Application to modify or discharge Section 106 Planning Obligations to
remove the existing waste catchment area and amend permissive path at Sutton
Courtenay Landfill Site.
Report by Director for Planning, Environment and Climate Change.
It is RECOMMENDED that
i)
Oxfordshire
County Council enter into a deed of variation to amend
the existing Section 106 legal agreement with regards to removing the
hinterland restriction and amending the date for the provision of a permissive
path.
ii)
The
Director of Planning, Environment and Climate Change is authorised to enter
into negotiations with the applicant and any other parties to the legal
agreement with regard to making the variations set out
in this report.
Minutes:
Mary Hudson, Principal
Planning Officer, advised in her introduction that the landfill site had been
operating since the 1970s and as a result
of an existing planning permission granted in 2015
was permitted to continue operating until 2030.
The application proposed two changes to the S106 legal agreement and no
changes to the conditions or the routing agreement that HGVs would take. The proposed changes to the S106 legal
agreement were firstly, to remove the restriction on the source of waste permitted
to be imported to the landfill site.
Currently, the S106 agreement restricted the source of waste to
Oxfordshire, Reading, Bracknell, Wokingham and West
Berkshire. The second proposed change
was to amend the date for the provision of the north-south permissive path that
the S106 Agreement required as part of the restoration. The Agreement stated that the relevant paths
should be provided by 30 September 2023.
However, it could not be provided within that timescale due to active
developments which had consent to 2030, within that part of the site.
Ms Hudson
added that the Monitoring Team had identified that waste was already being
imported in significant quantities to the landfill site from outside the
approved Hinterland area. The current
application was therefore retrospective.
The recommended changes were due to the applicant being unlikely to be
able to complete the landfilling in accordance with the approved restoration by
2030 as required by the conditions without bringing in waste from other areas. Ms Hudson stated that it was recognised that
the patterns of movement of waste to landfill had changed since the agreement
had been signed in 2008. The Hinterland
area was no longer seen to serve a useful purpose and was not supported by
planning policy. It was also the case
that the permissive path could not be implemented until the active developments
on that part of the site had concluded. In the event that the two proposed changes were approved by
the Committee, the Council would enter into a deed of variation to the existing
S106 Agreement.
The
following points of clarification were provided in response to questions and
matters raised by the Committee:
· There had been no request by the applicant to change the annual import
of waste being 600,000 tonnes with no more than 350,000 tonnes being imported
by road. The Hinterland agreement only
related to waste that was being imported via road. It was noted that the number of road
movements at the site would be the same.
The change would be in terms of where the vehicles were coming
from. The point was discussed that the
original agreement sought to minimise carbon emissions and with vehicles coming
from further afield they were likely to generate more carbon emissions. There had originally been concern expressed
by the Committee in relation to the original agreement regarding the
transportation of waste by road. In
theory there was the possibility of all the permitted tonnage being brought in
by rail but this was unlikely, depending on contracts.
· HIF 1 had not yet been considered as a planning application and it was
recommended to Committee Members not to attach too much weight to it in
deliberations on the current application.
· Mr Periam stated that in recommending the removal of the restriction on
the source of waste permitted to be imported to the landfill site in order to complete the landfilling by 2030, there had been
regard to policies in the Council’s Minerals and Waste Local Plan which
encouraged timely restoration of landfill sites.
Councillor O’Broin,
representing Appleford Parish Council, stated that the Council had good
relations with the applicant and acknowledged that the site was confidently
managed. However, there were concerns
regarding noise, dust and air quality from commercial operations and the impact
of traffic, particularly heavy commercial vehicles, in the vicinity of
Appleford village. The Parish Council
was opposing the extension of the Hinterland agreement. He referred to paragraph 56 of the report
that the Environment Agency Waste Data giving a total of approximately 713,000
tonnes of waste being imported to the landfill site, which was above the
permitted annual import figure and therefore was a planning breach. 80% of the waste was coming from outside the
permitted Hinterland area which Cllr O’Broin commented was a material and not
an inconsequential breach. Overall, he
believed the applicant had demonstrated a casual disregard for the S106
Agreement and that they should be required to advise the Council of any non-compliance.
Councillor O’Broin
expressed concerns regarding the proposed amendment of the permissive path and
the delays caused by the cement plant occupying the land. He also expressed the view that the applicant
needed to consult the local community and that local authorities such as
Appleford Parish Council and Sutton Courtenay Parish Council were consulted on
the terms of any agreement or were parties to any agreement. He considered that the application lacked
detail on traffic volumes, expected tonnage or remaining capacity at the
site. He added that approving the
application would be to approve historical non-compliance. Failure to meet the 2030 deadline on the part
of the applicant should not result in automatic extension and could be used for
other purposes. Councillor O’Broin
requested that the application was refused, pending submission of meaningful
traffic information and projected waste tonnage from the applicant.
The Committee also heard
from Mr Draper, representing himself and Sutton Courtenay Parish Council. He requested that the Committee refused the
application, taking into account the breach of the
legal agreement. He referred to the
Council having identified the breach and commented that the retrospective
application lacked transparency and should not be approved. He concurred with Councillor O’Broin’s point that there was a lack of detail in the
applicant’s application. Mr Draper also
expressed concerns regarding the planning breaches of 568,000 tonnes of waste
in 2021 being imported from outside the Hinterland area and the overall total
being 713,000 tonnes of waste. It was
unlikely on this basis that the applicant would have kept to the limit of
350,000 tonnes being imported by road.
Mr Draper recommended
that the application was deferred, with full historic details provided of the
waste movement and a plan stipulated by the applicant as to how the restoration
of the site was to be completed by 2030 and the site returned to agricultural
use. Maintenance should be provided by
the applicant for the footpath for the benefit of the local community.
Councillor
Constance formally proposed that the application was deferred. This was in order to
obtain details on the level of the applicant’s compliance or non-compliance
since 2021 (when the previous Environment Agency’s Waste Data was available)
and what the impact would be on the restoration of the site, if the application
was not approved by the Committee. It
was noted that a number of authorities were sending
waste to the landfill site and that it would be useful to look at whether it
was necessary for the waste to travel from further away or whether they should
be treating it. Councillor Bennett
requested that policy work was undertaken to ascertain what the proportion of
waste that needed to be landfilled was and if there was waste that could be
treated without being landfilled and also comparing
the percentage of waste that the local authorities sent elsewhere with that
sent to Sutton Courtenay Landfill Site.
The applicant would again be invited to attend the meeting to answer
questions.
The
proposal was seconded by Councillor Fadlalla.
Councillor Howson spoke in support
of refusing the application as he was persuaded by the representations of the
two Parish Councils at the meeting and what he perceived to be the flagrant
nature of the planning breaches in terms of the tonnage being imported and the
apparent length of time this had been taking place. It was noted that it was not possible to
require the applicant to change their application and that they had the ability
to appeal against the decision should the application be refused
and the matter considered by the Planning Inspectorate.
It was noted by the Committee that
it was not possible for the Council to require the applicant to have
discussions with the parish councils.
Members did have the option to ask officers to pass on their concerns to
the applicant that they ought to seek to improve the nature of the engagement
and more promptly with the parish councils.
The
Chair called for a vote on the recommendation to defer the application. The votes cast were, as follows:
For:
9
Against:
1 (Councillor Howson voted against as he wished to refuse the application).
Abstentions:
0
RESOLVED:
that the application be DEFERRED for the reasons set out above.
Supporting documents: