The Planning
Development Manager introduced the application to the Committee explaining that
it had been submitted by the Environment Agency. This was the second
application submitted. The first application was submitted in April 2018 and
withdrawn in March 2020. Two consultations have taken place and all comments
submitted during both consultations had been considered by Officers. The Senior
Planning Officer presented the presentation and gave detail to the application.
The Team Leader Landscape and Nature Recovery gave clarification on some of the
landscape points.
The application is
for a flood alleviation scheme to reduce flood risk in Oxford through
construction of a new two stage channel from the confluence of the Botley and
Seacourt Streams, extending south easterly to north Kennington; Floodwalls to
the north of Botley Road, at Seacourt Park and Ride and adjacent to Bullstake Close allotments; Floodgates at Helen Road, Henry
Road and Seacourt Park and Ride Flood defences at New Hinksey
between Abingdon Road in the west and the River Thames in the east, Ferry Hinksey Road and north of South Hinksey;
Control structures at Bullstake Stream, Eastwyke Ditch, Hinksey Pond,
Redbridge Stream and Cold Harbour; Bridges and culverts to cross highways and
footpaths maintaining access routes; Spillways, embankments, low flow control
structure, modifications to Seacourt Stream, ford crossings, channel clearance,
ditch widening and deepening, removal of weir and installation of telemetry
cabinets; repairs to existing walls along Osney
Stream and in Hinksey Park. The creation of new and
improved habitat for flora, fauna and fisheries, and change of use of land to
provide exchange for existing open space. Works will include extraction of some
sand and gravel for reuse on the site and exportation from the site.
The Senior Planning
Officer, Matthew Case, updated the Committee on the addenda to the reports
since the report had been published. Members were informed that three further
representations, in objection, had been received, including a response from the
Oxford Flood and Environment Group (OFEG). The issues raised in the objections
were summarised in the first addendum along with the Officer responses.
The recommendation
to the Committee was as follows:
It is
RECOMMENDED that planning permission for application no. MW.0027/22 be granted
subject to conditions to be determined by the Head of Strategic Planning to
include the matters set out in Annex 1 (and any amendments to those conditions
as deemed necessary), signing of a Section 106 Agreement to secure the 30 years
Habitat Management and Monitoring Plan for offsite BNG and a monitoring fee for
both the onsite and offsite Habitat Management and Monitoring Plans (and any
amendments as deemed necessary) and the application first being referred to the
Secretary of State as it would have a
significant
impact on the openness of the Green Belt.
Members asked for
clarification on a couple of points.
The Committee were
addressed by the following registered public speakers:
- Patricia Murphy representing the Oxford Flood Environmental Group
was speaking against the application. The Committee was due to make a key
decision but she felt that the report was flawed. Some vital information
from the recent Compulsory Purchase Order public inquiry had not been
considered, making the application legally unsafe and incomplete. The
Group urged the Council to reconsider the application due to a significant
oversight and improper application of the planning balance between public
benefit and environmental harm. The distinction made between the
compulsory purchase order determination and planning considerations was
invalid. The test should be whether the issues raised were material to the
planning decision, not if they were part of separate processes. Ignoring
the key concerns exposed the Council to potential legal challenges.
Specific failures included adequately considering alternatives and
evidence to the five-kilometre channel through the west Oxford Green Belt.
This proposal was shown to be unnecessarily destructive, costly and of
minimal benefit and non-compliant with mitigation hierarchy. Para 186(a)
of the NPPF mandates avoiding significant harm to biodiversity first then
mitigating and compensating as the last resort. No attempt to avoid harm
had been demonstrated, violating the requirement to Para 186(c),
development that results in the loss of deterioration of irreplaceable
habitats should be refused unless there were wholly exceptional reasons
and a suitable compensation strategy. There were alternatives that do not
lead to the loss of Hinksey Meadow and the
compensation strategy was insufficient. An independent report highlighted
the EA’s failures to adequately model less damaging, no channel
alternatives. The minimal difference between the proposed scheme and the
no channel option wasn’t properly investigated, revealing that not enough
effort was made to explore viable alternatives. The failure to recognise
the MG4A Hinksey Meadow far too late in the
process was a critical oversight. With only four-square miles remaining in
the UK, the EA did not address the mitigation hierarchy for irreplaceable
habitat. This undermines the Council’s ability to accurately assess
compliance. The report also ignores evidence from an independent
hydrogeology expert of potential catastrophic current water changes to the
meadow, although the EA claimed to have data since 2018, this had not been
included in the calculation nor provided to the inquiry, leaving the
Council without crucial information. There was no information on
groundwater flooding risks to evidence. The failures to incorporate
material considerations and to comply with the NPPF renders this
application legally unsound. The Group urge the Council to reject or defer
the decision until all the evidence from the public inquiry had been
thoroughly considered.
