Decision Maker: Director of Environment & Highways
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The
agreement will allow the construction of the HIF1 DSB (including A4130) scheme
to commence.
The procurement process is complete, and the contractor (Volker Fitzpatrick Ltd.) was successful. Construction of the Didcot Science Bridge scheme needs to be commenced.
The
alternative would be to not permit the contract to be completed. This would mean construction would not be
able to commence, putting the HIF1 programme at risk.
Publication date: 03/02/2026
Date of decision: 16/12/2025