Meeting documents

Delegated Decisions by Cabinet Member for Transport
Thursday, 14 September 2006

XT140906-02

Return to Items for Decision

Division(s): Brightwell-cum-Stowell, Warborough, Benson

ITEM CMDT2

CABINET MEMBER FOR TRANSPORT – 14 SEPTEMBER 2006

SHILLINGFORD BRIDGE SIGNALISATION

Report by Head of Transport

(Statement of Decision)

Introduction

  1. This report is concerned with the introduction of single-lane traffic control across Shillingford Bridge, which is required because the bridge is inherently weak at the edges. Annex 1 sets out the detail of the bridge problems, proposed solution and longer-term measures. The plan at Annex 2 (download as .doc file) details the proposals.
  2. Public consultation

  3. Because this bridge maintenance scheme involves introduction of traffic lights the County Council consulted with residents and local businesses in the immediate area of the bridge (between 22 June and 31 July) in order to address as many concerns as practical with the proposed scheme.
  4. Consultation was undertaken 142 residents, Thames Valley Police Traffic Management, Oxford Ambulance Services, local Parish Councils, South Oxfordshire District Council, Area Engineer, Thames Travel, Cyclists Touring Club, Road Haulage Association and County Councillors David Robertson and Tony Crabbe.
  5. 31 replies were received (14 letters, 7 e-mails and 10 telephone enquiries) Ffour of these fully supported the proposed scheme raising. The remaining 27 enquiries raised 41 different questions and concerns and these are detailed at Annex 3 with officer comment. Some questions were raised by more than one person.
  6. Shillingford Hill Residents Association and Benson, Brightwell-Cum-Sotwell and Warborough Parish Councils all supported the proposed scheme but had particular concerns.
  7. Five replies thought the scheme inappropriate.

    1. Three residents thought that the County Council had no right to permanently disrupt and inhibit traffic flow and cause long-term inconvenience to motorists.
    2. A reply from a local business adjacent to the bridge thought that the scheme would have a hugely detrimental effect on their business in visual terms, noise and traffic flow.
    3. The fifth, a local business who gave a telephone response is concerned that the length of the road closure and the timing of the closure could have a detrimental effect on their business. They were also concerned about the safety implications of stationary vehicles on Shillingford Hill.

  8. The County Council is aware that pre-Christmas and the months of January and February are busy periods and in an effort to minimise the impact to the Hotel and Caravan supplier will be having further discussions before finalising the programme of works.
  9. In addition to the concerns of the two businesses, other main concerns related to the combined footpath and cycling, safety, traffic speed, signals and the works programme.
  10. Footpath and Cycling

  11. Pedestrian use is low and the Residents Association and Parish Councils considered that one footpath was more suitable with a separate cycle-way or alternatively a shared footpath/cycle-way more appropriate.

    1. The primary purpose of the footpaths is to direct traffic into the centre of the bridge. A secondary but intended benefit is to provide safer use of the bridge by pedestrians.
    2. The footpaths ensure that vehicles are restricted to the centre of the bridge, which reduces loading on weak edges and keeps them away from inadequate parapets.
    3. The main reason for not including cycle-ways on the bridge is that parapets are lower than the minimum recommended 1.4m height required for bridge parapets adjacent to cycle-ways. In places, the parapet is less than one metre.

Safety and Speed

  1. Residents and Councillors expressed concern regarding access from properties and stationary vehicles on Shillingford Hill. In particular, the measures being under taken to prevent vehicles travelling north bound towards Shillingford from skidding when approaching traffic queues on the hill.
  2. Residents are also concerned about the speed of vehicles in the area. Traffic speed measured in November 2005 produced peak averages over a 5 day period. Easterly 32.5 to 33.5mph ; westerly 30 to 33.5mph; southerly 38.9 to 56.8mph and northerly 47.1 to 48.5mph.
  3. Since November 2000, there have been four accidents. Three of these accidents were on Shillingford Hill where traffic speeds have measured a maximum of 33.5mph. In three of the accidents, there were slight injuries. In one accident, the driver received fatal injuries. In that incident, the driver was not wearing his seatbelt.
  4. We will be taking speed measurements in September 2006 (after the school summer holidays) and then six months after the signals are installed. This will enable the effects of the scheme on traffic speed to be measured. Up to date accident data will also be considered.
  5. Brightwell-cum-Sotwell Parish Council were concerned about safe access from the hotel area and the road access to North Farm. Related questions and answers are provided at Annex 3.
  6. Measures to prevent vehicles from skidding when approaching traffic queues on the Shillingford Hill and to meet concerns regarding speed will be met through the introduction of ‘soft traffic calming’ in the form of 30mph road markings (roundels), slow signs, signals warning signs, temporary "new traffic signals ahead" signs combined with introduction of new high friction surfacing (anti-skid).
  7. The safety concerns about access to and from residential properties at the northern end of the bridge have been addressed.
  8. Traffic Signals

  9. In the main signal related questions related to their configuration and operation. A significant question related to the position of the traffic lights on the south side of the bridge.