- Brian Durham, floodplain resident and retired meteorologist. Brian
Durham worked as anarchaeology specialist for
the City Council. Members had been sent a traffic light map presenting
solutions to issues raised in the Officers report. One detail referred to
a new railway divider that Network Rail commented would be required. But a
local pumping scheme had been offered that completed the scheme without
railway engineering. The two details jointly make the flood scheme
autonomous that the committee could safely approve subject to the draft
conditions. The Defra Secretary of State had asked for the copies of the
redraft planning conditions.
- Dr Chris Sugden, resident of North Hinksey
Village, Chair of Ferry Hinksey Trust and
convener of the Hinksey Environmental Group. Mr
Sugden asked if there was a conflict of interest as OCC were a partner of
the scheme and whether the concerns raised would be considered. Mr Sugden
requested that the application be deferred until evidence from the public
inquiry had been considered. The concerns were that the NPPF was followed
with respect, otherwise legal advice would be sought on a potential
judicial review. No real consideration had been given to the harm to
biodiversity and irreplaceable habitats, neither had been considered
correctly. The 4th Oxford Scout Group would no longer be able
to access the street near the Fairly Easy Trust field, which was an
invaluable resource for scouting activity. The plans could be altered so
access was maintained.
- Tim O’Hara retired chartered surveyor with over 30 years of
experience in public sector in Oxfordshire. The Planning Officer had
identified aspects of the application that conflicted with the plans,
policies and guidelines but the belief was that these were outweighed by
the flood protection benefits of the application. The conflicts of the
application had been understated and the flood protection benefits had
been taken at face value and were therefore overvalued. Mr O'Hara gave
some examples and asked what the EA considered as severe floods. The
Planning Officer repeated the applicants' claims that there would be flood
protection benefits for transport links and utilities, yet the total cost
analysis carried out by the EA suggested that this was too small to even
consider.
- Riki Therivel, an environmental consultant specialising in impact
assessment. The support was there for most of the flood scheme but opposed
to the channel because of its traffic impact, which was partly mentioned
in the environmental statement and the officers' report. The application
suggests that the EA would like to reduce the traffic speed on the A34
near South Hinksey to 40 mph from 70 mph, and
four times faster than the speed out which the HGV's would be exiting the
A34, causing potential accidents and traffic jams. The EA had suggested
that the works would take three years, but this could very easily
increase. This would affect approximately 36 million vehicle journeys,
which had been massively underplayed. It had been suggested that the
issues could be resolved by a construction traffic management plan but
this does not exist yet, however, the only resolution so far would be to
further reduce the speed limit on the A34 to 20-30mph. If the application
was approved, it would be with no real evidence of how the traffic issues
could be solved.
- Dr Tim King, an independent ecologist, associated with Oxford
University, ex member of the governments committee on air pollution and
health, and a plant ecologist. Dr King urged the councillors to reject the
application, knowing that there's an alternative in the background which
could be implemented with relatively short notice. The scheme seemed a
worthwhile idea, when originally suggested 17 years ago. After all, it
would have improved flow at the points where it was currently impeded.
Evidence in the last 7 years, especially from computer modelling has
showed that it makes relatively little difference to the channel, which
has formed a major part of the publicity of the scheme between Botley and
Redbridge and is unnecessary. The meadows had been a worthwhile flood
plain for about 1000 years and if someone decided that they wanted to
build a channel across the equivalent, it would be rejected. The EA
engineers were not equipped to balance the problems with their scheme
against all sorts of other activities, such as the Green Belt, landscape,
biodiversity, local opinion etc. it was up to this committee to balance
the whole thing and reject this premature application, in the hope that a
better alternative can be implemented.
