Report by the Assistant Director Strategic Infrastructure and Planning (PN7).
The report sets out the two proposed developments for which planning permission has been applied under application nos. MW.0057/21 and MW.0058/21. Having considered the report against the development plan and other material considerations including consultation responses and representations received it is recommended the two applications are refused.
It is RECOMMENDED that planning permission for
application MW.0057/21 be refused for the following reasons:
i)
The
development is Major Development in the Cotswolds Area of Outstanding Natural
Beauty for which exceptional circumstances do not exist and for which it has
not been demonstrated
that the development is in the public interest. Therefore, the development is contrary to paragraph 177 of the
National Planning Policy Framework, policy C8 of the Oxfordshire Minerals and
Waste Local Plan: Part 1 Core Strategy, policies EH1 & EH2 of the West
Oxfordshire Local Plan and policies CE1, CE4, CE10, CE11, CE12 & CE13 of
the Cotswolds AONB Management Plan 2018.
ii)
The
development is not necessary in order to achieve the
satisfactory restoration and afteruse of the existing
quarry in a timely manner contrary to Oxfordshire Minerals and Waste Local
Plan: Part 1 Core Strategy policies W6 and M10.
iii)
The
development would not minimise carbon emissions nor make effective use of
natural resources contrary to policy C2 of the Oxfordshire Minerals and Waste
Local Plan: Part 1 Core Strategy and policy OS3 of the West Oxfordshire Local
Plan.
It is RECOMMENDED that planning permission for application
MW.0058/21 be refused for the following reasons:
i)
In
combination with the importation of inert material proposed in application no. MW.0057/21
which the proposed variations to the existing planning permission18/02008/CM
(MW.0027/18)would facilitate, the development is Major
Development in the Cotswolds Area of Outstanding Natural Beauty for which
exceptional circumstances do not exist and for which it has not been demonstrated that the development is in
the public interest. Therefore the development is contrary to paragraph 177 of
the National Planning Policy Framework, policy C8 of the Oxfordshire Minerals
and Waste Local Plan: Part 1 Core Strategy, policies EH1 & EH2 of the West
Oxfordshire Local Plan and policies CE1, CE4, CE10, CE11, CE12 & CE13 of
the Cotswolds AONB Management Plan 2018.
ii)
In
combination with the importation of inert material proposed in application no.
MW.0057/21 which the proposed variations to the existing planning
permission18/02008/CM (MW.0027/18) would facilitate,
the development is not necessary in order to achieve the satisfactory
restoration and afteruse of the existing quarry in a
timely manner contrary to Oxfordshire Minerals and Waste Local Plan: Part 1
Core Strategy policies W6 and M10.
iii)
In
combination with the importation of inert material proposed in application no.
MW.0057/21 which the proposed variations to the existing planning
permission18/02008/CM (MW.0027/18) would facilitate,
the development would not minimise carbon emissions nor make effective use of
natural resources contrary to policy C2 of the Oxfordshire Minerals and Waste
Local Plan: Part 1 Core Strategy and policy OS3 of the West Oxfordshire Local
Plan.
Minutes:
The Committee considered (PN7) a report setting out two applications in
relation to Castle Barn Quarry. One (MW.0057/21) sought permission for the importation
of inert material for use in restoration of the site and the second
(MW.0058/21) a Section 73 application to vary certain conditions attached to
planning permission MW.0027/18 regarding importation of material and an
extension to the restoration date to 31 December 2024.
Officers presented the report.
Responding to questions officers advised that the statement by the
applicant’s counsel on page 44 of the report had unsurprisingly stated that
this application did not constitute major development and was in the public
interest because of benefits from the proposed scheme and improvements to
safety on the site. However, under the NPPF a view had to be taken on any
application in an AONB and it was for the Committee as decision takers to
decide on whether advice given by officers in this case was correct or not.
There had been a quarry there for many years and the original permission had
been for restoration using on site material but, for whatever reason, more
material had been removed from the site and as a result some imported material
would now be required. However, the level of import being proposed was twice
what was required to infill under the existing scheme.
While giving a higher bio-diversity net gain the new scheme would also
result in more HGVs and carbon emissions so a balance was needed between the
benefits to be derived from any net gains against the disbenefits from 27,00
additional vehicle movements when restoration could be achieved without that.
There was a duty of regard for the management of AONBs.
The Highway Authority had initially raised some concerns but not now, subject
to routeing agreements
Antony Cook for the applicant. Castle Barn Quarry had historically
been worked for building stone but in 2015 that changed to allow surplus waste
mineral to be crushed and exported as aggregate enabling the quarry to be
worked in a more efficient and effective manner while creating a viable product
from finite mineral resources. However,
adequate safeguards had not been established by that permission or those that
followed to ensure retention of sufficient waste material on site for
restoration, which now meant that the approved restoration scheme could not now
be delivered without importing inert material.