    1. Simpler two-phase shuttle working with signals positioned adjacent to either end of the bridge were found not to be practical following swept path analysis for HGV movements. It was consequently determined that a 3-way system incorporating the Hotel entrance as an additional phase was the only practical option.
    2. Traffic lights positioned at the top of the hill would not conform to required safety standards due to the inter-green period being 57 seconds. Traffic queues would be 90 metres or more. Full details of the reasons for the unsuitability of this option are contained in the ‘Signals’ section at Annex 3 (download as .doc file).

    The Works Programme

  10. The intended eight-week closure of Shillingford Bridge is causing particular concern to two local businesses. The proposed programme of works was set by the contractor who is a very experienced highway contractor. The County Council has examined the programme and supports it but subject to agreement with the contractor it may be possible to secure a reduction.
  11. Prior to commencement of any construction work consultation will be undertaken with affected businesses in order to minimise any detrimental effect of the works.
  12. Thames Travel have been asked to ensure continuation of bus services although some changes to timetables are likely to occur.
  13. Initially it was envisaged that signalisation and construction of the footway would be carried out together. This has proved impractical because of the delay in obtaining listed building consent, which is required for construction of the footways but not for the proposed signalisation. Hence, two stages of work are required to enable completion of the programmed work in this financial year.
  14. Stage 1 is the re-surfacing of Shillingford Hill in mid October 2006. The installation of traffic signals is planned to commence in either November 2006 or January 2007 and will take six weeks. Road closures will be minimal. This later portion of work is subject to the signing of an agreement for placing one on the traffic signals heads on private land.
  15. Stage 2 involves removal of the bridge road surface, repairs to the concrete slab, waterproofing, laying ducting for permanent signal cabling and provision of new footpaths before resurfacing. A maximum of an eight-week road closure is required to carry out this work and the likely earliest start date for this work will be January 2007.
  16. A third stage being planned is an extensive stonework repair scheme, which requires separate listed building consent and other approvals. This would be carried out predominately from below the bridge, once the new waterproofing had allowed the stonework to dry out and therefore should not have a significant impact on road users.
  17. Listed Building Consent (Application S.15/06)

  18. English Heritage has advised that they support the measures in principle, which will assist in protecting the Grade II listed bridge and welcome the use of natural stone and granite for the footways.
  19. English Heritage has asked for some minor amendments to the proposed tactile paving. They have stated that the bridge should remain uncluttered and suggested that the traffic lights be located more discreetly. These points are being discussed with the scheme designers.
  20. After the consultation period, but within the consultation period for Listed Building Consent Brightwell-cum-Sotwell Parish Council and Warborough Parish Council made a formal objection to the listed building consent. Their questions with officer response are set out at Annex 3 (download as .doc file).
  21. The listed building consent requires approval by the Secretary of State and the timescale for this is uncertain.
  22. How the Project Supports LTP2 Objectives

  23. Cabinet funding for structural maintenance of road and bridges is allocated through the Local Transport Plan (LTP) to keep the network available for use and to preserve this asset for the future.
  24. This scheme and future planned work fulfils both objectives of the LTP funding.
  25. Financial Implications (including Revenue)

  26. The approved budget, previous expenditure and predicted expenditure are set out in the table below. Funding is Supported Capital Expenditure.
  27.  

    Previous years

    2006-07

    2007-08

    Total

    Budget

    £53K

    £250k

    £10k

    £313k

    Expenditure

    £53K

    £380k

    £30k

    £463k

  28. Increased costs are has detailed:
  29. Details

    Costs

    The costs of the bridge stonework assessment is higher

    £35k

    The original design stipulated re-constituted stone whereas natural stone paving and granite are required.

    £20k

    Additional traffic signals on the adjacent side road and legal fees associated with the location of these.

    £10k

    Repairs to the existing road surface and additional high friction road surfacing to mitigate accidents

    £22k

    Traffic management and interim scheme additions

    £14k

    Additional interim design fees, safety audit and works supervision fees.

    £20k

    Works contingency.

    £29K

    Total

    £150k

  30. This additional budget requirement will be found from within this years bridge maintenance allocation of £1.893K or from a funding re-allocation within the E&E Capital Programme Review in either September or November 2006.
  31. These costs do not include stage three repairs to the bridge stonework. This will be funded separately from within future bridge maintenance funding.
  32. RECOMMENDATIONS

  33. The Cabinet Member is RECOMMENDED to:
          1. approve stage one of the works programme for carriageway repairs on Shillingford Hill and introduction of signalisation for single-way traffic control on the bridge; and
          2. subject to listed building consent approve stage two of the works programme for bridge waterproofing and footpath installation.

STEVE HOWELL
Head of Transport

Background papers: Consultation documentation

Contact Officer: Gary Critchlow-Smith, Tel 01865 815817

September 2006


Return to TOP