- Peter Canavan, planning consultant and speaking on behalf of the
Oxford Preservation Trust. The Trust had not taken lightly the prospect of
objecting to this scheme. It accepted the need to address the effects of
flooding in Oxford. It supported the principle of flood alleviation,
however the application was an incomplete picture and without all the
evidence, the full extent of the harms of the scheme being presented, a
proper, balanced, planning judgement could not be reached. After having
constant contact with the EA and the County Council over almost 10 years,
the Trust acknowledges that some of its concerns have been considered, but
there remains a very real risk to Hinksey
Meadow. The Trust’s concerns were bought into sharp focus through the CPO
hearings. Whilst the CPO process was separate to the planning decision,
the evidence presented in that process was material to the deliberations.
The scheme was contrary to the City Council’s environmental policies and
to the NPPF, paragraphs 180 and 186. The harms created by the scheme were
not properly understood and therefore could not be accepted to be
outweighed by public benefits. It was therefore impossible to demonstrate
very special circumstances necessary to allow development in the Green
Belt, also contrary to the NPPF, paragraph 153. The issues such as direct
loss of grassland and indirect loss of grassland, the EA had failed to
fully assess the indirect effects from the scheme on the remaining
grassland and without mitigation, these effects would also weigh
significantly against the scheme.
- Jonathan Maddan was speaking on behalf of Hinksey
and Osney Environmental Group against the
application. He had worked as an architect for several years. He, with
others had developed a versatile method of pumping large volumes of flood
water away from Hinksey Meadows with the
capacity of up to 44 cubic metres per second, 4 million tonnes per day.
This conceptual design was presented at the CPO inquiry in January 2024.
The main advantage was that water was pumped in the early stages of a
flood, reducing peak flood levels. This system was powered from local
electricity supply with a back-up generator and the engineering and
technology was worldwide industry standard. Such a system would cost less
and take less time.
- Martin Dowie was speaking as a councillor from Botley and North Hinksey Parish Council, against the application. The
Parish Council had considered biodiversity, recreation and amenities,
traffic and highways, climate change, pollution and health and cost
efficiency. The three main points addressed included that the Parish Council
had not changed its position, it had concerns about the independence of
the application and the economic case for the scheme but was pleased to
see that measures had been taken and the referral to the Secretary of
State. The Parish Council recognised the need for the flood alleviation
scheme and welcomed some of the aspects of the scheme. The Parish Council
did not support the secondary channel and the damage it caused and it
being the element of the scheme that resulted in harm which outweighed the
benefits of the scheme. The Parish Council hoped that the scheme would be
revised, eliminating the secondary channel and modifying the remaining
elements as necessary.
- Sarah Ainsworth was speaking as a resident of North Hinksey, supporting a flood alleviation scheme but not
the scheme in the application. Sarah had personal experience of flooding
and professional experience of high-level planning in flood emergencies to
ensure highly vulnerable people and their families were kept safe. Sarah
was keen to maintain the access to Hinksey
Meadows for residents but also to ensure that public funds were not wasted
on the wrong scheme. There were nine major funders that had a duty to
deliver public benefits. The secondary channel would damage the precious,
beautiful, biodiverse water meadows, being the most expensive and
environmentally damaging part of the scheme. Due diligence should be given
at all aspects of the scheme and delivered by a bespoke scheme.
- Jocelyn Wogan-Browne, a professor of medical studies, was speaking
against the second stage channel. Jocelyn had been very badly flooded in
2007 but not in 2014 because of nuanced local measures in large pumps and
drains keeping the ground and surface water away, outside her home.
Flooding was upsetting, expensive and time consuming to repair. This was
not the correct scheme; it was expensive and would take a long time and
would not eliminate the problem.
- Debbie Hallett, Councillor at Vale of White Horse District Council
was representing the residents of Botley and North Hinksey
and South Hinksey Parish Councils. Councillor
Hallett initially supported the scheme but had concerns about the impact
of the construction on residents. The concerns had now broadened, deepened
and increased. Councillor Hallett asked about what mitigation measures had
been taken to reduce five years of pollution in an already polluted
corridor. The Committee would be weighing up the harms against the
benefits and making a decision. Councillor Hallett asked the following
questions to the Committee:
- How confident were the Committee about the proven benefits of the
scheme?
