That applications MW.0057/21 and MW.0058/21 be refused.
Minutes:
The Committee considered a report by the
Assistant Director for Strategic Infrastructure and Planning recommending that
the following applications be refused –
i.
MW.0057/21:
importation of inert material for use in restoration of the site; and
ii.
MW.0058/21:
Section 73 application to continue the development of limestone quarry
extension permitted by 18/02008/CM (MW.0027/18) without complying with
condition 1, condition 2, condition 8 and condition 26 in
order to amend the approved restoration scheme, extend the end date for
restoration and allow the importation of inert material.
Matthew Case, Senior Planning Officer,
Strategic Infrastructure and Planning, presented the report that was before the
Committee.
Representations
on Behalf of the Applicant
Mr Antony Cook of David Jarvis Associates
Ltd gave a presentation in support of the applications.
In response to questions by Members of the
Committee, Mr Cook provided the following information.
(a)
Regarding
the amount of construction waste generated within the Areas of Outstanding
Natural Beauty (AONB) vis-à-vis what would be imported from outside, Mr Cook
stated that the volume [of inert waste] proposed was 118,000 m3.
However, he had no further information on the volume of waste being generated.
(b)
Referring
to the consented scheme, Mr Cook stated that the quarry had been overworked and
there wasn’t sufficient material on the site for restoration purposes, and
there was no consent to import material to the site.
[Mr
Periam confirmed that the current consent did not provide for the importation
of any material].
(c)
Concerning
the number of lorry movements, Mr Cook stated that 58 lorry movements per day
were permitted during the operation of the quarry and the same number of lorry
movements were being sought for the proposed additional 18 months working.
(d)
Mr
Cook stated that, for the purposes of the restoration, the application was for
a three-year extension comprising 18 months of importation of materials and 18
months completing the restoration work.
(e)
In
response to a question by the Chair, Mr Cook stated that Earthline
Exchange Ltd [the potential infilling operator] had subsequently confirmed
that, if they were to be carry out work at the site, they would operate within
a much closer radius of the site as it was not cost-effective to haul inert
materials long distances, particularly given increasing fuel costs.
The
applicant stated that if the infilling operator had Castle Barn Quarry within
their portfolio, they would focus on developments within Chipping Norton, Stow
on the Wold, and nearby towns to ensure they could
generate the material within a locally sourced area and were not hauling
materials great distances.
(f)
Regarding
the biodiversity net gain and who would create, manage, and monitor the scheme,
and how this would be assured if the scheme was approved, Mr Cook stated there
was an expectation there would be a Planning Condition requiring a detailed
restoration and after-care scheme which would set out a five- or 10-year
monitoring period. In addition, it was proposed that there would be annual
monitoring of the scheme, in conjunction with the local authority, to ensure
that the scheme was carried out and had become self-sustaining by the end of
the monitoring period.
(g)
In
response to a question about the quarry having been overworked, and the
application possibly being refused, Mr Cook stated that, if the restoration was
to be carried out, it would be necessary to submit a further Planning
application.
(h)
Mr
Cook confirmed that it would not be possible to restore the site without
bringing material on to the site. He stated there was an option to bring 50,000
m3 on to the site which would achieve a satisfactory restoration
outlined in the consented restoration scheme.
As there were no more questions for Mr Cook,
the Chair stated that the decision for the Committee was whether the applications
constituted major development in an AONB. If the Committee deemed the
applications to be major development, they should be refused, unless there were
exceptional circumstances, and the development could be demonstrated to be in
the public interest.
In the subsequent discussion, the following
points were raised.
(a)
In
response to a question about the dangers of leaving a large void in the area,
Mr Periam noted that this was a closed quarry and that Health and Safety
matters where the remit of other agencies. Mr Case confirmed that both
restoration schemes included areas of geological interest which consisted of
exposed quarry face.
(b)
In
response to several questions by Members of the Committee, Haidrun Breith, Landscape Specialist, Strategic Infrastructure and
Planning, provided the following information –
i.
For
the reasons set out in the report (see Paragraphs 27 et seq), Ms Breith stated that she remained of the view that
the benefits of the proposed restoration did not justify the impacts associated
with the proposed level of infilling. Therefore, on balance, she did not
support the application.
ii.
Regarding biodiversity, Ms Breith stated there was merit in the present
application but, when compared with the consented restoration scheme which did
not involve HGV lorry movements, the consented scheme was to be preferred when
considering issues of tranquillity.
iii.
That
it was possible to have a scheme which provided similar biodiversity gains
without the requirement to infill site in the manner proposed by the present
application. That is, the biodiversity net gain was not dependent upon the
amount of infill but on the nature of the restoration scheme.
iv.
