4. Housing Infrastructure Fund (HIF2) – A40 Eynsham to Wolvercote Construction Contract
PDF 337 KB
Cabinet Member: Highway Construction and Repair
Forward Plan Ref: 2026/119
Key Decision
Contact: Yousuf Javed, Senior Project Manager – HIF2 Programme (Yousuf.Javed@oxfordshire.gov.uk)
Report by Director of Environment and Highways (CMDHCR4).
A proposal to approve the Housing Infrastructure Fund (HIF2)
– A40 Eynsham to Wolvercote construction contract.
The Cabinet Member is
RECOMMENDED to:
a) Delegate authority to the Director of
Environment and Highways in consultation with the Head of Legal and Governance
Services (Deputy Monitoring officer) to:
i)
Subject
to finalising the scope, target cost, and programme for Stage 1 as well as the
Option X22 Budget and Pricing Information, to approve the award of the NEC4
Engineering and Construction Contract, for an estimated total value of £70m,
for the A40 Eynsham Park and Ride to Wolvercote scheme to Balfour Beatty Group
Limited under the Scape Civil Engineering and Infrastructure Framework (Lot 2);
and
ii)
Subject
to finalising the scope, target cost and programme for Stage 2, approve the
issuing of a Notice to Proceed under the Contract to commence the main
construction works.