- How many properties were going to be protected and by what means?
- How confident was the Committee that the scheme was deliverable
taking previous large projects into account such as the railway and
Botley Road?
- What would be the impacts on local areas if the scheme was
abandoned? Were there any mitigation steps planned? How big of a risk was
tolerable?
- 85% of the measures did not depend on the channel and suggested an
incremental approach to the project. Why not implement the most damaging
measures first and then evaluate the outcome?
A flood alleviation
scheme was a good thing, but the costs were tremendous. She urged for careful
balancing of the proven and likely benefits to the responsibilities to all
residents regarding environmental preservation, maintaining existing
infrastructure and fiscal prudence.
- Julia Hammett spoke as Chair of Oxfordshire Badger Group, in
objection to the application. Julia commented that the scheme in its
current form was an environmental disaster and would cause irreversible
damage to biodiversity including protected species, badgers, nature
reserves, meadows and priority habitats. The only compensation would be a
10% minimum net gain by off-site compensation, which many regard as
greenwashing. The Council ecologist stated that the scheme should have
been viewed against the NPPF in the report. This would cause three setts of badgers to be lost and many more compromised.
- Simon Collings was representing the Oxford Flood Alliance, a
resident of Osney Island since 2000 and speaking
in favour of the application. He had had direct experience of flooding and
it was a horrible experience. Mr Collings had been working closely with
the EA and had created the Oxford Flood Alliance. He had seen the scheme
be developed, adapted, modified in light of all the challenges and
comments from the public from consultations. The EA had set out, during
the CPO inquiry, their reasons for rejecting the points raised by speakers
earlier rejecting the application. He urged the Committee to support the
application.
- Nigel Chapman representing Oxford City Council and portfolio owner
for Citizens Focus Services which included flooding and the responses and
management of flooding. Oxford City Council were a partner of the Oxford
Flood Alleviation Scheme and strongly supported the implementation. The
Council was the largest contributor of the scheme and working actively
with the EA for the last five years. Oxford had a history of flooding and
causing damage to homes and businesses. The floods were increasing and
needed to be managed. The number of properties getting flooded would
increase if the scheme was not implemented. A flood alleviation scheme was
urgently required to protect not only current but future communities. The
scheme would reduce floods in the city and would direct the water to the
existing flood plain. It was estimated that the scheme would save £1.4m in
its lifetime by reducing flood damage and impact on the area. The scheme
would have environmental benefits, prevent the production of carbon
emissions in the long-term, create a new wet land corridor to the west of
Oxford, providing an opportunity for enhanced habitat connectivity. Oxford
City Council believed that the scheme presented was the best scheme for
Oxford, managing the floods in Oxford for the next 100 years.
- Liz Sawyer is a resident with two small children who used the Hinksey Meadow regularly with the family. Flooding had
an enormous environmental cost in terms of repair, replacement and
disruption. This was the last generation to enjoy a high carbon lifestyle
without suffering its negative consequences. The EA knew that there was a
responsibility to adapt now and had spent 10 years iterating the design
before all, and only submitting a scheme that would work.
- Annie Blows, a resident with first hand
experience of regular flooding with sewage caused by overflowing of the
Oxford sewer system due to flood water. The sewage overflowed and damaged
her garden, utility room, children’s playroom and other areas of their
home causing potential health risks. There was never any assistance from
Thames Water and the clean-up was insufficient leaving soiled tissues and
faeces to disintegrate naturally. She stated that no home in 2024 should
have to suffer this.
- Andrew Down, Officer at Vale of White
Horse District Council, Deputy Chief Executive for Partnerships and
working with the EA and other partners on the scheme since 2014. The
District Council supported the application, which would reduce the flood
risk for over 1000 homes and businesses in both Oxford city and the Vale.
When roads closed due to the flooding, the impact on transport and the
local economy was severe. Whilst he supported the application, a number of
requests had been made. The Planning Officer was satisfied that all had
been or would be addressed. The EA had listened to the views of residents
and had proposed the scheme as it was presented.