If
the Committee were to decide that the application did not fall within the
category of major development, it still had to conform with other policies that
would influence the decision-making process, such as those relating to the
importation, purpose, and suitability of fill materials.
v.
In
terms of biodiversity habitats, the proposed scheme was to be preferred to the
consented scheme. However, landscaping and levels of infill could vary and, if
infilled to the level before the quarrying operation, it would be possible to restore
the agricultural fields. However, it would not be out of character to have a
dip in the landscape and there were many former quarries that were rich in
terms of biodiversity.
Referring
to the Plans that were before the Committee, Ms
Breith noted that no habitat was shown on the consented scheme, but the site
was not as bare as it appeared on the Plan.
(c)
The
previous operator would have known that the quarry was being overworked and
that this may not have been apparent from monitoring the operation.
(d)
Under
the consented scheme, it would take the operator nine months to import the
materials necessary to restore the quarry. As the restoration being proposed
went beyond the original scheme, it was considered reasonable to allow the
operator 18 months in which to import the materials necessary for the revised
scheme.
(e)
In
response to a question as to why officers viewed the proposals as constituting
a major development, Members were informed that this was the first time there
had been an application to import infill materials to the site. In accordance
with the requirement that each application be considered on its merits, it was
necessary to consider the application in accordance with the relevant AONB
policies. In so doing, officers were of the view that importing 118,000 m3
material requiring 28,000 HGV movements over the specified period constituted
major development.
The
quarry should have been restored using on-site material and this work should
have already been completed. Therefore, the current position was that there was
no permission for the HGV movements required to import the amount of material
proposed in the application. However, deciding whether this constituted a major
development was a matter for the Committee to determine.
(f)
Regarding
Core Strategy Policy W6: Landfill and other permanent deposit of waste to land,
there was a requirement that there be an environmental benefit which had to be
considered within the context of the number of HGV movements required to import
the material.
(g)
Referring
to Paragraph 61 on page 24 of the agenda pack, officers confirmed that the HGV
movements would be within the AONB.
(h)
It
was confirmed that Oxfordshire County Council was responsible for monitoring
the quarry operations.
(i)
Presently,
there was no permission to import materials as the restoration of the quarry
was to have been carried out using materials that were on site. If there had
been an application to import materials necessary to restore the quarry in
accordance with the consented scheme, it is possible that officers may have
recommended approval of such an application. The application before the
Committee was to import twice the amount of material required to restore the
quarry. Therefore, the present application went beyond what was required to
restore the quarry in accordance with the consented scheme.
[Mr
Periam advised the Committee of the various matters it should take into
consideration when determining whether the present application constituted
major development].
(j)
Regarding
imposing conditions that would address the concerns of the Landscape Officer
and any concerns of Committee Members, officers proposed that the current
application went beyond the requirements of the consented scheme. Should the
Committee decide to refuse the application, it was open to Members of the
Committee to instruct officers to liaise with the applicant, without prejudging
the matter, on what might be required if the applicant was to submit a revised
application.
At
this stage in the proceedings, Councillor Stefan Gawrysiak moved
the following motion.
Motion
That the Committee approve the application
for the following reasons –
i.
Following
discussion, it was the Committee’s view that the application did not constitute
“major development”;
ii.
The
additional HGV movements required to import material did not vary significantly
from the number of HGV movements when the quarry was in operation; and
iii.
The
proposals included a gain in terms of biodiversity and landscaping.
The motion was seconded by Councillor Bloomfield.
In the subsequent debate regarding the
motion during which officers, including the Legal officer, advised the
Committee Members, a document comprising a proposed list of Planning
Conditions, an Informative, and a Statement of Legal
Requirements, was circulated by officers in anticipation of the Committee
approving the application.
At the conclusion of the debate, the mover
of the motion, Councillor Gawrysiak, amended the motion, to include
the proposed Planning Conditions, subject to the conditions being suitably
renumbered, the Informative, and a Section 106 Agreement, including there being
no geographical restriction on the routeing of the waste, circulated by officers. Councillor Bloomfield seconded the motion, as
amended.
The votes cast were, as follows:
For: 10
Against: 1
Abstentions: 1
RESOLVED:
1.
To
approve Planning Permission for application numbers:
i.
MW.0057/21:
importation of inert material for use in restoration of the site; and
ii.
MW.0058/21:
Section 73 application to continue the development of limestone quarry
extension permitted by 18/02008/CM (MW.0027/18) without complying with
condition 1, condition 2, condition 8 and condition 26 in
order to amend the approved restoration scheme, extend the end date for
restoration and allow the importation of inert material.
2.
Subject
to the inclusion of the suitably amended list of the Planning Conditions,
Informative, and a Section 106 Agreement, as circulated by officers at the
meeting.
Supporting documents: