Capital Programme Monitoring Report

Meeting: 22/04/2025 - Cabinet (Item 73)

73 Capital Programme Approvals - April 2025 pdf icon PDF 208 KB

Cabinet Member: Finance

Forward Plan Ref: 2025/011

Contact: Natalie Crawford, Capital Programme Manager

Natalie.crawford@oxfordshire.gov.uk

 

Report by Executive Director of Resources and Section 151 Officer

 

The Cabinet is RECOMMENDED to:

 

a.             approve the addition of a new phase of energy saving measures into the capital programme, at a total cost of £10.360m. The two-year programme will run from 2025-2027 and is to be funded by £10.000m from corporate resources, as approved by Council in February 2025, with the remaining £0.360m to be funded by a successful bid to Phase 4 of the Public Sector Decarbonisation Scheme (PSDS4). 

 

b.             approve the inclusion of phase 2 and 3 of Fire Compartmentation Remedial works into the capital programme, at a cost of £3.700m.  The programme of work is to be funded from £2.000m corporate resources agreed by Council in February 2024 and a further £1.700m agreed by Council in February 2025.

 

 

Decision:

Recommendations approved.

Minutes:

Cabinet had before it which set out change requests requiring Cabinet approval that will be incorporated into the agreed Capital programme and included in the next update to programme in June 2025.  

 

Councillor Dan Levy, Cabinet Member for Finance, presented the report.  He referred to the two schemes detailed in the report relating to energy saving measures funded through corporate resources and a government decarbonisation scheme and fire safety improvements in council buildings, ensuring compliance with safety regulations. Both initiatives reflected the council's commitment to reducing carbon emissions and maintaining safe facilities.

 

RESOLVED to:

 

a)    approve the addition of a new phase of energy saving measures into the capital programme, at a total cost of £10.360m. The two-year programme will run from 2025-2027 and is to be funded by £10.000m from corporate resources, as approved by Council in February 2025, with the remaining £0.360m to be funded by a successful bid to Phase 4 of the Public Sector Decarbonisation Scheme (PSDS4). 

 

b)    approve the inclusion of phase 2 and 3 of Fire Compartmentation Remedial works into the capital programme, at a cost of £3.700m.  The programme of work is to be funded from £2.000m corporate resources agreed by Council in February 2024 and a further £1.700m agreed by Council in February 2025.