- Pete Sudbury was speaking in his capacity as Cabinet Member for
Climate, Environment, and Future Generations and Chairman of the OFAS
Sponsoring Group. He also sat on the regional and coastal committee. The
programme had been excellently led and had been thorough and well managed.
- Robin Neatherway was speaking as a resident since 2000. The water
had been getting higher each year, and along with it came sewage and
soiled paper. This was not even cleaned by Thames Water. We had been
reassured by the discussions of the flood alleviation scheme and hoped
that four years on, this would now be approved and would be able to move
on. With the shortage of homes in Oxford, it was not great that there were
areas of Oxfordshire that were so badly flooded.
- Anthony O'Rourke had been a resident since 2003. He said that the
flooding was getting bad. Emails and alerts from the EA caused dread for
the preparation to move furniture and belongings. The stress, mould, damp,
and smell lasted years. The garden floods annually and gets worse each
year. A signed letter was sent to the Leader of the Council to approve the
application.
- Bethia Thomas was speaking as Leader of Vale of White Horse
District Council and partner of OFAS. The District Council was in support
of the scheme. The floods affected many residents of Abingdon, disrupting
life, work, and education. She advised that OFAS offered advanced flood
alleviation and protection for almost 1000 homes and businesses in Botley,
South Hinksey and the Vale, and it would prevent
disruption and would create over 20 hectares of new wetland helping to
reverse the national decline of wetland habitats. By working with the EA,
there would be the opportunity to influence the design and construction of
the scheme.
- Anna Railton, Deputy Leader for Oxford City Council but speaking as
the Ward Member of Hinksey Park, South Oxford
and speaking in favour for the scheme. South Oxford had suffered regular
ground water flooding along with the heartache, disruption, stress and
clean-up. Climate change would cause warmer and wetter conditions and
therefore more misery due to flooding. OFAS would alleviate the flooding
problems in South Oxford.
- John Mastroddi, resident since 1980 and researcher of the effects
of flooding in the Redbridge area. Research had shown that planning
projects in the area had made flooding events worse since 1947. The
upgrading of the A34 from two of the four lanes had narrowed the flood
channel considerably. All low-lying land around Redbridge had been filled
with household waste. The old Abingdon Road had been raised, the A43
bridge had been constructed with no consideration to the flood channel and
a concrete wall had been built across the Hinksey
drain preventing flood water from flowing underneath the railway bridge.
All projects now prevented the flow of flood water through the western
corridor.
- David Radford, speaking as a resident of 30 years. Every five
years, his garden would disappear in floods. This year, it has already
flooded twice. Much damage was caused by the floods. The pumping mechanism
discussed would not solve the problem.
- Susanna Pressel, County and City Councillor and representing the
Botley Road area, today and for over 28 years. Councillor Pressel was
speaking on behalf of hundreds of people in the Botley Road area. This was
an excellent report, and the officers were recommending the application.
The application had been supported by many. It was vital for the local and
the UK economy. There were 58 conditions to reduce the negative impacts
from the scheme.
- Claire Wilson, resident of South Hinksey,
speaking in support of the scheme but had concerns about the traffic,
construction, and time frames. Claire had been flooded six times, and on
one occasion, she had to leave home in a foot of water for her wedding in
France and abandoned the honeymoon to come back home and clean up the
mess. Since then, the house had been made flood resistant but the
maintenance of all the measures were getting costly and timely. There was
a resident scheme in place where everyone took turns every two hours to
monitor the pumps, causing disruption to sleep. A permanent solution was
needed for flooding problems. Many residents wanted the scheme.
- Matthew Frohn was speaking as a resident of South Hinksey. The OFAS is over a decade of capital analysis
and design by multiple agencies, national bodies with the knowledge and
expertise in flood and river management, as well as local bodies with
responsibility for community and environmental sensitivities. The scheme
would be noisy, disruptive, and annoying, but would be temporary and
inconsequential when measured against the glowing benefits to the city,
businesses, home, and communities.
- Councillor Gawrysiak asked what the views were on the environmental
aspect of implementing the scheme as a resident. Matthew Frohn responded
that he had been particularly impressed by a presentation given to South Hinksey residents about four years ago about how the
scheme would generate the flow, provide a far better flow, and how the
wetlands would develop. A lot of care had gone into the scheme.
