning permission
reference 10/00361/CM to add biodrying and gasification waste treatment
technologies and associated power generation together with the extension of the
operational life of the materials recycling facility – Application 11/00015/CM
(2) To
continue development of non hazardous landfilling operations without complying
with conditions of planning permission 00/01480/CM 08/02519/CM (as varied by appeal reference APP/U3100/A/09/2117987/NWF)
relating to phasing of landfilling and restoration, life of the site,
restoration and aftercare schemes and tipping levels – Application 11/00026/CM
Agreed subject to an additional condition to
secure the removal of plant within 2 years of it ceasing to operate
Agreed subject to an amendment to an existing condition and 2 additional conditions:
- an amendment to Condition 7 (Annex 1) requiring capping of cells within 12 months of completion of tipping
-
no implementation of this permission unless
or until the gasification plant is operating in the MRF and variation of end
date if plant implementation is delayed, relative to the effect of that delay
in terms of filling rates
-
tipping and restoration of cells 1 – 6, 8
and 9 to be completed by 2015