10:35
Accordingly,
George Eleftheriou will present details of
progress against the 2018-19 programme of works as well as details of the
proposed projects for 2019-20. Outlining the main issues/mitigations,
opportunities and way forward. A handout
to accompany the presentation will be circulated prior to the meeting.
The Committee is
asked to receive the presentation.
Minutes:
At a previous meeting, the Committee had
requested to receive a presentation on how the Schools Structural Maintenance
Programme (SSMP) was compiled and the methodology used, including the
information that had been transferred from Carillion and how this information
had been utilised to provide a robust programme of works based upon the most
urgent priority rating.
Accordingly,
George Eleftheriou, Assistant
Director Community Facilities Management had been invited to the Meeting to present
details on the progress against the 2018-19 programme of works, together with
details of the proposed projects for 2019-20. Outlining the main
issues/mitigations, opportunities and way forward.
Mr Eleftheriou explained that the County Council, as part of
its strategic asset management plan, carried out a programme of condition
surveys on all its buildings every 5 years. The County Council considered the
conditions survey data they held, together with intelligence held by local
managers of buildings and its own maintenance teams to prioritise the
expenditure of funding received from central government under the Schools
Structural Maintenance Grant. The last Asset Condition Survey had been
undertaken by Carillion in 2016.
The School Structural Maintenance Programme (SSMP) was primarily
based on the County Councils PUF rating (Performance, User, Fabric) and the
intent was to deal with the highest priority repairs and maintenance needs.
Those needs were considered against:
a) The condition survey data,
b) Existing repairs and maintenance programmes,
c) Basic need programme,
e) Programme and compliance pressures because of the devolution of
DSG funding to maintained schools
The 2018-19 programme of works was identified using the above
criteria following the collapse of the Carillion contract. Unfortunately, limited information was
transferred to the County Council when the Carillion contract ceased, however
the condition data for the majority of maintained schools that was collected
under the Carillion contract was available. This high-level condition data
identified major repair/life cycle replacement items.
This information was used to draft an initial
programme. To ensure that the data used was robust, a programme of inspections
were undertaken by County Council Building Surveyors and Engineers, of the
highest priority items. This inspection detailed the urgency, scope and budget
cost of the works initially identified.
This collected information was then re-assessed
from a PUF rating perspective to identify the most urgent items to be delivered
within the budget allocated.
The 2019-20 programme of works had been
identified and was awaiting approval in April.
Once the programme was ratified
the schools would be contacted to notify them of their inclusion in the
programme and relevant timings.
The agreed programme for 2018-19 consisted of 14
major projects, some of which had been carried forward from the Carillion
contract. Seven operationally critical
projects had been successfully completed by the County Councils project
delivery team.
o
Blewbury School –
Heating pipework and boiler replacement.
o
Bloxham School –
Structural repairs to roof.
o
Crowmarsh Gifford School
- Pitched roof replacement due to structural failure.
o
Fir Tree School –
Pitched roof replacement due to structural failure.
o
St Francis School – Hot
and cold-water pipework replacement.
o
St Swithuns School –
Replacement lintels.
o
Windmill School– Boiler
replacement.
The remaining projects from the 2018/19 programme had been carried over
and scheduled to be delivered within the 2019-20 programme. This rescheduling
of works would have minimal impact on the school’s operation as the projects
were predominantly condition based and re-profiling would not cause any major
inconvenience.
The main issue faced following the Carillion collapse was to
establish stability and at the same time carry on with the set programme of
works minimising any service disruption. This included various resource issues,
permanent delivery model applied and overall long-term strategy. The team had
done a fantastic job carrying on delivering as per the programme under the
circumstances i.e. moving on from an outsourced delivery model to now
re-establishing an in-house long-term delivery team.
This
situation had presented an opportunity for the County Council to re-evaluate
the way services were being delivered, including the current on-going
development of an in-house FM and Construction unit.
In
answer to questions from Members, Mr Eleftheriou
confirmed that he was satisfied that the condition data from Carillion was
reliable and that he was confident that the 2019/20 programme could be
delivered on time.
Following
discussion, the Committee made the following points:
The
Committee expressed the importance of communicating with schools (particularly
those that were not prioritised under the 2018/19 programme but were moved to
the 2019/20 programme) about when their works were to be undertaken so that
they could have a reasonable view of when they could expect works to be carried
out. Feedback from Schools was that
there had been no dialogue from OCC leaving schools frustrated.
The
Committee established that the 7 school projects that had been carried over to
the 2019/20 programme had not been business critical. The more urgent of the 7 (Tier 2) had been
prioritised for this year and were being progressed.
The
Committee welcomed the service coming back in-house and the opportunity this presented
to maintain the schools building to an appropriate standard.
The
Committee expressed the importance of schools understanding what maintenance
fell within their budgets and what fell with OCC budget.
Following debate, the Committee
AGREED to:
(a)
receive the presentation;
(b)
ask officers to provide members with an update in relation to St.
Andrews School Chinnor;
(c)
email members with the report references which point to the
overall cost of the collapse of Carillion to the Council;
(d)
receive a report back on progress in six months’ time.
Supporting documents: