Decision Maker: Director of Environment & Highways
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This
decision achieves the following key outcomes:
-
OCC
will receive the necessary grant funding contribution from OxCity to be able to
pay its chosen supplier (Connected Kerb) to deliver an additional 140 new
GULO-funded chargers within its wider LEVI contract
-
The
Department for Transport grant funded GULO will successfully be completed –
meeting OxCity’s obligations to the funders at the Department of Transport and
providing an additional 140 public EV charging sockets in Oxford
-
The
existing estate of GULO P1 chargers will be operated by Connected Kerb under
the OCC contract and will continue to provide a valuable service for residents
The responsibility for on-street public charging will sit with OCC which is clearer, more appropriate and easier to manage contractually than the prior temporary arrangements
In 2013,
OxCity were granted special permission to be able to install, own and operate
public EV chargers on the public Highway in order to deliver what was at the
time an innovative trial of this type of EV charging technology as part of the
Go Ultra Low Oxford project (GULO).
This was
always intended to be a short-term practical arrangement to enable the
OxCity-led project to go ahead; under normal circumstances OCC would not want
assets to be installed and operated on the highway by third parties with whom
OCC had no direct contractual relationship.
By 2015,
around 51 chargepoint sockets had been delivered under the GULO project part 1
(GULO P1) but by 2022 the delivery of remainder of the scheme (GULO P2) had not
been completed by OxCity. Around the
same time in 2022 the Department for Transport announced that OCC – as Highways
Authority and strategic transport lead for Oxfordshire - would be receiving
Local EV Infrastructure (LEVI) grant funding and be expected to lead on the
strategic planning and practical delivery of this large-scale public EV charging
programme across the County.
It was
agreed between OCC and OxCity at this point that no further public EV
infrastructure would be installed on the Highway by OxCity, and that this would
instead be delivered by OCC under their own chargepoint operator contracts, as
was always in the intention in the long-term.
As a result
of this decision around changing responsibilities, it was decided that:
-
a)
OCC – via their chosen chargepoint operator - would adopt and be responsible
for the existing on-street infrastructure that had been delivery by OxCity in
the GULO P1 project
-
B)
OxCity would transfer the remaining £402,000 of unspent GULO funding to OCC
along with the responsibility for delivering the remaining 140 on-street EV
charging sockets required to complete the GULO P2 project (to which Ox City
insist on continuing to be responsible for to the funders at the Department of
Transport).
-
c)
In order to repay Ox City for their investment to date, OCC would pass to Ox
City up to £451,000 from the income generated by the whole GULO charging estate
over the next 15 years
A
legally-binding GULO agreement has been drawn up to reflect the above
responsibilities and financial and practical arrangements relating to the above
decision.
The reasons
for this decision are to allow the most effective delivery and management of
public EV charging estate on the Highway in both the short and long term.
The
alternative option would have been to allow OxCity to continue to own and
operate public EV charging infrastructure on the Highway and to continue to
deliver the remaining 140 GULO P2 chargers on the Highway under the previous
agreement.
This would
have made the estate difficult to manage and would have led to further delays
in the new infrastructure being delivered, and in the existing infrastructure
being updated and replaced. It would
also lead to continued uncertainly from public perspective about where the
responsibility for EV infrastructure on the Highway sits between OCC and
OxCity.
Publication date: 04/03/2026
Date of decision: 27/02/2026