- Adrian Porter, resident of South Hinksey,
flooded very badly, which still causes trauma. Adrian worked very hard as
a flood warden. Flooding caused anxiety and physical disruption on an
annual basis. He was very much in support of the scheme and the
environmental benefits.
Veronica James, applicant, Environment Agency, Planning Manager for the
Oxford Flood Alleviation Scheme (OFAS). The scheme would reduce the risk
of flooding for all properties at risk from the river flooding in Oxford.
The need for the scheme had been explained clearly and convincingly by
previous speakers. The local residents that had spoken, some of whom had
suffered the trauma of flooding in the past. The floods were not new to
Oxford and closed down the transport links, causing issues for homes and
businesses. With climate change, floods were predicted to be more frequent
and more severe. As an organisation, there was a responsibility for
managing the risks from flooding from the main rivers, and to do this,
projects, such as this are delivered. The scheme proposed in this planning
application were the best solution to managing the flood risk, to reduce
flood risk to Oxford, to reduce the flood risk to homes, businesses, to
the main transport links and to local infrastructure. Alternatives had
been considered during the options appraisal process approach. A process
that had to be completed to get approval from the organisation and
government in order to proceed. Only technically feasible options were
considered. At each stage of the projects design, the proposal had been
revisited to ensure the best options for this location. Evidence had been
provided to support this with the planning application and the hydraulic
modelling had been peer reviewed prior to submission. All local government
guidance on climate change had been followed and the evidence had been
reviewed by the statutory consultees for flooding during the formal
consultation process with no objections raised. The environment had been
at the forefront of the design. The principle aim under the Environment
Act 1995 was to protect or enhance the environment, to make a contribution
towards sustainable development and there was a duty under the same Act
generally to promote the conservation and enhancement of the water courses
and the land, fauna and flora associated with them. The EA would like to
be proud of the scheme and for it to be a success, not only for reducing
flood risk but also for the environment. The scheme worked well with the
flood plain to the west of Oxford. The water would be drawn away from the built-up
areas by creating a new stream and lowering parts of the floodplain to
make more space for the water, whilst also bringing environmental benefit
to the area. The same amounts of water brought to the north of Botley Road
would re-enter the Thames where it would rejoin in Kennington. This was
very important as it ensured that flood risk would not increase
downstream. The design was a passive one, with waste entering the wetland
as levels rose and in major floods, water would still use the existing flood
plain. This flood plain was within the Green Belt; therefore the scheme
was located within the Green Belt. A very thorough analysis had been set
out by the case officer for this. It concluded that very special
circumstances existed so the application could be approved. The
considerations for Hinksey Meadow had been
detailed and thorough and modifications made where possible. The tree
planting proposals would increase the woodlands in the areas after
completion. The scheme would be maintained, and public access carefully
considered and made better. With respect to traffic, the EA had worked
with National Highways and their advice had been taken on board and the
scheme modified. Consultation had taken place with the local planning
authority, parish councils, consultees and the scheme was a result of all
the comments made.
The following
questions were asked to the applicant and their technical officers and officers
of the planning authority:
- Were the soil characteristics of the proposed grassland area the
same as or similar to the soil taken? The applicants technical officer
informed the Committee that the soils were very similar.
- How long was the Electric Road to be closed for? Officers advised
that it was not due to close at all.
- Would the piling in North Hinksey near
the school affect the school as they were informed that the school would
not be affected. One of the conditions was about the noise and to limit it
and that would include the school.
- The Network Rail agreement was discussed but this only related to
the compulsory purchase order.
- There would be no substantial harm to the heritage assets. The
scheme would work around the monuments. The impact would only be around
the setting and not to the monuments.
- How much confidence was there that the channel would not increase
the downflow stream? The EA team reported that water would move away from
residential areas, at the same speed and the same distance, through the
flood scheme.
- Why was the no channel model discounted and how had the project
been sequenced? It was reported that there was no prioritisation from one
end to the other. The no channel option had not been progressed as the
course around Oxford was very flat and complex and with that option, there
was no way of knowing where the water was going so it could not be
monitored.
- A new meadow was to be established; how long would this take? It
was a good position as a meadow was already present. The process to
improve the quality was going to be by using green hay spreading, it would
take 5-10 years to achieve a high-quality meadow.
