Report by the Director of Finance.
The report
provides an update on the Internal Audit Service, including resources,
completed and planned audits.
The Committee is
RECOMMENDED to note the progress with the 2022/23 Internal Audit Plan and the
outcome of the completed audits.
Minutes:
Sarah Cox, Chief Internal Auditor, presented the quarterly
progress report. She stated that
recruiting to fill the Senior Auditor post was still ongoing and agencies were
continuing to be consulted on providing appropriate candidates. To assist with Q4 in 2022, one of the
Council’s ex-principal auditors had been recruited on a casual basis. The Senior Auditor vacancy was having some
impact on progress with the Internal Audit Plan. There had been three additions to the Plan
since the last update and five audits that had been removed or deferred until
the 2023/2024 Plan. This had happened
largely because they needed to be delayed due to work currently ongoing within
the services. There was sufficient
assurance across all the key risk areas and across the directorates in order
that it was possible to provide the Annual Opinion.
Ms Cox added that many of the audits which had been
undertaken from September to December were at draft stage or near to
finalisation and the bulk of the work had been completed. There had also been a commitment to reduce
the residual management actions which had been open for some time. There was now an 80% implementation rate and
10% of the actions were not yet due. This
high rate was a reflection of the work of the team and
support from the Senior Leadership Team.
In response to questions, Ms Cox made the following points:
·
A risk relating to security alerts had been
identified in the report as they were only received by one member of the IT
team and, in their absence, this could lead to alerts not being received and
acted upon on a timely basis. The
Committee were informed that IT had agreed to implement the required action in
response to the risk being identified.
The overall opinion of the IT Virtual Infrastructure audit had been
rated ‘green’. There were therefore not
significant concerns as it was a well managed area.
·
Work had been undertaken to provide some
assurance that there had been improvement from a position that there had
previously been contract spend without the formalised contracts in place. Some improvement had been found, including that where contracts in the
sample had been found not to be in place, this had already been identified by
the service area with work underway with the Hub to formalise contract
arrangements. The procurement hub and
the team were working with services to identify residual arrangements where
contracts are needed. The issues were
generally related to lower level contracts rather than
the major ones. Improvement was required
in relation to the contract management system.
The policies, procedures and guidance were found to be acceptable. There was training in place
and this was being targeted for the appropriate level of contract managers.
·
It was expected that there would be some
resource to cover the Senior Auditor vacancy and that it would be sufficient to
provide the Annual Opinion. Some of the
work going forward could be covered by casual staff or via an agency but this
recruitment was cost dependent.
RESOLVED: That the Committee
NOTED the progress with the
2022/23 Internal Audit Plan and the outcome of the completed audits.
Supporting documents: