A4130 Steventon Lights Integrated Transport Corridor Scheme

Meeting: 16/11/2023 - Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy (Item 4.)

4. A4130 Steventon Lights Integrated Transport Corridor Scheme pdf icon PDF 517 KB

Forward plan Ref: 2023/326

Contact:dan Hammond, Programme Lead - South & Vale Programme,

dan.hammond@oxfordshire.gov.uk

 

Report by Corporate Director Environment & Place

 

The Cabinet Member is RECOMMENDED to 

Delegate authority to the Corporate Director of Environment & Place in consultation with the Director of Finance and the Head of Legal Services & Deputy Monitoring Officer to award and enter into a Stage 1 (detailed design, ECI and target cost setting) contract under the NEC4 PSC Option A and NEC4 ECSC (enabling works/surveys) with Milestone Infrastructure Limited in respect of the A4130 Steventon Lights Integrated Transport Corridor Scheme. 

Decision:

Recommendations approved.