- Why was the biodiversity being carried out offsite? The EA Officers
explained that the vision to lower the land and recreate high quality
habitat on the land had been agreed by all of the conservation groups in
Oxford. They all agreed that by doing it this way, it would be far better
than it was now. Detail was given on the matrix and how it worked.
- What was the vision for the end of the scheme for the meadow, a
pristine landscape or a meadow as it is now? The plan was for a
semi-natural, low intensity management flood plain habitat, all managed
with nature principles in mind.
- How many lorries would there be every day? There would be 111
lorries using different accesses per day.
- A lot of residents had talked about sewage in the homes, is the
scheme going to prevent this after it is implemented? Thames Water was
part of the partnership. The scheme would reduce sewer flood risk.
- Speakers had mentioned the benefits of the pumping system so why
was it not used? The scheme used was a passive scheme with minimal risks
of it going wrong. A mechanical system such as a pump could go wrong and
stop working. The scheme has been kept as simple as possible.
- Was there an impact statement for the traffic around Botley Road? A
construction management plan would be in place covering the distribution
of lorries and HGV management.
- The scheme is said to take 3-5 years, will there be 111 lorries
every day across the full term and would it be in the same direction or
both ways? The 111 lorries would be spread across all different accesses
and during peak construction, mainly through Parker Road with the majority
going north and some south. No earth works would take place over the
winter months because of the flood plain and floods.
- The recommendation read that there was a 30-year habitat management
plan, what were the views to change this to 100 years? The 30 years had
been stipulated and related to the biodiversity net gain plan and was
mandatory. EA would manage the landscape. The OCC Planning Officer
clarified that the application was not subject to the Biodiversity Net
Gain Regulations as this application was not subject to the mandatory
requirement for 30 years habitat management, but they were committing to
do so anyway.
- What would the temporary re-routing of the Old Abingdon Road look
like? This would be a temporary carriageway, a loop below Abingdon Road.
This would be one-way and then the other and then reinstated to woodland
after taken away.
- Had the new bridge been factored in when considering the impact of
traffic in Botley? And will residents be adequately informed of processes?
The earth works would take place in the summer months only and other works
during the winter months too. The EA were aware of all other works as they
were directly linked with infrastructure companies. A Community Liaison
Officer would be the first point of contact for residents. Engagement with
residents was part of the construction management plan and it was conditioned.
Engagement would be through various methods.
- Was 30 years adequate for the habitat management plan? It was
explained that 30 years was adequate to implement? the management plan,
the monitoring would feed back into the plan. It was not just about the
timeframe; the principle was more important.
- Could the condition during peak times in the construction traffic
plan be altered and widened, two hours in the morning and two hours in the
afternoon seemed too less and did not encompass the actual traffic times.
The traffic management plan was a live document and was regularly
monitored and could be changed, in discussion and within reason and if
required.
- If the application was to be approved, the recommendation read
subject to being referred to the SoS, will that happen? How long would
that delay the work? And what weight would the Committee’s decision carry?
The advice of the officers was to refer to SoS to see if they wanted to
call it in, if it was approved. They may not want to call it in. a
decision would possibly come withing 4-6 weeks.
- Was it possible to add a condition that the Planning and Regulation
Committee see the landscaping plan including trees and habitats? It was
perfectly normal for the Planning and Regulation Committee to make this
request, stating which conditions they wished to be referred back to them
for approval when applications were made to discharge them.
- The word ‘same’ before standards was missing in condition 30 in
Annex 1. Could this be added? This would be amended.
ACTION: Amend
condition as above
Councillor
Gawrysiak proposed to APPROVE the Officers’ recommendation in the addenda with
the conditions stated and the addition for the Planning and Regulation
Committee to see the landscaping scheme, the tree planting details and the
construction traffic management plan, all at a future meeting. This was
seconded by Councillor Saul.
A named vote was
carried out. Councillors Bennett, Edosomwan, Elphinstone, Fenton, Gawrysiak,
Johnston, Saul and Snowden voted for the motion. Councillor Roberts abstained
from voting.
RESOLVED: that the planning application for the
Oxfordshire Flood Alleviation Scheme be APPROVED with the additional
three requests from the Planning and Regulation Committee.