Return
to Items for Decision
Division(s):
Banbury (Easington, Neithrop, Ruscote and Hardwick)
|
ITEM CMDT3
CABINET
MEMBER FOR TRANSPORT – 14 SEPTEMBER 2006
BANBURY
WESTERN CORRIDOR STUDY
Report by
Head of Transport
Introduction
- On 14 September
2004 Jacobs Babtie was commissioned by Oxfordshire County Council to
produce a route strategy for the Banbury Western Corridor, commencing
on the A422 Ruscote Avenue at the junction with the A361 Southam Road
and concluding at the junction with the A361 Bloxham Road.
- This resulted
in the development of the Banbury Western Corridor Study which sets
out the existing situation and problems and considers the traffic management
improvements and proposals that could be implemented within the confines
of the existing carriageway space.
Background
- The study was
commissioned to produce a package of measures that would enable the
objectives of the Local Transport Plan (LTP) and the Banbury Integrated
Transport and Land Use Strategy (BITLUS) to be delivered, whilst also
taking into account other policies that would influence the corridor’s
future transport programmes and objectives such as those contained with
the Oxfordshire Structure Plan and the Non-Statutory Cherwell District
Local Plan.
- A copy of the
Banbury Western Corridor Study is available in the Members’ Resource
Centre. A number of smaller scale schemes are already proceeding through
design and implementation processes. The schemes that remain to be implemented
are identified at Annex 1 (download
as .doc file) and a map identifying locations will be available
at the meeting. These include some further assessment of the larger
scale proposals and the remaining improvements to footways and cycleways.
Progress So Far
- Because the study
was completed in May 2005 it was not fully agreed to in its complete
form until the next meeting of the BITLUS Members Steering Group in
January 2006. Progress made towards implementation of schemes in the
first year (‘05/06) was in full cooperation with Banbury TAC and some
schemes in their initial stages were refined through the TAC process,
for example, how to control parking or protect bus stops.
- During that period
the study and subsequent officer/Jacobs discussion has looked at four
larger improvement proposals:
- Ruscote Avenue
and the Tesco Roundabout
- Warwick Road
Roundabouts and Cromwell Avenue
- Roundabout Solution
at Queensway / Bloxham Road
- Reposition gaps
in central reserve on Queensway
- The Ruscote Avenue
/ Tesco roundabout has been looked at alongside a right turn ban proposal
for Beaumont Road (see below). Consultation has been undertaken and
a separate report will be produced for the November Transport Delegated
Decisions meeting.
- The Warwick Road/Cromwell
Avenue scheme has not proved feasible in value for money terms. The
TAC members have been fully involved in this judgement.
- The scheme on
Bloxham Road has been taken forward in greater detail but the design
is currently being scrutinised for cost savings in advance of a full
project appraisal.
- The repositioning
of the gaps in the central reserve on Queensway would be at Mascord
Road and Bretch Hill. These have been discussed at TAC, but given the
costs of over £150,000 the scheme has so far been deferred to enable
smaller already identified improvements to proceed first.
- The most substantial
of the smaller measures, which have either been carried out or are at
the preparation stage, concern improved pedestrian movements between
the northern area such as Bretch Hill and the schools further south
including Easington and control of speed in the corridor. Further work
has been undertaken on a number of elements contained within the package.
The existing position is:
Schemes
completed:
- Broughton Road
Pedestrian Refuge (05/06)
- Queensway Primary
School Pedestrian Routes Improvement (06/07)
- Bloxham Road
Pedestrian Refuge (06/07)
Still
to do (imminent) with no further consultation issues:
- Orchard Way Zebra
Crossing
- VAS speed information
signs
Still
to be completed with consultation and TRO aspects outstanding:
- Protection of
the bus stop at Bretch Hill corner
- Beaumont Road
right turn ban into Ruscote Avenue
- Regularised
parking along the corridor
- Broughton Road
Zebra
- Informal consultation
has been completed for the Beaumont Road right turn ban which is an
accident reduction proposal. Informal consultation with regards to Bretch
Hill Corner no waiting and parking bays should be completed in time
for the meeting and any issues will be reported orally. With regard
to the extension of regularised parking bays and protection of the central
reserve informal consultation may not have been completed in time for
the meeting.
Corporate Policies and
Priorities
- This corridor
study all works towards making the north-western side of Banbury a "special
place in which to work and live" by making access, in particular to
workplaces and schools, more efficient and effective. Officers have
been working closely with the local TAC to take on-board local views
and have been open with them about the funding position and prioritisation
that therefore needs to be made. We have been maximizing value by implementing
the "smaller" schemes quickly as they have an immediate effect and benefit
to the public. Our value for money considerations have resulted in the
decision to drop one of the major schemes being considered.
Financial and Staff Implications
- The LTP assessment
framework identified the congestion problems on part of this corridor
as a medium priority and a limited amount of Single Capital Expenditure
(SCE) was allocated to it in 2006/07 and 2007/08. Further funding will
be sought through developer funding.
- The time required
to implement the measures contained within the study, negotiate with
developers and procure any additional funding would be met largely from
existing staff resources and supplemented where required by our Term
Consultants.
RECOMMENDATION
- The Cabinet
Member is RECOMMENDED to:
- confirm
that the Banbury Western Corridor Study forms part of the Banbury
Integrated Transport and Land Use Study; and Annex 1 (download
as .doc file)
to this report as and when finance permits.
STEVE HOWELL
Head of Transport
Background papers:
Banbury Western Corridor Study
Contact Officer:
Suzanne Roberts Tel: 01865 815582
September 2006
Return to TOP
|