While this was an issue that could have been prevented and was a problem
inherited by the applicant (as landowner) who was now responsible for
delivering the restoration of the quarry the scheme as now proposed presented
an opportunity to deliver significant
improvements through development, which sought only continuity of the nature
and scale of the quarry operation that had existed on this site between 2015
and 2020 with a maximum three-year extension to complete restoration works. However, it was anticipated that the infill
operation would be completed within eighteen months with the only discernible
difference between the previous mineral operation and the proposed infilling of
the remaining void being that associated HGVs would import rather than export
material with the number of daily vehicle movements remaining the same. Central
to the officer recommendation was the implied impacts of maintaining HGV
movements in the AONB but recent development history for the application site
included three planning permissions across 2015, 2017 and 2018 each of which
approved 58 daily HGV movements from the quarry and in assessing the impact of
these applications county officers had consistently stated that 58 HGV
movements exporting mineral did not comprise major development in the AONB and
did not result in any adverse impact upon the landscape, including the
Cotswolds AONB. How could that be different from the same number of HGV
movements importing clean, unrecyclable inert material over an 18 month period
and if it was that such adverse impacts existed then there should be compelling
evidence resulting from the previous mineral operation. But that was not the
case. The officer report referred to the
lesser number of movements required to deliver the existing ‘satisfactory’
restoration scheme but policy dictated that quarry restoration schemes must
strive to be more than satisfactory especially within an AONB landscape. The
consented scheme was almost entirely agricultural with limited biodiversity
gains and a retained void resulting in a landform uncharacteristic of the
designated landscape and he doubted whether the scheme if it were to be
determined today would secure planning permission whereas the proposed
development presented an opportunity to reinstate the pre-extraction landform in
this part of the AONB; deliver wide-ranging and significantly enhanced
biodiversity gains that were not achieved by the consented restoration and
remove a large and hazardous void only a matter of metres from a public right
of way all through 18 months of importation at a scale of development
consistent with that which had currently existed at this site, without issue or
detriment, for roughly 6 years and supported by the Parish Council. Extending HGV movements would be central to
any decision making process but as the material proposed to be used to fill the
void already existed in the form of soils and clays from construction sites
which, because of its unsuitability for use as recycled aggregate, would in any
event need to be transported for management purposes. He accepted that there was a consented restoration scheme that could be
delivered within a shorter timeframe but that would still require importation
of inert material while resulting in at best nothing more than a satisfactory
outcome whereas now there was an opportunity to deliver long term landscape,
biodiversity and public safety benefits while representing ‘exceptional
circumstances’ in accordance with national policy to provide justification to
allow these planning applications to be approved.
Responding to questions from Councillors he:
Confirmed that waste would be supplied by a local haulier in North
Oxfordshire.
The operation would use inert waste and be subject to an Environmental
Permit.
The number of HGVs had been deliberately framed to be consistent with existing
limits.
They were aware of surrounding traffic restrictions in settlements such
as Chipping Norton.
As local member Councillor Leffman was well aware of the history of this
site and did not consider this application constituted major development. What
was being proposed would result in a complete infill of the site with a return
to agricultural use and substantial improvements to both biodiversity and
ecology. There had been traffic
movements here for many years comprising tractors and lorries with no
complaints and problems resolved through appropriate routeing to avoid
neighbouring settlements. There had been no ecology objections or objections
from neighbouring communities who accepted that the application would allow a
return to agriculture with other major benefits. She considered that the
application should be approved.
Councillor Constance supported the views put forward by the local
member. Her expectation was that major development would be above ground rather
than filling in below ground level. It seemed clear to her that there was an
ambition here to restore this area to a higher standard, that there were
exceptional circumstances and it was in the public interest with a net gain in
biodiversity.
The Chairman reminded the Committee that the main question was whether
the development was major development in the AONB. While there was the
potential for biodiversity gains and clearly a desire locally to get on with
restoration the question remained about development in the AONB along with
concerns regarding the balance to achieve that against increased carbon
emissions.
Councillor Roberts referred to the concerns of Chipping Norton residents
who were very exercised about pollution and that they might find it difficult
to recognise the benefits to their community. Chipping Norton was also an AQMA
and this seemed to be going against that. She agreed that more information was
needed as this was a very tight balance.
Councillor Rouane advised that environmental officers had not commented
on the AQMA issue he did not see that as
a problem and if it wasn’t classed as a major scheme before then why should it
be now.
Officers advised that Policy C8 and Policy C11 and Appendix 9 of the
Cotswolds AONB Management Plan offered guidance on the issue of major
development and whether the proposal had a material impact on the AONB. The
Cotswolds Management Plan stated that material should address local needs and come
from within the AONB. Given the opportunity could become good biodiverse sites and
there were landscape benefits to the proposed scheme but to do that here would
require traffic movements estimated at around 28,000 HGVs with increased CO2
emissions. This was an infill application and restoration of the quarry did not
have to be completed in this way as there was an alternative approved scheme as
set out in the existing planning permission. The question which needed to be
asked was why this restoration scheme required so much more material than the
original permission. Care was also needed to ensure a precedent was not set for
other schemes.
It was clear from the full discussion that some Members felt that more
information was needed in order to reach a conclusive decision and Councillor
Edosomwan moved that the applications be deferred. Seconding the motion
Councillor Bennett added that the restoration scheme as now proposed seemed an
improvement on the original scheme but agreed that in order to address the
issues raised and reach a satisfactory conclusion more information was required
to support a decision.
The motion was then put to the Committee and:
RESOLVED: (by 7
votes to 3) that Applications MW.0057/21 and MW.0058/21 be deferred to a future
meeting for further information specifically relating to:
·
Biodiversity - to include a comparison
of the approved and proposed schemes but more generally whether the proposed
restoration scheme was exceptionally better than the approved scheme in order
to support the need to demonstrate exceptional circumstances and whether the
public interest test had been met if it was concluded that it was major
development in AONB terms.
·
Landscape – Landscape Assessments to be
provided by applicant for consideration.
·
More detail on the two sites/operators
in the north of Oxfordshire which the applicant’s agent had identified as the
likely sources of the inert material.
·
An assessment of the CO2 emissions
associated with the importation of inert material to the site as proposed.
Supporting documents: