Decision Maker: Director of Property & Assets
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To enter into a contract with a
consultant to provide a multi-disciplinary team to lead the feasibility study,
detailed design, manage the planning application, procure the build contractor,
and act as project manager overseeing delivery of the project from feasibility
through to completion.
Approval
for Oxfordshire County Council to enter into a Contract for the Provision
of Services as principal designer, technical adviser and project manager
relating to a project to design and construct a new modern household recycling
center to the south of Bicester Park & Ride, Oxfordshire.
The
Contract Value is £488,200.66 (excluding VAT)
A decision is required to move onto OCC Stage 1 Feasibility and Design Development, procure a Contractor and to obtain Outline Business Case.
1)
Do
nothing. The lease for Ardley Fields
HWRC expires in Sep 2026 and site is forced to close, reducing the HWRC network
from seven to six locations.
2)
Negotiate
extension to the Lease of Ardley Fields HWRC by 2-3 years as a temporary
measure. The land is not owned by OCC
and medium to long terms, Ardley Fields HWRC must be
relocated to a new replacement site.
3)
A
new site search identified the land south of Bicester Park and Ride to build a
new HWRC to replace Ardley HWRC. This is
the option OCC are proceeding with.
Publication date: 19/03/2026
Date of decision: 04/03/2026